**Executive Summary**
The document is an answer provided by the Minister of Railways, Information & Broadcasting and Electronics & Information Technology to the Lok Sabha Unstarred Question No. 2037, regarding the status of railway projects in Uttarakhand. The response, dated to be answered on 11.02.2026, details budget allocations, progress on new lines, and progress on the Rishikesh-Karnaprayag rail line project. The document also considers challenges impacting the project completion time and cost.
**Key Points / Main Content**
* **Budget Allocation:**
* The budget allocation for infrastructure projects and safety works in Uttarakhand has increased significantly.
* 2009-14: Rs 187 Crore/year
* 2025-26: Rs 4,641 Crore (nearly 25 times)
* **New Lines:**
* As of 01.04.2025, three new lines covering a total length of 216 km, costing Rs 40,384 crore, have been sanctioned.
* 16 km of the sanctioned length has been commissioned.
* Expenditure of Rs 19,898 crore has been incurred up to March 2025.
* **Rishikesh-Karnaprayag Rail Line Project:**
* A new rail line project (125 km) has been sanctioned to provide rail connectivity to Chardham.
* The alignment passes through multiple districts, providing rail connectivity to religious and tourist spots.
* The project involves the construction of 16 Main line tunnels (104 km) and 12 Escape tunnels (98 km).
* 99 km of main line tunnels and 94 km of escape tunnels have been completed.
* 8 Adits have been identified to expedite tunnel excavation.
* 19 Important/Major Bridges are under construction, with 8 already completed.
* **Section-wise Progress:**
* Details are provided for the progress of tunnels and bridges in various sections of the railway line (Virbhadra-Yog Nagari Rishikesh, Yog Nagari Rishikesh-Shivpuri, Shivpuri-Byasi, Byasi-Devprayag, Devprayag-Janasu, Janasu-Maletha, Maletha-Srinagar, Srinagar-Dhari Devi, Dhari Devi-Tilani, Tilani-Gholtir, Gholtir-Gauchar, Gauchar-Karnprayag).
* **Future Connectivity:**
* A survey has been completed to further extend rail connectivity to Gangotri, Yamunotri, Kedarnath, and Badrinath.
* **Factors Affecting Completion:**
* Land acquisition
* Forest clearance
* Shifting of infringing utilities
* Statutory clearances from various authorities
* Geological and topographical conditions
* Law and order situation
* Number of working months
**Impact Analysis**
**Stakeholder:** Uttarakhand State and its Residents
* **Impact:** Enhanced rail connectivity, increased tourism potential, and economic development in the region.
* **Action Required:** No direct action required, but the state government may need to facilitate land acquisition, clearances, and address law and order issues to ensure the timely completion of the projects.
**Stakeholder:** Ministry of Railways
* **Impact:** Responsible for the execution and completion of the railway projects within budget and timeline.
* **Action Required:** Monitor project progress, address challenges related to land acquisition, clearances, and geological conditions, and ensure coordination with state authorities for smooth project execution.
**Stakeholder:** Pilgrims and Tourists
* **Impact:** Improved access to religious and tourist destinations in Uttarakhand, making travel more convenient and potentially boosting tourism.
* **Action Required:** No direct action required, but may need to plan travel based on project completion timelines and available rail connectivity.
Key Entities Referenced
Ministry of Railways: The primary government body responsible for the planning and execution of railway projects, including those mentioned in the document.
Rishikesh-Karnaprayag railway line: A specific railway line project in Uttarakhand, the extension and status of which is being discussed.
Uttarakhand: The Indian state where the railway projects are located, defining the geographical scope of the inquiry.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2037
TO BE ANSWERED ON 11.02.2026
RAILWAY PROJECTS IN UTTARAKHAND
†2037. SHRI ANIL BALUNI:
SHRI AJAY BHATT:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of rail projects currently under process in Uttarakhand
including the status of each projects till date;
(b) whether any of the project is lagging behind the prescribed timeline;
(c) whether the Government proposes to extend the Rishikesh-
Karanaprayag railway line and if so, the details thereof;
(d) whether any study has been conducted in this regard and if so, the
details thereof; and
(e) the current status of the said railway line along with the details
thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Budget allocation for Infrastructure projects and safety works,
falling fully/ partly in Uttarakhand is as under:
Period Outlay
2009-14 Rs 187 Crore/year
2025-26 Rs 4,641 Crore (nearly 25 times)
As on 01.04.2025, 03 New Lines, covering total length of 216 Km costing
Rs 40,384 crore falling fully/partly in the State of Uttarakhand are
sanctioned, out of which 16 Km length has been commissioned and an
§expenditure of Rs 19,898 crore has been incurred upto March’ 2025. The
summarized details are as under:-
Category No. of Total Length Expenditure upto
projec Length Commissioned March 2025
ts (in Km) (in Km) (Rs in crore)
New 03 216 16
19,898
Lines
To provide rail connectivity to Chardham, Rishikesh-Karnaprayag new rail
line project (125 km) has been sanctioned.
The project alignment passes through Dehradun, Tehri Garhwal, Pauri
Garhwal, Rudrapryag and Chamoli Districts of Uttarakhand and will provide
rail connectivity to Devprayag and Karnaprayag religious and tourist spots
with Rishikesh and National Capital of India.
The alignment of the project predominantly passes through tunnels. The
project involves construction of 16 Main line tunnels of 104 km length and
12 Escape tunnels of about 98 km length. So far, Main line tunnels of 99 km
length and 09 Escape Tunnels of over 94 km length have been completed.
To increase progress of works, 08 Adits in various tunnels were also
identified. These adits created additional work faces of tunnel excavation
expediting early completion of long tunnels. Works of all 8 Adits (5 km)
have also been completed.
The project also involves construction of 19 Important/Major Bridges. 8 out
of 19 Important/Major Bridges have also been completed. Works in balance
bridges have also been taken up.Section wise progress of the project is as under:
S.N. Name of Status of Tunnels Status of Major Bridges
Section
1 Virbhadra- Yog
Nagari Already Completed and Commissioned.
Rishikesh (4.7
Km)
2 Yog Nagari Tunnel (10.8 km) There is 01 Major Bridge in
Rishikesh- 94 % this section, which has been
Shivpuri (13.4 excavation completed
completed
Km)
Lining taken
up
3 Shivpuri-Byasi Tunnel (12.7 km) There are 02 Major Bridge in
(14.3 Km) 01 out of 02 this section. Both have been
tunnels completed.
completed
Excavation of
2nd tunnel
Completed
lining taken
up
4 Byasi- Tunnel (13.3 km) There are 04 Major Bridge in
Devprayag (15 03 out of 04 this section. All 4 bridges
Km) tunnels have been completed.
completed
69%
excavation of
4th tunnel
Completed
lining taken
up
5 Devprayag- Tunnel (14.6 km)
Janasu (14.8 Completed -
Km)
6 Janasu- Tunnel (2.9 km) There is 01 Major Bridge in
Maletha (4.7 Completed this section, which has been
Km) completed7 Maletha- Tunnel (4.1 km)
Srinagar (5.2 Completed -
Km)
8 Srinagar-Dhari Tunnel (9.1 km) There are 03 Major Bridge in
Devi (11.2 Km) Excavation this section. 1 Bridge has been
completed completed and work for other
lining taken
2 Bridges have been taken up.
up
9 Dhari Devi- Tunnel (16.6 km) There is 01 Major Bridge in
Tilani Excavation this section, which has been
(Rudraprayag) completed taken up.
lining taken
(17.6 Km)
up
10 Tilani Tunnel (6.6 km) There are 02 Major Bridge in
(Rudraprayag)- 79% this section. Work for both the
Gholtir (7.6 Excavation Bridges have been taken up.
completed
Km)
11 Gholtir- Tunnel (7.1 km)
Gauchar (7.8 Excavation
Km) completed -
lining taken
up
12 Gauchar- Tunnel (6.3 km) There are 03 Major Bridge in
Karnprayag Excavation this section. Work for all 3
(8.4 Km) completed Bridges have been taken up.
lining taken
up
To further extend the rail connectivity to Gangotri, Yamunotri, Kedarnath
and Badrinath, survey has been completed. However, the project alignment
lies near the main Central thrust of Himalayas which is highly seismically
active.
Completion of Railway project/s depends on various factors which include
the following: Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****