GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4150
TO BE ANSWERED ON 18.03.2026
REDEVELOPMENT OF KOVILPALAYAM RAILWAY STATION
4150. SHRI ESWARASAMY K:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware that the Kovilpalayam railway station
on the Coimbatore-Pollachi line has remained non-functional since the
broad-gauge conversion and if so, the details thereof;
(a) whether any proposal has been received/considered for the
reconstruction of a passenger platform and providing of a stoppage for
the Coimbatore-Pollachi passenger train at Kovilpalayam and if so, the
details thereof;
(c) whether the Government has examined the feasibility of executing such
works under the Station Redevelopment Programme or through
Corporate Social Responsibility (CSR) funds and if so, the details
thereof; and
(d) the estimated cost and timeline for the proposed revival of the
Kovilpalayam station and the steps taken/being taken by the
Government to expedite it?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Kovilpalayam station was earlier existing on Podanur-Pollachi
Meter Gauge section. It was closed during Gauge Conversion of this
section due to low patronage. However, the feasibility of providing a new
station at Kovilpalayam has been taken up.
...2/-
§-2-
Tamil Nadu:-
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹879 crore/year
2025-26 ₹ 6,626 crore (more than 7.5 times)
Project sanctioned:-
As on 01.04.2025, 15 projects (09 new line, 03 gauge conversion and 03
doubling) of 1,700 km length, costing ₹22,808 Crore, falling fully/partly in
the State of Tamil Nadu, are sanctioned. The summary is as under:-
Category No. of Total Length Expenditure
sanctione Length Commissioned upto Mar’ 25
d (in km) upto Mar’25 (₹ in Cr.)
projects (in km)
New Line 9 812 24 1,337
Gauge Conversion 3 748 604 3,471
Doubling 3 140 37 2,783
/Multitracking
Total 15 1,700 665 7,591
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
...3/--3-
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
Tamil Nadu are as under :
S. Cost
Project
N. (₹in Crores)
1 Dindigul-Palani-Pollachi gauge conversion (121 km) 610
2 Pollachi-Palghat gauge conversion (56 km) 350
3 Pollachi-Podhanur gauge conversion (40 km) 400
4 Quilon-Tirunelveli-Tiruchendur gauge conversion (357
1,122
km)
5 Mayiladuturai-Thiruvarur-Karaikkudi gauge
1,338
conversion (187 km)
6 Madurai-Bodiyakannur gauge conversion (90 km) 593
7 Chengalpattu-Villupuram doubling (102 km) 670
8 Tiruvallur-Arakkonam 4th line (27 km) 83
9 Chennai Central-Basin Bridge doubling (2 km) 31
10 Thanjavur-Ponmalai doubling (48 km) 370
11 Villupuram-Dindigul doubling (273 km) 2,000
12 Chennai Beach-Korukkupet 3rd line (5 km) 168
13 Chennai Beach-Attipattu 4th line (22 km) 293
14 Omalur-Metturdam Patch doubling (29 km) 327
15 Chengalpattu - Villupuram and Tambaram-
1,122
Chengalpattu - 3rd line (133 km)
16 Salem-Magnesite Junction-Omalur doubling (11 km) 115
17 Madurai- Maniyachi-Tuticorin doubling (160 km) 1,891
18 Maniyachi-Nagercoil doubling (102 km) 1,752
19 Chennai Beach-Chennai Egmore doubling (4 km) 272
20 Karaikal-Peralam new line (23 km) 373
21 Northern End Port connectivity to Karaikal Port (1 18
km)
...4/--4-
Ongoing Projects:-
Some of the projects falling fully/partly in the State of Tamil Nadu which
have been taken up are as under :
Cost
S.N Project
(₹ in Crores)
1 Tindivanam-Nagari new line (184 km) 3,631
2 Morappur-Dharmapuri new line (36 km) 359
3 Nagapattinam - Tiruturaipundi new line 7 4 2
(43 km)
4 Trivandrum-Kanyakumari doubling (87 km) 3,785
5 Arakkonam yard 3rd & 4th line (6 km) 98
6 Perambur - Ambattur 5th & 6th lines (6 Km) 178
7 Irugur-Podanur doubling (11 Km) 277
8 Tambaram-Chengalpattu 4th Line (30 km) 757
9 Attipattu - Gummidipundi 3rd & 4th line 3 7 5
(23 km)
10 Tirupati - Pakala - Katpadi doubling (105 km) 1,332
11 Tindivanam-Gingee-Tiruvannamalai New Line 1,400
(71 Km)
12 Atipattu – Puttur New Line (88 Km) 1,700
13 Chennai – Cuddulore via Mahabalipuram New 2,670
Line (179 Km)
Execution of important infrastructure projects falling fully/partly in the
State of Tamil Nadu are held up due to delay in land acquisition. Status of
land acquisition in Tamil Nadu is as under:
Total Land required for Projects in 4,326 ha
Tamil Nadu
Land Acquired 1,052 ha (24%)
Balance Land to be acquired 3,274 ha (76%)
Support of the Government of Tamil Nadu is needed to expedite the land
acquisition.
...5/--5-
Details of some major projects which are delayed due to land acquisition
are as under:-
SN Name of the project Total Land Balance
land acquired Land to
required (in ha) be
(in ha) acquired
(in ha)
1. Tindivanam - Tiruvannamalai 276 33 243
new line (71 km)
2. Attiputtu - Puttur new line 1 8 9 0 189
(88 km)
3. Morappur-Dharmapuri new line 92 45 47
(36 km)
4. Mannargudi-Pattukkottai new 196 0 196
line (41 km)
5. Thanjavur-Pattukottai new line 152 0 152
(52 km)
Further, Rameshwaram – Dhanushkodi new line (18 km) was sanctioned at
a cost of ₹734 Cr. The Foundation Stone of the project was laid on
01.03.2019. However, the project could not be started because the land
acquisition has not been undertaken by the State Govt. of Tamil Nadu.
Government of India is geared up to execute projects, however success
depends upon the support of Government of Tamil Nadu.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
...6/--6-
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****