GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6200
TO BE ANSWERED ON 01.04.2026
REDEVELOPMENT OF UDAIPUR CITY RAILWAY STATION
†6200. DR. MANNA LAL RAWAT:
Will the Minister of RAILWAYS be pleased to state:
(a) the number of railway station is identified for redevelopment under the
PPP model, zone-wise;
(b) the number of stations redevelopment work has commenced so far and
the total number of stations where this work has been completed,
Station-wise;
(c) the details of total investment proposed under station redevelopment
projects and the actual investment received so far;
(d) the timeline fixed for completion of remaining station redevelopment
projects;
(e) the details of the budget allocated for the redevelopment of Udaipur
City Railway Station the portion of work completed so far and the
remaining construction work; and
(f) whether there has been a delay in completing the said redevelopment
work and if so, the reasons therefor and the time by which this work is
proposed to be completed?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
Udaipur city station has been identified for redevelopment under Amrit
Bharat Station Scheme. The redevelopment work of Udaipur city railway
station has been sanctioned and work awarded. The structural works of
§ Page 1 of 7east side building, west side building & basement have been completed.
The finishing works of east side of building, west side of building &
basement and upgradation work of platform area have been taken up.
So far, 1,338 stations, including 15 stations in Public-Private Partnership
(PPP) model, have been identified for redevelopment under the Amrit Bharat
Station Scheme.
The scheme involves preparation of master plans and their implementation
in phases to improve the stations. The master planning, keeping in view the
necessity at each station includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
• Amenities for Divyangjans
• Better passenger information systems
• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc.
Page 2 of 7The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
Development works at railway stations under Amrit Bharat Station Scheme
have been taken up at a good pace. Till now, works have been completed at
208 stations. Names of stations completed so far are as following:
Aishbagh Jn., Alnavar, Amb Andaura, Ambikapur, Amgaon, Anandpur Sahib,
Anara, Angamali For Kaladi, Ayodhya Dham Junction, Badami, Bagalkot,
Baheri, Baijnath Paprola, Balaghat, Balrampur, Bantawala, Barabhum,
Baramati, Bareilly City, Baripada, Barmer, Barpali, Begumpet, Beohari,
Bhanupratappur, Bhilai, Bhind, Bijnor, Bimalgarh, Bommidi, Bundi, Byculla,
Chalakudi, Champa, Chanda Fort, Changanassery, Chennai Park,
Chhindwara, Chidambaram, Chinchpokli, Chinna Salem, Chirayinkeezh,
Chunar Jn., Coonoor, Cumbum, Cuttack, Dakor, Dausa, Deeg, Derol,
Deshnoke, Devlali, Dhampur, Dharwad, Dhule, Dongargarh, Eluru,
Fatehabad, Fatehpur, Fatehpur Shekhawati, Ferok, Gadag, Gangapur City,
Godda, Godhra Jn., Gogameri, Gokak Road, Gola Gokarnath, Gomtinagar,
Govardhan, Govind Garh, Govindpur Road, Govindpuri, Hafizpeta,
Haibargaon, Haldia, Haldibari, Hapa, Harpalpur, Hathras City, Hi-tech city,
Himayatnagar, Hodal, Idgah Agra Jn., Izzatnagar, Jaisalmer, Jam Jodhpur,
Jam Wanthali, Joychandi Pahar Jn., Junnor Deo, Kakinada Town Jn,
Kalyani Ghoshpara, Kamakhyaguri, Kanalus Jn, Karaikkudi Jn., Karamsad,
Karimnagar, Katni South, Kedgaon, Kesinga, Khairthal, Khalilabad,
Khambhaliya, Koppal, Kosamba Jn, Kulitturai, Kuttippuram, Lasalgaon,
Limbdi, Lohardaga, Lonand Jn., Madhupur Jn., Mahe, Mahuva, Mailani Jn.,
Mambalam, Manaparai, Mandal Garh, Mandawar Mahwa Road, Mandi
Dabwali, Mangalagiri, Mannargudi, Matunga, MCS Chhatarpur, Mithapur,
Morappur, Morbi, Muktsar, Munirabad, Muri Jn., Murtizapur Jn., Nainpur Jn.,
Namakkal, Nandura, Narmadapuram, Narwana Jn., Netaji Subhash Chandra
Page 3 of 7Bose Itwari Junction, Nidadavolu Jn., Nilambur Road, Okha, Orchha,
Palitana, Panagarh, Panki Dham, Parappanangadi, Parel, Parlakhemundi,
Pirpainti, Piska, Pokhrayan, Pollachi Jn., Polur, Porbandar, Rajgarh,
Rajmahal, Rajula Jn., Ramagundam, Ramghat Halt, Rayanapadu, Sabaur,
Saharanpur Jn., Sahibganj, Sahibzada Ajit Singh Nagar Mohali, Samakhiyali,
Samalpatti, Sanchi, Sankarpur, Sarona, Savda, Seoni, Shahad, Shajapur,
Shivanarayanpur, Sholavandan, Shoranur Jn., Shridham, Siddharth nagar,
Sihor Jn., Simultala, Siuri, Somesar, Sri Bala Brahmeswara Jogulamba,
Srirangam, Srivilliputtur, St.Thomas Mount, Sullurpeta, Suraimanpur,
Swaminarayan Chappia, Talcher, Tamluk, Tanakpur, Thalassery, Thawe,
Thiruvarur Jn., Tiruvannamalai, Tripunithura, Tuni, Udagamandalam, Ujhani,
Urkura, Utran, Vadakara, Vadala Road, Vidisha, Vindhyachal,
Vriddhachalam Jn., Wadakancheri, Warangal
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Ranapratap Nagar: The structural work of main entry station building,
provision of booking counter, drainage work, improvement of
circulating area, landscaping, entry/exit gates, provision of platform
shelters, high mast light, pathway and improvement of platform (PF)
surfacing of PF-4 have been completed. The works for tactile path,
divyangjan toilet, divyangjan parking, provision of water booth and
construction of 12 m wide foot over bridge have been taken up.
Kota Junction station: The structural works of front departure hall,
front arrival hall and rear side station building have been completed.
The finishing works of front departure hall, rear side station building,
air concourse, through roof, circulating area have been taken up.
Tirupati station: The structural framework of new second entry
station building on South side, 2 nos. air concourses and sewage
Page 4 of 7treatment plant have been completed. The finishing works of new
second entry station building on South side and air concourses,
structural work of station building on North side, platform shelter, lift,
escalator etc. have been taken up.
Nellore station: The structural framework, brickwork and plastering
of station building on both east and west sides have been completed.
The finishing works of station building on both east and west side and
air concourse, extension work of subway, parking, water tanks and
sewage treatment plant have been taken up.
Bangalore Cantonment station: The works of diversion road on south
side, training centre, hostel on north side, electric substation building
have been completed. The works of south side station building, north
side station building, circulating area and foot over bridge have been
taken up.
Bhubaneshwar station: The structural works of new station building
at east and west side and air concourse have been completed. The
structural works of elevated driveway at east and west side station,
extension of foot over bridge and platform shelter have been taken up.
The finishing works of new station building at east and west side,
works of MEP (Mechanical, Electrical and Plumbing), HVAC (Heating,
Ventilation and Air Conditioning) and escalators have been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station are carried out based on category
of station/condition/traffic handled etc.
Page 5 of 7Rani Kamalapati station in Madhya Pradesh has already been developed
and commissioned under PPP model. Out of 15 stations identified for
redevelopment under PPP model, the bid for redevelopment of Vijayawada
station has been invited. The other 14 stations are at various stages of
master planning and financial modelling.
Further, funding from private investment depends upon numbers of variable
e.g. the cost of the projects, revenue stream available, station footfall,
locality around the station. Therefore, it cannot be indicated at this stage.
For redevelopment of Rani Kamalapati station, an investment of Rs. 115
Crores was made by concessionaire. Further, an amount of Rs. 47.46 Cr.
has been received by railways for additional built up area given to
concessionaire. Additionally, an amount of Rs. 2.37 crores towards revenue
share has been received from concessionaire.
Development / upgradation of stations including under Amrit Bharat Station
Scheme is generally funded under Plan Head-53 ‘Customer Amenities’. The
details of allocation under Plan Head-53 are maintained Zonal Railway-wise
and not station-wise or State-wise. Udaipur City railway station falls under
the jurisdiction of North Western Railway (NWR) for which a total allocation
of ₹ 907 crores (RE) has been made for the financial year 2025-26 under
Plan Head-53.
Further, development/redevelopment/upgradation of Railway Stations is
complex in nature involving safety of passengers & trains and requires
various statutory clearances such as fire clearance, heritage, tree cutting,
airport clearance etc. The progress also gets affected due to brown field
related challenges such as shifting of utilities, (involving water/sewage
lines, optical fiber cables, gas pipe lines, power/signal cables etc.)
Page 6 of 7infringements, operation of trains without hindering passenger movement,
speed restrictions due to works carried out in close proximity of high
voltage power lines etc. and these factors affect the completion time.
Therefore, no time frame can be indicated at this stage.
*****