**Executive Summary**
This document details the status of railway projects in West Bengal as of December 17, 2025, answering Unstarred Question No. 2987 in Lok Sabha. It highlights delays due to land acquisition and other issues, particularly those related to the State Government. The document outlines specific projects affected and the extent of delays, land acquisition status, and financial allocations.
**Key Points / Main Content**
* **Land Acquisition and Project Delays:**
* Many railway infrastructure projects in West Bengal, including Purulia, are delayed due to delays in land acquisition.
* Out of 4,564 Ha of land required, 1,250 Ha (27%) has been acquired, leaving 3,314 Ha (73%) still to be acquired.
* Several specific projects are listed with details on total land required, land acquired, balance to be acquired, and amount paid to the state.
* Law and order issues also contribute to delays, particularly in the Tarakeswar - Bishnupur project.
* **Kolkata Metro Projects:**
* Of the 52 km of Kolkata Metro corridors under construction, 20 km are held up due to land acquisition and utility shifting issues.
* Joka-Esplanade work is affected by land issues, with the State Government finally according approval on 09.07.2025 after almost 5 years for land acquisition.
* New Garia - Dum Dum Airport project is facing temporary traffic diversion issues at Chingrighata crossing, with a proposal submitted to the Government of West Bengal in February, 2025.
* New Barrackpore to Barasat work is held up due to land acquisition and encroachment issues.
* Baranagar to Barrackpore work is held up due to pending utility shifting.
* **Financial Allocation and Project Status:**
* Budget allocation for infrastructure projects in West Bengal has increased significantly, with Rs. 13,955 Cr allocated for 2025-26, more than three times the allocation in 2009-14 (Rs. 4,380 Cr/year).
* As of 01.04.2025, 42 projects (12 New Lines, 4 Gauge Conversions, and 26 Doubling) costing Rs. 67,991 crore are sanctioned, with 1702 km commissioned and an expenditure of Rs. 23,410 crore incurred upto March, 2025.
* Details are provided for recently completed projects in West Bengal, along with their costs.
* **Factors Affecting Project Completion:**
* Project sanction depends on traffic projections, connectivity, demands from State Governments, operational requirements, socio-economic considerations, and funds.
* Completion depends on land acquisition, forest clearance, utility shifting, statutory clearances, geological conditions, law and order, and working months.
**Impact Analysis**
**Stakeholder:** Government of West Bengal
* **Impact:** The State Government is identified as a key factor in the delays of railway projects due to land acquisition issues, lack of necessary approvals (NOC), and law and order problems.
* **Action Required:** Expedite land acquisition processes, issue necessary NOCs promptly, address law and order issues affecting project sites, and coordinate effectively with the Ministry of Railways to resolve pending matters.
**Stakeholder:** Ministry of Railways (Government of India)
* **Impact:** The Ministry is responsible for the execution of railway projects but is facing obstacles due to the State Government's actions.
* **Action Required:** Continue efforts to coordinate with the Government of West Bengal, resolve delays through a special coordination mechanism, and potentially explore alternative solutions for land acquisition and project execution.
**Stakeholder:** Commuters/Passengers
* **Impact:** Delays in railway projects are negatively impacting passenger safety, regional connectivity, and overall development in West Bengal.
* **Action Required:** N/A
**Stakeholder:** Project Contractors
* **Impact:** Projects are stalled due to lack of land.
* **Action Required:** N/A
Key Entities Referenced
West Bengal: The Indian state where railway projects are facing delays, often due to land acquisition issues and state government coordination.
Ministry of Railways: The central government ministry responsible for overseeing and executing railway projects, including those in West Bengal.
Railway Projects: Infrastructure projects related to railways, including new lines, doubling, and gauge conversions, specifically those facing delays in West Bengal.
Land Acquisition: The process of acquiring land for railway projects, identified as a major bottleneck in project execution, particularly in West Bengal.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO.2987
TO BE ANSWERED ON 17.12.2025
RAILWAY PROJECTS IN WEST BENGAL
†2987. SHRI JYOTIRMAY SINGH MAHATO :
Will the Minister of RAILWAYS be pleased to state:
(a) whether it is a fact that many important railway projects across West
Bengal, including Purulia, have been pending for years simply due to the
administrative apathy of the State Government, non-issuance of
necessary NOC, non-availability of land and unnecessary delay in various
approvals, while the Central Government has been continuously trying to
push these projects forward and if so, the details thereof;
(b) whether the Government has a detailed list of such projects where
land transfer could not be started and construction work is stalled due to
the inaction of the State Government and if so, the details thereof:
(c) whether the Government proposes fixing accountability of the State
Government or resolving the delays through a special coordination
mechanism to move forward these stalled projects and if so, the details
thereof; and
(d) whether it is a fact that continuous delays on part of the State
Government are seriously affecting passenger safety, regional
connectivity and overall development and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Execution of important infrastructure projects falling
fully/partly in the State of West Bengal including Purulia are held up due
to delay in land acquisition. Status of land acquisition in West Bengal is
as under:
Contd…2/--2-
Total Land required 4,564 Ha
Land Acquired 1,250 Ha (27%)
Balance Land to be acquired 3,314 Ha (73%)
Details of some major projects which are delayed due to land acquisition
are as under:
SN Name of the project Total Land Balance Amount
land acquired Land to Paid to
required (in Ha) be State
(in Ha) acquired (in Cr.)
(in Ha)
1. Chandil- Purulia - 8.15 0 8.15 0
Anara- Burnpur - 3rd
line
2. Nabadwipghat- 106.71 0 106.71 50
Nabadwipdham new
line
3. Byepass at Sainthia 22.28 0 22.28 0
4. Naihati – Ranaghat 13.33 0 13.33 1.3
3rd line
5. Sivok-Rangpo new 134.62 127.54 7.08 7.98
line
6. Kaliyaganj-Buniadpur 167.804 0 167.804 0
new line
7. Canning- Bagankhali 18.36 0 18.36 0
new line
8. Adra- Sanka- Rukni 5.14 0 5.14 0
doubling
Contd…3/--3-
9. Kalipahari- 14.55 0 14.55 0
Bakhtarnagar 5th line
10. Rail Flyover at Anara 34.90 0 34.90 0
from Rukni to Anara
station
11. Rail Flyover at 34.12 0 34.12 0
Gourinathdham end to
Purulia
12. Chandanpur 5 0 5 0
Shaktigarh 4th Line
Further, Tarakeswar - Bishnupur (83 Km) New Line project is held up due
to law and order issues in Goghat-Kamarpukur section falling in Hooghly
district. The work was stopped by local villagers in about 900m length
near Bhabadighi Pond. The work is held up since 2016.
Deshpran -Nandigram (18.5 km) Line was sanctioned in 2009-10 at cost
of ₹ 121.44 crores. The entire Project length is located in East Midnapore
District. The project could not progress due to problems in land
acquisition and was kept in abeyance. In April 2023 it was decided to re-
start the work. However, Survey for Land Acquisition from Deshpran to
5.0 Km could not be completed due to law and order issues. As Deshpran
is the connecting station, acquisition of this land is essential for
commissioning of this project.
Several meetings have been held with officials of Government of West
Bengal for land acquisition for the above projects.
Government of India is geared up to execute projects, however success
depends upon the support of Government of West Bengal.
Contd…4/--4-
Kolkata Metro:
Metro project in Kolkata started in 1972. The details of the Metro
commissioned since then are as under:
Period Metro Commissioned
1972 to 2014 ( 42 years) 28 km
2014 to 2025 ( 11 years) 45 km
Presently, 4 metro corridors of total 52 km are under construction in and
around Kolkata out of which 20 Km is held up due to land acquisition and
utility shifting issues pertaining to State Government. The status of
these corridors is as given below:
(i) Joka–Esplanade (14 km):- Joka-Majerhat (7.74 km) has been
commissioned and balance work from Majerhat to Esplanade (6.62
km) has been taken up. However, progress of the work is affected
due to the following issues:
S.No. Location Issues
1. Khidderpur 1. 837 square meter permanent and 1702 sq.m.
Metro Station temporary land of Kolkata Armed Police
(KAP) was required for utility shifting and
road traffic diversion for which proposal was
sent to State Government on 24.08.2020.
2. Multiple meetings with officials of
Government of West Bengal (GoWB) were
held.
3. State Government finally accorded approval
on 09.07.2025 after almost 5 years.
Contd…5/--5-
2. Dr. B.C. Roy 1. For construction of Esplanade Metro Station,
Market temporary shifting of unauthorised 528
Shops at B.C. Roy Market on Defence land
was required. The proposal for NOC of
temporary shifting of market was submitted
in February, 2022.
2. Shops for temporary shifting were also
constructed.
3. The State Government has been requested
to facilitate shifting. Regular coordination
with PWD is being done also, a meeting was
held with Hon’ble Mayor of Kolkata on
30.07.2025.
4. Issue is pending for more than 3.5 years.
(ii) New Garia - Dum Dum Airport (32 km): New Garia – Belaghata (9.8
km) has been commissioned and balance work from Belaghata to
Dum Dum Airport (22.2 km) has been taken up. However, progress of
the work is affected due to the following issues:
S.No Location Issues
.
1. Chingrighata 1. Temporary traffic diversion at Chingrighata
Crossing crossing for launching of viaduct segments is
(Between required for 3 + 3 nights (8 hours each) on
Beleghata – each side of road alternately. The proposal
Gour Kishore was submitted to Government of West
Ghosh station) Bengal (GoWB) in February, 2025.
Contd…6/--6-
2. The diversion road as desired by Kolkata
traffic police has already been constructed
in February, 2025.
3. Multiple meetings were held with various
State Government and Kolkata police
officials for NOC.
4. The NOC is still awaited even after about 10
months.
(iii) Noapara – Barasat (18 km): Noapara- Jai Hind Airport (6.77 km)
has been commissioned and work from Jai Hind Airport to Michael
Nagar is in progress. However, work from New Barrackpore to
Barasat (7.5 Km) is held up due to land acquisition and
encroachment issues by State authorities.
S.No. Location Issues
1. New 1. Land acquisition (23000 sq. m) and removal
Barrackpore of heavy encroachments (1277 hutments,
to Barasat 764 shops) are involved in this section.
2. The matter is not yet resolved by GoWB.
(iv) Baranagar – Barrackpore - Dakshineshwar (14.5 km): Baranagar –
Dakshineshwar (2 km) has been commissioned and balance work
from Baranagar to Barrackpore (12.5 Km) is held up due to pending
utility shifting in the alignment by state government authorities.
S.No. Location Issues
1. Baranagar to 1. The original alignment along the B.T road
Barrackpore was agreed in 2011 as per MoU between
Metro Railway, RVNL and Kolkata Municipal
Corporation.
Contd…7/--7-
2. As per MoU, existing pipeline was to be
replaced by new 64 inch pipeline by the
State Government.
3. Shifting of 64 inch pipeline was completed
in 2012.
4. Now, the State Government is insisting for
construction of a new 90 inch pipeline
costing about ₹1400 crore.
5. The demand is not covered under the cost of
the project and MoU provisions.
6. NOC is still awaited from GoWB.
West Bengal:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly
in the State of West Bengal is as under:-
Period Outlay
2009-14 Rs.4,380 Cr./year
2025-26 Rs. 13,955 Cr. (More than 3 times)
As on 01.04.2025, 42 projects (12 New Lines, 04 Gauge Conversions and
26 Doubling), of total length of 4402 Km, costing ₹67,991 crore falling
fully/partly in the State of West Bengal are sanctioned, out of which,
1702 km length has been commissioned and an expenditure of ₹23,410
crore has been incurred upto March, 2025. The summary is as under:
Contd…8/--8-
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2025
(in Km) till March, 2025 (Rs. in Cr.)
(in Km)
New Lines 12 1,032 337 11,368
Gauge
Conversio 4 1,201 854 3,673
n
Doubling/
Multi- 26 2,169 511 8,370
tracking
Total 42 4,402 1,702 23,410
Details of some of the recently completed projects falling fully/partly in
the State of West Bengal are as under:
Cost
S. No. Project
(Rs. in Cr.)
1 Rampurhat-Mandarhill new line and Rampurhat- 1,500
Murarai 3rd line (159 Km)
2 Azimganj-Murshidabad new line (7 Km) 164
3 Bardhaman-Katwa Gauge Conversion (52 Km) 696
4 Ahmedpur-Katwa Gauge Conversion (52 Km) 440
5 Panskura Kharagpur Doubling (45 Km) 408
6 Lalgola – Jiaganj Doubling (23 Km) 124
Contd…9/--9-
7 Krishnanagar-Bethuadahari Doubling (28 Km) 152
8 Nabadwipdham-Patuli Doubling (22 Km) 170
9 Bethuadhahari-Plassey Doubling (23 km) 132
10 Ambikakalna-Nabadwipdham Doubling (23 km) 145
11 Nalhati-Sagardighi Doubling (26 km) 193
12 Tamluk Jn.- Basulya Sutahata Doubling (24 km) 245
13 Plassey- Jiaganj Doubling (54 km) 234
14 Azimganj-Manigram Doubling (21 km) 150
15 New Coochbehar-Gumanihat Doubling (29 km) 330
16 New Coochbehar-Samuktala Road Doubling (29 km) 445
17 Sainthia-Tarapith 3rd line (22 Km) 186
18 Ambari Falakata-New Maynaguri Doubling (37 km) 843
19 Bandel-Boinchi - 3rd line (31 km) 546
20 Boinchi-Shaktigarh 3rd line (26 km) 424
21 Bazar Sau-Azimganj Jn. Doubling (42 km) 343
22 Sagardighi- Malda Town Doubling (25 Km) 248
23 Kharagpur-Narayangarh 3rd line (24 km) 270
24 Monigram-Nimtita Doubling (24 Km) 713
25 Purulia-Kotshila Doubling (36 Km) 393
Contd…10/--10-
Some of the projects falling fully/partly in the State of West Bengal which
have been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Chandil-Purulia-Anara-Damodar 3rd Line(121 Km) 1,932
2 Tarakeshwar-Bishnupur New Line (83 Km) 1,542
3 Sivok-Rangpo New Line (44 Km) 11,973
4 Balurghat-Hilli New Line (30 Km) 1,209
5 Kaliyaganj-Buniadpur New Line (33 Km) 1,147
6 Katihar-Kumedpur and Katihar-Mukuria Doubling 943
(65 Km)
7 Kharagpur-Adityapur 3rd line (132 Km) 3,250
8 Narayangarh-Bhadrak 3rd line (153 Km) 2,136
9 Kalipahari-Bakhtarnagar 5th Line (18Km)
350
10 Dankuni-Baltikuri 3rd & 4th line (18 Km) 429
11 Murarai-Barharwa 3rd Line (49 Km) 935
12 Ranaghat-Krishnanagar City 3rd Line (26 Km) 446
13 Aluabari Road-New Jalpaiguri 3rd & 4th Line (57 1,630
Km)
During last three years (i.e. 2022-2023, 2023-24, 2024-25 and current
Financial Year i.e. 2025-26), total 97 Nos. of Surveys (10 New Line, 87
Doubling) falling fully/partly in the State of West Bengal having a total
length of 4,004 Km have been sanctioned.
Contd…11/--11-
Sanction of any railway project depend upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which
include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****