**Executive Summary**
This document is the answer provided by the Minister of Railways, Information & Broadcasting and Electronics & Information Technology to the Lok Sabha Unstarred Question No. 873, regarding the redevelopment of railway stations in Maharashtra and Madhya Pradesh under the Amrit Bharat Station Scheme, to be answered on 04.02.2026. It outlines the progress and plans for station upgrades in both states, focusing on completed works, ongoing projects, and future provisions. No specific completion timeline is provided due to the complexity of the project and several variables.
**Key Points / Main Content**
* **Amrit Bharat Station Scheme Overview:**
* Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach
* Scheme involves preparation of master plans and their implementation in phases to improve stations.
* 1337 stations have been identified for redevelopment: 80 in Madhya Pradesh and 132 in Maharashtra.
* **Redevelopment Focus:**
* Improvement of access to stations and circulating areas
* Integration of station with both sides of city
* Improvement of station building
* Improvement of waiting halls, toilets, sitting arrangement, and water booths.
* Provision of wider foot over bridges/air concourses.
* Provision of lifts/escalators/ramps
* Improvement/Provision of platform surface and cover over platforms
* Provision of kiosks for local products.
* Parking areas and Multimodal integration
* Amenities for Divyangjans.
* Better passenger information systems
* Provision of executive lounges, nominated spaces for business meetings, landscaping, etc.
* Scheme envisages sustainable and environment-friendly solutions.
* **Financial Allocation:**
* The development is generally funded under Plan Head-53 ‘Customer Amenities'.
* Madhya Pradesh and Maharashtra fall under multiple zonal railway jurisdictions.
* Total allocation of ₹5800.68 crores (Revised Estimate) for financial year 2025-26 under Plan Head-53 across the relevant zones.
* **Maharashtra:**
* Works of 17 stations including 5 suburban stations have been completed under the scheme.
* Includes, Amgaon, Chanda Fort, Chinchpokli, Devlali, Dhule, Kedgaon, Lasalgaon, Lonand Junction, Matunga, Murtizapur Junction, Netaji Subhash Chandra Bose Itwari Junction, Parel, Savda, Shahad, Vadala Road, Baramati and Nandura.
* Specific ongoing works at Chhatrapati Shivaji Maharaj Terminus, Diva, Mumbra, Titwala, Vikhroli, Charni Road, Malad, Kalyan, Dadar, Thane, and Pune stations are detailed.
* **Madhya Pradesh:**
* Works of 14 stations have been completed under the scheme.
* Includes, Beohari, Bhind, Harpalpur, Junnor Deo, Katni South, MCS Chhatarpur, Nainpur Jn., Narmadapuram, Orchha, Sanchi, Seoni, Shajapur, Shridham and Vidisha.
* Specific ongoing works at Balaghat, Rewa, Ruthiyai, and Ratlam stations are detailed.
* **Heritage Preservation:**
* Ministry of Railways is committed to preservation of items of heritage value during redevelopment.
* Site-specific measures are taken based on the context and condition of the structure/artifact.
**Impact Analysis**
**Stakeholder: Passengers**
* **Impact:** Improved station amenities, increased accessibility, and enhanced travel experience through upgraded facilities and better information systems.
* **Action Required:** Utilize the improved facilities and provide feedback on further improvements.
**Stakeholder: Railway Authorities (Ministry of Railways, Zonal Railways)**
* **Impact:** Responsible for planning, funding, and executing the redevelopment projects, while adhering to heritage preservation guidelines and managing operational challenges.
* **Action Required:** Continue monitoring the progress, allocate funds effectively, address project complexities, and ensure timely completion of works.
**Stakeholder: Local Communities/Vendors**
* **Impact:** Potential economic opportunities through the "One Station One Product" scheme and improved local infrastructure.
* **Action Required:** Engage with railway authorities to set up kiosks and participate in local economic development initiatives.
**Stakeholder: Divyangjans (Persons with Disabilities)**
* **Impact:** Increased accessibility through the provision of ramps, lifts, and dedicated facilities.
* **Action Required:** Utilize the accessible facilities and provide feedback for further improvements.
Key Entities Referenced
Amrit Bharat Station Scheme: A railway station redevelopment scheme launched by the Ministry of Railways focusing on long-term station upgrades.
Ministry of Railways: The Indian government ministry responsible for the railway system, overseeing the implementation of the Amrit Bharat Station Scheme.
Maharashtra: One of the two states (along with Madhya Pradesh) where railway stations are being redeveloped under the mentioned scheme.
Madhya Pradesh: One of the two states (along with Maharashtra) where railway stations are being redeveloped under the mentioned scheme.
Chhatrapati Shivaji Maharaj Terminus (CSMT): A railway station in Mumbai, Maharashtra, specifically mentioned for redevelopment under the Amrit Bharat Station Scheme.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 873
TO BE ANSWERED ON 04.02.2026
REDEVELOPMENT OF RAILWAY STATIONS IN MAHARASHTRA AND
MADHYA PRADESH UNDER ABSS
873. SMT. BHARTI PARDHI :
DR. SHRIKANT EKNATH SHINDE :
SHRI RAVINDRA DATTARAM WAIKAR :
SHRI SHRIRANG APPA CHANDU BARNE :
SHRI NARESH GANPAT MHASKE :
Will the Minister of RAILWAYS be pleased to state:
(a) the physical progress of the redevelopment of stations in
Madhya Pradesh and Chhatrapati Shivaji Maharaj Terminus (CSMT)
of Maharashtra under the Amrit Bharat Station Scheme as of
January 2026;
(b) the specific measures taken/being taken by the Government to
preserve the UNESCO World Heritage status of the buildings while
integrating modern airport-like amenities;
(c) the list of stations in Balaghat, Lok Sabha Constituency and sub-
urban stations in Mumbai Metropolitan Region identified for Phase-2
of the Amrit Bharat Station Scheme and the budgetary outlay for the
same;
(d) the details of passenger amenity upgrades such as escalators,
lifts and executive lounges planned for major suburban hubs like
Dadar, Raigad and Pune, Thane and Kalyan; and(e) the timeline for the completion of the CSMT redevelopment
project and the expected increase in daily passenger handling
capacity post-completion?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): The progress of redevelopment of various railway
stations situated in Maharashtra and Madhya Pradesh is as
under:
Maharashtra:
Development works at railway stations under Amrit Bharat
Station Scheme in Maharashtra has been taken up at a good
pace. Till now, Works of 17 stations including 05 suburban
stations (Amgaon, Chanda Fort, Chinchpokli, Devlali, Dhule,
Kedgaon, Lasalgaon, Lonand Junction, Matunga, Murtizapur
Junction, Netaji Subhash Chandra Bose Itwari Junction, Parel,
Savda, Shahad, Vadala Road, Baramati and Nandura) have been
completed in Maharashtra under the scheme. The progress of
some of the stations in Maharashtra identified in Amrit Bharat
Station Scheme is as given below:
Chhatrapati Shivaji Maharaj Terminus: The work for redevelopment
of station has been sanctioned. The work for relocation of
Divisional Engineering Training Centre to Wadi Bunder,foundation work of foot over bridge no. 6 on platform no. 18 &
12/13 and refurbishment of ground floor & 1st floor of main line
building have been completed. The works for foundation of long
distance node building, long distance concourse and foot over
bridge no. 1 and 2, parcel, linen and C&W building have been
taken up.
Diva: The works of improvement of circulating area and parking on
east side, improvement to station building on east side, new entry
gate, improvement to Foot Over Bridge at Kalyan and Mumbai end,
construction of new staircase for Foot Over Bridge, platform shelter
of platform no. 7/8, platform raising and flooring improvement of
platform no. 5/6 and 7/8, new toilet block, sewage treatment plant
on west side and new service building have been completed. The
work for construction of Foot Over Bridge has been taken up.
Mumbra: The works for improvement to platform surface,
improvement of seating arrangement, improvement to flooring of
Foot Over Bridge, new toilet block, sewage treatment plant,
improvement of circulating area and improvement of ticket booking
office have been completed. The work for provision of escalators
has been taken up.
Titwala: The works of improvement of two wheeler parking and
approach road on east and west side, new station building, new
entrance gate, improvement of ticket booking office, new toilet
block, sewage treatment plant and platform surfacing have been
completed. The work of new Foot Over Bridge has been taken up.Vikhroli: The works for improvement of platform surfacing,
improvement of platform shelter, improvement of Foot Over Bridge,
new toilet block on Mumbai end, improvement of toilet block on
Kalyan end and improvement of station building on west side have
been completed. The works of development of circulating area on
west & east side and new booking office & parking on east side
have been taken up.
Charni Road: The works of widening of entry-exit, construction of
the new booking office on Platform No. 1, improvement of the
footpath pavement surface, construction of fencing and boundary
work on Platform No. 4, improvement of existing platform shelter at
platform 1, 2 & 3 and fencing work at the north-side entry have been
completed. The works of platform shelter sheet replacement on
Platform No. 4, Foot over Bridge and Platform No. 1 surfacing work
have been taken up.
Malad: The works for the raising of platform 1, 2, 3, 4 & 5 and
improvement of existing platform shelters have been completed.
The works for improvement of booking office and toilets have been
taken up.
Kalyan: The works for provision of new ‘A’ building at Kalyan
(east), provision of platform shelter on platform (PF) no. 4 & 5,
provision of one lift and two escalator, improvement of
circulating area and augmentation of water supply have been
completed. The work of extension of platform 2 & 3,
construction of lokgram foot over bridge has been taken up. The
works for provision of 04 nos. escalators, provision of additionalaccessibility facilities for divyangjan and provision of sewage
treatment plant have been sanctioned.
Dadar: The works for raising of platform no. 8 and 10, provision
of platform shelter on platform 8, 10 and 11, provision of lifts and
escalators, construction of toilet block and improvement of
water supply have been completed. The works for
provision of foot over bridge connecting PF 8 to PF 9 and
provision of additional platform shelters have been sanctioned.
Thane: The works for raising of platform no. 2, replacement of
two foot over bridges, widening of platform 5 & 6, construction
of new waiting hall, toilet block, provision of new parking lot,
provision of platform shelter and 2 escalator have been
completed. The works of provision of one foot over bridge,
provision of additional 02 escalators and additional platform
shelters have been sanctioned.
Pune: The works for improvement of platform surface on platform
no. 6 and platform 2&3, provision of 02 divyangjan toilets,
improvement to parcel office, provision of additional platform
shelters have been completed. The works for provision of 04 nos
lifts, improvement to station circulating area at main and 2nd entry
side and extension of platforms have been taken up.
Madhya Pradesh:
Development works at railway stations under Amrit Bharat Station
Scheme in Madhya Pradesh has been taken up at a good pace. Till
now, works of 14 stations (Beohari, Bhind, Harpalpur, Junnor Deo,
Katni South, MCS Chhatarpur, Nainpur Jn., Narmadapuram, Orchha,
Sanchi, Seoni, Shajapur, Shridham and Vidisha) in Madhya Pradeshhave been completed under this scheme. This includes Seoni
station which is situated in Balaghat lok sabha constituency. The
progress of some of the stations in Madhya Pradesh taken up in
Amrit Bharat Station Scheme is as given below:
Balaghat station in Balaghat lok Sabha Constituency, the works for
improvement of station building, improvement of circulating area,
parking with provision of 1 no high mast lighting, renovation of
waiting hall, improvement of platform surfacing, provision of
standard signages, additional platform shelter, toilet block,
installation of CCTV and Coach & Train Indication Boards have been
completed and finishing work taken up.
Rewa: The works for improvement of station building, entry and exit
porches, improvement of drainage, construction of new toilet blocks
and improvement of waiting hall have been completed. The works of
improvement of circulating area with provision of parking lots,
provision of 12 m wide Foot Over Bridge and raising & platform
surfacing of Platform No. 1 have been taken up.
Ruthiyai: The works of Improvement of Station Building,
improvement of circulating area with provision of parking lots,
improvement to Platform surfacing at PF 1 & 2, construction of new
toilet block, improvement of waiting hall, provision of additional
platform shelters and improvement of divyangjan amenities have
been completed. The work for construction of 12m wide Foot Over
Bridge has been taken up.
Ratlam: The works for widening of platform 4, provision of platform
shelter on PF 4, improvement of waiting room, toilets, development
of second entry with approach road, improvement of circulatingarea and parking have been completed. The works for foot over
bridge has been taken up.
Dewas: The works for improvement of circulating area, widening of
platform, improvement of platform surface, platform shelters,
improvement of waiting hall, toilets and provision of new toilet
block have been completed. The works for provision of foot over
bridge, lifts, escalator and signage have been taken up.
Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach. The
scheme involves preparation of master plans and their implementation
in phases to improve the stations. The master planning, keeping in
view the necessity at each station includes:-
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement,
water booths
Provision of wider foot over bridge/air concourse
commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like
‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems Provision of executive lounges, nominated spaces for
business meetings, landscaping, etc.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks, etc. as per necessity,
phasing and feasibility and creation of city centre at the station in
the long term.
So far, 1337 stations have been identified under Amrit Bharat
Station Scheme. Out of these, 80 stations are located in Madhya
Pradesh and 132 stations located in Maharashtra. The name of
stations identified for redevelopment under Amrit Bharat Station
Scheme in Madhya Pradesh and Maharashtra are as following:
State No. of Name of Stations
Stations
Madhya 80 Akodia, Amla, Anuppur, Ashoknagar,
Pradesh Balaghat, Banapura, Bargawan, Beohari,
Berchha, Betul, Bhind, Bhopal, Bijuri, Bina,
BiyavraRajgarh, Chhindwara, Dabra, Damoh,
Datia, Dewas, Gadarwara, Ganjbasoda,
Ghoradongri, Guna, Gwalior, Harda,
Harpalpur, Indore Jn, Itarsi Jn, Jabalpur,
Junnor Deo, Kareli, Katni Jn, KatniMurwara,
Katni South, Khachrod, Khajuraho Jn,
Khandwa, Khirkiya, Laxmi Bai Nagar, Maihar,
Maksi Jn, Mandla Fort, Mandsor, MCS
Chhatarpur, Meghnagar, Morena, Multai,
Nagda Jn, Nainpur Jn, Narmadapuram(Hoshangabad), Narsinghpur, Nepanagar,
Nimuch, Orchha, Pandhurna, Pipariya, Ratlam,
Rewa, Ruthiyai, Sanchi, Sant Hirdaram Nagar,
Satna, Saugor, Sehore, Seoni, Shahdol,
Shajapur, Shamgarh, Sheopur Kalan, Shivpuri,
Shridham, Shujalpur, Sihora Road, Singrauli,
Tikamgarh, Ujjain, Umaria, Vidisha,
Vikramgarh Alot
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road,
Akola, Akurdi, Amalner, Amgaon, Amravati,
Andheri, Badnera, Balharshah, Bandra
Terminus, Baramati, Belapur, Bhandara Road,
Bhokar, Bhusawal, Borivali, Byculla,
Chalisgaon, Chanda Fort, Chandrapur, Charni
Road, Chhatrapati Sambhajinagar,
Chhatrapati Shivaji Maharaj Terminus,
Chinchpokli, Chinchwad, Dadar (CR), Dadar
(WR), Dahisar, Daund, Dehu Road, Devlali,
Dhamangaon, Dharangaon, Dharashiv,
Dharmabad , Dhule, Diva, Dudhani, Gangakher
, Godhani, Gondia, Grant Road, Hadapsar,
Hatkanangale, Hazur Sahib Nanded,
Himayatnagar , Hinganghat, Hingoli Deccan,
Igatpuri, Jalgaon, Jalna, Jeur, Jogeshwari,
Kalyan Junction, Kamptee, Kandivali, Kanjur
Marg, Karad, Katol, Kedgaon, Kinwat ,
Kopargaon, KurduwadiJunction, Kurla
Junction, Lasalgaon, Latur, Lokmanya TilakTerminus, LonandJunction, Lonavla, Lower
Parel, Malad, Malkapur, Manmad Junction,
Manwath Road , Marine Lines, Matunga, Miraj
Junction, Mudkhed Junction, Mumbai Central,
Mumbra, Murtizapur Junction, Nagarsol,
Nagpur Junction, Nandgaon, Nandura,
Nandurbar, NarkherJunction, Nashik Road,
Netaji Subhash Chandra Bose Itwari Junction,
PachoraJunction, Palghar, Pandharpur,
Panvel Junction, Parbhani Junction, Parel,
Parli Vaijnath, Partur , Phaltan, Prabhadevi,
Pulgaon Junction, Pune Junction, Purna
Junction, Raver, Rotegaon , Sainagar Shirdi,
Sandhurst Road, Sangli, Satara, Savda, Selu ,
Sewagram, Shahad, Shegaon, Shivaji Nagar
Pune, Shri Chhatrapati Shahu Maharaj
Terminus Kolhapur, Solapur, Talegaon,
Thakurli, Thane, Titvala, Tumsar Road, Umri,
Uruli, Vadala Road, Vidyavihar, Vikhroli,
Wadsa, Wardha, Washim, Wathar
Ministry of Railways is committed to preservation of items of heritage
value while planning and execution of redevelopment/modernization
of stations. Site specific measures are taken based on the context
and condition of the structure/artifact.
Development/upgradation of stations on Indian Railways is a
continuous and ongoing process and works in this regard are
undertaken as per requirement, subject to inter-se priority andavailability of funds. The priority for development / redevelopment /
upgradation / modernisation of stations is accorded to higher
category of station over lower category of station while
sanctioning and executing the works.
The phasing of the station redevelopment project depends on several
factors like requirement, level of existing infrastructure, changes in
station footfall, development of adjoining areas and their interaction
with the station, changes in complementary mode of transport,
availability of funds, inter-se priority etc. This is a gradually evolving
process depending upon a numbers of variables and no time frame
can be indicated at this stage for the same.
Development / upgradation of stations including under Amrit Bharat
Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation under Plan Head-53 are
maintained Zonal Railway-wise and not station-wise or State-wise.
Madhya Pradesh and Maharashtra state falls under the jurisdiction of
Central Railway, Western Railway, South Central Railway, West
Central Railway, East Central Railway, North Central Railway, South
East Central Railway. For these zones, a total allocation of ₹5800.68
crores (Revised Estimate) has been made for the financial year 2025-
26 under Plan Head-53.
Escalators and lifts at railway stations are provided depending upon
techno-economical feasibility and inter-se priority of the station. So
far, 66 nos. escalators at 12 railway stations and 25 nos. lifts at 09
railway stations have been provided at Major Suburban Hubs like
Dadar, Pune, Thane, Kalyan and station in Raigad district, etc.Further, development/redevelopment/upgradation of Railway Stations
is complex in nature involving safety of passengers & trains and
requires various statutory clearances such as fire clearance,
heritage, tree cutting, airport clearance etc. The progress also gets
affected due to brown field related challenges such as shifting of
utilities, (involving water/sewage lines, optical fiber cables, gas pipe
lines, power/signal cables etc.) infringements, operation of trains
without hindering passenger movement, speed restrictions due to
works carried out in close proximity of high voltage power lines etc.
and these factors affect the completion time. Therefore, no time
frame can be indicated at this stage.
*****