GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4357
TO BE ANSWERED ON 18.03.2026
RAILWAY PROJECTS IN MAHARASHTRA AND MADHYA PRADESH
†4357. SHRI NILESH DNYANDEV LANKE:
SHRI GYANESHWAR PATIL:
Will the Minister of RAILWAYS be pleased to state:
(a) whether several railway projects are pending in Maharashtra and
Madhya Pradesh;
(b) if so, the details thereof including such railway projects where work is
yet to be commenced and those pending for completion including their
current status and timeline fixed for their completion;
(c) the details of the budgetary provisions made in respect of railway
projects which have formally sanctioned but are yet to be started and
those projects which are currently ongoing; and
(d) the project and year-wise details of the actual expenditure incurred on
these projects?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): The status of projects sanctioned in Maharashtra and Madhya
Pradesh are as under:
Maharashtra
Railway Budget:
Budget allocation during the last five years has increased significantly.
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Maharashtra is as under:
..P/2
§-:2:-
Period Outlay
2009-14 ₹1,171 crore/year
2025-26 ₹23,778 crore (More than 20 times)
Track construction:
The details of constructing new track falling fully/partly in the State of
Maharashtra during 2009-14 and 2014-25 is as under:
Period New track
Average commissioning of new tracks
Commissioned
2009-14 292 Km 58.4 Km/year
2014-25 2,292 Km 208.4 Km/year (More than 3 times)
Projects sanctioned:
As on 01.04.2025, 38 projects (11 New Lines, 02 Gauge Conversion and 25
Doubling), of a total length of 5,098 km, costing ₹89,780 crore, falling
fully/partly in Maharashtra, are sanctioned. The summary is as under:-
Category No. of Total Length Exp.
sanctioned Length Commissioned upto Mar'25
Projects (in Km) Upto Mar'25 (Km) (₹ in Cr.)
New Line 11 1,355 234 10,504
Gauge Conversion 02 609 334 4,286
Doubling/ 25 3,134 1,792 24,617
Multitracking
Total 38 5,098 2,360 39,407
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in
Maharashtra are as under:
..P/3-:3:-
S. No. Project Cost
(₹ in crore)
1 Pune-Miraj-Londa Doubling (467 Km) 4,670
2 Jabalpur-Gondia Gauge Conversion (300 Km) 2,005
3 Chhindwara-Nagpur Gauge Conversion (150 Km) 1,512
4 Panvel-Pen Doubling (35 Km) 263
5 Pen-Roha Doubling (40 Km) 330
6 Udhna-Jalgaon Doubling (307 Km) 2,448
7 Mudkhed-Parbhani Doubling (81 Km) 673
8 Bhusawal-Jalgaon 3rd Line (24 Km) 325
9 Jalgaon-Bhusawal 4th Line (24 Km) 261
10 Daund-Gulbarga Doubling (225 Km) 3,182
Ongoing projects:
To further improve the Railway Infrastructure in the state of Maharashtra,
following works have been taken up:-
S. No. Name of the project Cost (₹ In
crore)
1 Ahilyanagar (Ahmednagar)-Beed-Parli Vaijnath 4,957
New Line (261 Km)
2 Baramati-Lonand New Line (64 Km) 1,844
3 Wardha-Nanded New Line (284 Km) 3,445
4 Indore-Manmad New Line (360 Km) 18,529
5 Wadsa-Gadchiroli New Line (52 Km) 1,886
6 Jalna-Jalgaon New Line (174 Km) 5,804
..P/4-:4:-
S. No. Name of the project Cost (₹ In
crore)
7 Daund-Manmad Doubling (236 Km) 3,037
8 Kalyan-Kasara 3rd Line (68 Km) 1,433
9 Wardha-Nagpur 3rd Line (76 Km) 698
10 Wardha-Ballarshah 3rd Line (132 Km) 1,385
11 Itarsi-Nagpur 3rd Line (280 Km) 2,450
12 Rajnandgaon-Nagpur 3rd Line (228 Km) 3,545
13 Wardha-Nagpur 4th Line (79 Km) 1,137
14 Jalgaon-Manmad 4th Line (160 Km) 2,574
15 Bhusawal-Khandwa 3rd & 4th Line (131 Km) 3,285
16 Solapur-Tuljapur-Osmanabad New Line (95 Km) 2,933
17 Panvel-Chowk Double Line (17 Km) 491
18 Wardha-Balharshah 4th Line (135 Km) 2,226
19 Itarsi-Nagpur 4th Line (297 Km) 5,010
20 Wardha-Bhusawal 3rd & 4th Line (314 Km) 9,197
21 Asangaon-Kasara 4th Line (35 Km) 794
22 Badlapur-Karjat 3rd & 4th Line (32 Km) 1,324
23 Gondia-Dongargarh 4th Line (84 Km) 2,223
24 Gondia-Balharshah Doubling (240 Km) 4,819
Increasing train handling capacity in Mumbai area:
Presently, about 120 originating Mail/Express trains and about 3,200 sub
urban trains are handled daily in Mumbai area. To increase train handling
capacity at various stations in Mumbai area, following works have been
completed/taken up/planned at various stations:
..P/5-:5:-
SN Location Details
1 Bandra Terminus 3 Pit Lines have been completed
2 Mumbai Central Platform extension for 24 LHB coaches
3 Jogeshwari 2 additional platforms
4 Dadar 1 additional platform
5 Vasai road 6 platforms, 3 pit lines and 5 stabling lines
6 Panvel-Kalamboli 5 platforms , 4 pit lines and 2 sick lines
7 Kalyan 6 platforms and 4 pit lines
8 LTT 4 platforms and 2 pit lines
9 Parel 6 platforms, 5 pit lines, 6 stabling lines
10 Virar 25 stabling lines
11 Dahanu road 11 stabling lines
12 Mira road 25 stabling lines
In addition to above, Platform extension work at 34 stations to
accommodate 15 car EMUs have been taken up.
New projects for increasing capacity:
To improve the capacity of rail network in Mumbai suburban area, Mumbai
Urban Transport Project (MUTP)-II costing ₹8,087 crore, MUTP-III costing
₹10,947 crore and MUTP-IIIA costing ₹33,690 crore have been sanctioned.
These projects include following works in Mumbai Suburban Area:
SN Name of Project Cost
(in Cr.)
CSMT-Kurla 5th & 6th Line (MUTP-II) (17.5 km) 891
1
2 Mumbai Central-Borivali 6th Line (MUTP-II) (30 km) 919
..P/6-:6:-
SN Name of Project Cost
(in Cr.)
Extension of Harbour Line from Goregaon-Borivali
3 826
(MUTP-IIIA) (7 km)
4 Borivali-Virar 5th & 6th Line (MUTP-IIIA) (26 km) 2,184
5 Virar-Dahanu Road 3rd & 4th Line (MUTP-III) (64 km) 3,587
6 Panvel-Karjat Suburban Corridor (MUTP-III) (29.6 km) 2,782
Airoli-Kalwa (elevated) Suburban Corridor link
7 476
(MUTP-III) (3.3 km)
8 Kalyan-Asangaon 4thLine (MUTP-IIIA) (32 km) 1,759
9 Kalyan-Badlapur 3rd& 4th line (MUTP-IIIA) (14 km) 1,510
10 Kalyan-Kasara 3rd Line (67 km) 793
11 Naigaon-Juichandra double chord Line (6 km) 176
12 Nilaje-Kopar double chord Line (5 km) 338
13 Kalyan Yard remodeling work 866
New generation trains:
To enhance passenger carrying capacity, 238 rakes of 12 cars each with
doors have been sanctioned under MUTP-III & IIIA at a cost of ₹19,293
crore. The process for procurement of these rakes has been taken up.
Capacity Augmentation works for Pune Area:
Presently, about 33 originating Mail/Express trains are handled daily in
Pune area.
To increase train handling capacity at various stations in Pune area,
following works have been completed/taken up/planned at various
stations:
..P/7-:7:-
SN Location Details
1 Pune Junction 6 additional Platforms and Extension of 5
Platforms.
2 Hadapsar Extension of 3 Platforms to handle full
length trains.
3 Khadki Raising and Extension of PF-3/4 and
extension of running lines completed in
July’2025.
4 Alandi New Coaching Terminal with 9 additional
Platforms, 8 pit lines and 8 stabling lines
5 Phursungi 5 Stabling Lines at Phursungi
In addition to above, following capacity additional works have been
undertaken in Pune Area to increase the train handling capacity:
SN Name of Project
1 3rd Line between Hadapsar and Ghorpuri Yard
2 New Block station at Manjari Bhadrukin Pune-Daund Section and
Ramtekdi in Pune-Sasvad section
3 Bidirectional Signalling in Pune Sasvad Road Section
Bullet Train project:
The Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is the
only HSR Project under execution. The Project is passing through the
States of Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli
with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora,
Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
..P/8-:8:-
Entire land (1,389.5 Ha.) for MAHSR project has been acquired. All
Statutory Clearances have been obtained. All 1651 utilities have been
shifted. The delay in land acquisition in the State of Maharashtra has
impacted the project till 2021. The land acquisition picked up in 2022 in
Maharashtra.
The progress of various major items so far is as under:
Gujarat (352 KM):
Item Progress
Foundation 352 kms.
Piers 352 kms.
Girder Casting 342 kms.
Girder Launching 331 kms.
Track Bed Construction 152 kms.
OHE Masts Erection 121 kms.
Maharashtra (156KM):
Item Progress
Foundation 84 kms.
Piers 75 kms.
Girder Casting 12 kms.
Girder Launching 5 kms.
Out of total 12 stations, foundation works has been completed at 8 stations
(Vapi, Bilimora, Surat, Bharuch, Anand, Vadodara, Ahmedabad, and
Sabarmati). In Maharashtra section, foundation work is in progress at 3
stations (Thane, Virar, Boisar) and excavation work at BKC station is near
completion and Casting of base slab started.
..P/9-:9:-
17 river bridges have been completed. Work is in advance stage for 4 major
river bridges (Narmada, Mahi, Tapti and Sabarmati) in Gujarat & in progress
in 4 river bridges in Maharashtra. Work on Depots (Thane, Surat and
Sabarmati) is in full swing.
Civil works at Bandra Kurla Complex (BKC) are progressing satisfactorily.
Excavation works have achieved about 91% progress, and concreting
works are at various stages, with 100% completion of the basement slab at
Level-4. The work of the under-sea tunnel (approximately 21 km) has
commenced, out of which 4.8 km of tunnel between Ghansoli and Shilphata
in Maharashtra has been completed.
To ensure seamless passenger connectivity, the Government has planned
multi-modal integration of Bullet Train stations with the existing Mumbai
suburban railway network and upcoming metro lines. The integration
includes passenger connectivity with Metro Line-2B and Metro Line-3
through convenient pedestrian access at BKC station.
Bullet train project is a very complex and technology intensive Project.
Exact timelines for the completion of the project can be reasonably
ascertained after the completion of all associated works of Civil
Structures, Track, Electrical, Signaling & Telecommunication and supply of
Trainsets.
Dedicated freight corridor:
Western DFC also passes through Maharashtra. About 178 route Km of
western DFC is situated in Maharashtra which is about 12% of overall route
..P/10-:10:-
length of western DFC. 76 Km of this project from New Gholvad to New
Vaitarna in Maharashtra has already been commissioned. Balance works
have been taken up. Connectivity of WDFC to JNPT will boost the capacity to
handle cargo and container traffic from port to Delhi NCR.
Madhya Pradesh
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for Infrastructure projects and safety works, falling fully/partly in
the State of Madhya Pradesh is as under:
Period Outlay
2009-14 ₹632 crore/year
2025-26 ₹14,745 crore (More than 23 times)
Track construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Madhya Pradesh during 2009-14 and 2014-25 is as under:
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 145 Km 29 Km/year
2014-25 2,651 Km 241 Km/year (More than 8 times)
Projects sanctioned:
As on 01.04.2025, 24 Railway projects (08 New Lines, 02 Gauge Conversion
and 14 Doubling), of total length of 4,740 Km costing ₹89,542 crore falling
..P/11-:11:-
fully/partly in the State of Madhya Pradesh are sanctioned. The summary is
as under:
Category No. of Total Length Total Exp upto
projects Length Commissioned Mar'25
(in Km) (in Km) (₹ in Cr)
New Lines 8 1,914 544 15,069
Gauge
2 809 430 6,766
Conversion
Doubling /
14 2,017 1,118 19,566
Multitracking
Total 24 4,740 2,093 41,401
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the
State of Madhya Pradesh are as under:
S.No. Name of Project Latest Cost
(₹ in Crores)
1. Anuppur-Katni 3rd line (165 Km) 2,311
2. Pendra Road-Anuppur 3rd line (50 Km) 394
3. Khodri-Anuppur Doubling with flyover at Bilaspur (72 792
Km)
4. Bhopal-Bina 3rd line (145 km) 1,075
5. Bina-Kota Doubling (283 km) 2,477
6. Jabalpur-Gondia Gauge Conversion including 2,005
Balaghat-Katangi (300 Km)
7. Chhindwara-Nagpur Gauge Conversion (150 Km) 1,512
8. Chhindwara-Mandla Fort Gauge Conversion (182 Km) 1,268
..P/12-:12:-
S.No. Name of Project Latest Cost
(₹ in Crores)
9. Ghat Pindari-Balkheda Doubling (6 Km) 29
10. Guna-Ruthiyai Doubling (20 Km) 175
11. Jukhei Chord line, Bye Passing the Katni Yard (2 Km) 12
12. Sontalai-Bagratawa Doubling (7 Km) 110
13. Itarsi-Budhni 3rd line (25 Km) 286
14. Teegaon-Chichonda Ghat Section 3rd line (17 Km) 176
15. Barkhera-Bhopal 3rd line (41 km) 473
16. Nagda-Ujjain Doubling of Gambhir Bridge (2 Km) 28
17. Nimach-Chittaurgarh Doubling (56 Km) 560
18. Budhni-Barkhera 3rd line (27 Km) 1,703
19. Indore-Dewas-Ujjain Doubling (79 Km) 757
20. Powerkheda-Jujharpur Rail flyover (16 Km) 443
21. Guna- Etawah New Line (348 Km) 683
22. Ramna-Singrauli doubling (160 Km) 2,436
23. Karaila Road- ShaktinagarDoubling(32 Km) 763
24. Malkhedi-Mahadeokhedi Doubling (12 Km) 59
Ongoing projects:
Some of the projects falling fully/partly in the State of Madhya Pradesh
which have been taken up are as under:
S. No Project Cost
(₹ in Crores)
1. Shahdol-Singhpur 4th Line (6 Km) (passing through
54
Shahdol constituency)
2. Katni- Grade separator / Bypass (35 Km) 2,300
..P/13-:13:-
S. No Project Cost
(₹ in Crores)
3. Katni- Singrauli Doubling (257 Km) 4,377
4. Lalitpur-Satna, Rewa-Singrauli&Mahoba-Khajuraho
8,914
New Line (541 Km)
5. Ramganjmandi-Bhopal New Line (277 Km) 5,073
6. Indore-Budni New Line (198 Km) 7,474
7. Nimach-Badi Sadri New Line (48 Km) 495
8. Gwalior-Sheopurkalan Gauge Conversion with
2,913
extension to Kota (284 Km)
9. Itarsi- Nagpur 3rd line (280 Km) 2,450
10. Jhansi-Bina 3rd line (153 Km) 2,002
11. Mathura-Jhansi 3rd line (274 Km) 5,924
12. Jhansi-Kairar-Manikpur&Khirar-Bhimsen Doubling 4,330
(431 Km)
13. Satna-Rewa Doubling (50 Km) 590
14. Ruthiyai Bye Pass line (3 Km) 54
15. Guna Bye Pass line (2 Km) 179
16. Ujjain Fly Over (2 Km) 100
17. Manmad - Indore New Line (360 Km) 18,529
18. Bhusawal-Khandwa 3rd & 4th Line (131 Km) 3,285
19. Dahod-Indore New Line (205 Km) 9,746
20. Nimach-Ratlam Doubling (133 Km) 1,096
21. Chhota Udepur-Dhar New Line (147 Km) 1,794
22. Ratlam-Nagda 3rd and 4th line (41 Km) 964
23. Vadodara-Ratlam 3rd and 4th line (259 Km) 8,387
24. Ratlam-Khandwa Gauge Conversion (299 Km) 7,265
25. Bina-Itarsi 4th Line (237 km) 4,329
26. Itarsi-Nagpur 4th Line (297 Km) 5,010
..P/14-:14:-
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned authorities
for expeditious land acquisition, forestry and Wildlife clearances and
for resolving other issues pertaining to projects.
*****