GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3087
TO BE ANSWERED ON 11.03.2026
RENEWAL OF RAILWAY TRACKS
†3087. SMT. VIJAYLAKSHMI DEVI:
SHRI CHANDRA PRAKASH CHOUDHARY:
SHRI DILESHWAR KAMAIT:
Will the Minister of RAILWAYS be pleased to state:
(a) the total number of track kilometers (route kilometers) identified for
renewal across the entire rail network particularly in North-Eastern
Railway Network;
(b) the year-wise targets for track renewal and new track installation
during the last seven years;
(c) State-wise details of the actual route kilometers of track renewal and
new track installation during this period especially in Jharkhand
including pending work, zone-wise;
(d) the current status of the Parasnath-Madhuban-Giridih new railway line
project, the foundation stone of which was laid in 2019;
(e) the status of renewal of rail network in the States including Bihar and
Kolkata; and
(f) whether the Government proposes to construct new railway lines in
the States including Bihar and Kolkata and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) Upgradation and renewal of tracks is a continuous and ongoing
process. The track renewal is carried out as per the laid down criteria
based on age, traffic carried, condition etc.
§Track Renewal Works are planned and executed duly prioritizing the
condition of track and various other factors so as to ensure that track is
safe for running of trains at permitted speed.
The details of track renewal carried out across the entire railway network
during 2014-26 (up to Feb’26) are as under:
Track renewed ~ 54600 Km
The above track renewal includes railway tracks situated in North-
Eastern region, Jharkhand, Bihar and Kolkata.
Further, following measures are being taken to upgrade the railway
tracks:
i. Modern track structure consisting of 60 kg, 90 Ultimate Tensile
Strength (UTS) rails, Wider and heavier Pre-stressed Concrete
Sleepers (PSC) with elastic fastening, fan-shaped layout turnout on
PSC sleepers and H-beam Sleepers on girder bridges are being used
while carrying out primary track renewals.
ii. The Thick Web Switches and Weldable CMS Crossings are being used
in turnout renewal works.
iii. Supply of 260 meter long rail panels have been increased to avoid
welding of joints, thereby improving safety.
iv. Thick Web Switch Expansion Joints are being used in place of earlier
Conventional/Improved SEJs.
v. Adoption of better welding technology for rails i.e. Flash Butt
Welding.
vi. Adoption of mechanized system for track maintenance using high
output plain tampers and points & crossing tampers for improved
maintainability & reliability of track.
vii. Deployment of state-of-the-art modern machines including Rail
Grinding Machines to further improve asset reliability.
§viii. Mechanisation of track laying activities through use of track
machines like PQRS, TRT, T-28 etc.
ix. Use of advanced Phased Array technology of testing of rail and
welds.
x. Deployment of Integrated Track Monitoring Systems (ITMS) and
Oscillation Monitoring System (OMS) for comprehensive health
assessment to ascertain optimal maintenance requirements.
xi. Adoption of portable Track Measuring Trolley for continuous
recording of track parameters in yards.
xii. Using web enabled Track Management System (TMS) for integration
and data analytics of the track inspection records received through
various sources to enable precise maintenance inputs.
Parasnath–Giridih–Madhuban New Line:
Parasnath–Giridih–Madhuban New Line Project was sanctioned in 2018–19
on 50:50 cost – sharing basis with the Government of Jharkhand, at an
estimated cost of ₹903 Cr. Accordingly, Railways requested the State
Government to deposit its share of the cost. However, the Government of
Jharkhand is yet to deposit its share. As a result, the project has not
progressed.
Jharkhand:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects falling fully/partly in the State of
Jharkhand is as under:-
Period Outlay
2009-14 ₹457 Cr./Yr
2025-26 ₹7306 Cr. (approx. 16 times)
§As on 01.04.2025, 26 projects (9 New Lines and 17 Doubling), of total
length of 2363 Km, costing ₹47,729 crore falling fully/partly in the State
of Jharkhand including those which are in planning/approval/construction
stage, out of which, 598 km length has been commissioned and an
expenditure of ₹15,845 crore has been incurred upto March, 2025.
The summary is as under:-
Category No. of Total Length Total Exp.
projects Length Commissioned till Upto March,
(in Km) March, 2025 (in 2025
Km) (Rs. in Cr.)
New Lines 9 749 156 4239
Doubling/Mu- 17 1614 442 11606
lti tracking
Total 26 2363 598 15845
The details of commissioning/ laying of new track falling fully/partly in the
State of Jharkhand is as under:-
Period New Track Average Commissioning
Commissioned of new tracks
2009-14 287 Km 57.4 Km
2014-25 1316 Km 119.64 Km (More than 2
times)
During last three years (i.e. 2022-2023, 2023-24, 2024-2025 and current
Financial Year i.e. 2025-26), total 85 Nos. of Surveys (18 New Line, 67
§Doubling) falling fully/partly in the State of Jharkhand having a total
length of 3303 Km have been sanctioned.
West Bengal:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly
in the State of West Bengal is as under:-
Period Outlay
2009-14 Rs.4,380 Cr./year
2025-26 Rs. 13,955 Cr. (More than 3 times)
As on 01.04.2025, 42 projects (12 New Lines, 04 Gauge Conversions and
26 Doubling), of total length of 4402 Km, costing ₹67,991 crore falling
fully/partly in the State of West Bengal are sanctioned, out of which, 1702
km length has been commissioned and an expenditure of ₹23,410 crore
has been incurred up to March, 2025. The summary is as under:
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2025
(in Km) till March, 2025 (Rs. in Cr.)
(in Km)
New Lines 12 1,032 337 11,368
Gauge
4 1,201 854 3,673
Conversion
Doubling/Mu
26 2,169 511 8,370
lti-tracking
Total 42 4,402 1,702 23,410
§Details of some of the recently completed projects falling fully/partly in
the State of West Bengal are as under:
Cost
S. No. Project
(Rs. in Cr.)
1 Rampurhat-Mandarhill new line Rampurhat- 1,500
Murarai 3rd line (159 Km)
2 Azimganj-Murshidabad new line (7 Km) 164
3 Bardhaman-Katwa Gauge Conversion (52 Km) 696
4 Ahmedpur-KatwaGauge Conversion (52 Km) 440
5 Panskura Kharagpur Doubling (45 Km) 408
6 Lalgola – Jiaganj Doubling (23 Km) 124
7 Krishnanagar-Bethuadahari Doubling (28 Km) 152
8 Nabadwipdham-Patuli Doubling (22 Km) 170
9 Bethuadhahari-Plassey Doubling (23 km) 132
10 Ambikakalna-Nabadwipdham Doubling (23 km) 145
11 Nalhati-Sagardighi Doubling (26 km) 193
12 Tamluk Jn.- BasulyaSutahata Doubling (24 km) 245
13 Plassey- Jiaganj Doubling (54 km) 234
14 Azimganj-Manigram Doubling (21 km) 150
15 New Coochbehar-Gumanihat Doubling (29 km) 330
16 New Coochbehar-Samuktala Road Doubling (29 445
km)
17 Sainthia-Tarapith 3rd line (22 Km) 186
§Cost
S. No. Project
(Rs. in Cr.)
18 Ambari Falakata-New Maynaguri Doubling (37 843
km)
19 Bandel-Boinchi - 3rd line (31 km) 546
20 Boinchi-Shaktigarh 3rd line (26 km) 424
21 Bazar Sau-Azimganj Jn. Doubling (42 km) 343
22 Sagardighi- Malda Town Doubling (25 Km) 248
23 Kharagpur-Narayangarh 3rd line (24 km) 270
24 Monigram-Nimtita Doubling (24 Km) 713
25 Purulia-Kotshila Doubling (36 Km) 393
Some of the projects falling fully/partly in the State of West Bengal which
have been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Tarakeshwar-Bishnupur New Line (83 Km) 1,542
2 Sivok-Rangpo New Line (44 Km) 11,973
3 Balurghat-Hilli New Line (30 Km) 1,209
4 Kaliyaganj-Buniadpur New Line (33 Km) 1,147
5 Katihar-Kumedpur and Katihar-Mukuria Doubling 943
(65 Km)
6 Kharagpur-Adityapur 3rd line (132 Km) 3,250
7 Narayangarh-Bhadrak 3rd line (153 Km) 2,136
8 Chandil-Anara-Damodar 3rdLine(121 Km) 1,932
§9 Kalipahari-Bakhtarnagar 5th Line (18Km) 350
10 Dankuni-Baltikuri 3rd & 4th line (18 Km) 429
11 Murarai-Barharwa 3rd Line (49 Km) 935
12 Ranaghat-Krishnanagar City 3rd Line (26 Km) 446
13 Aluabari Road-New Jalpaiguri 3rd & 4th Line (57 1,630
Km)
During last three years (i.e. 2022-2023, 2023-24, 2024-25 and current
Financial Year i.e. 2025-26), total 97 Nos. of Surveys (10 New Line, 87
Doubling) falling fully/partly in the State of West Bengal having a total
length of 4,004 Km have been sanctioned.
Kolkata Metro:
Metro project in Kolkata started in 1972. The details of the Metro
commissioned since then are as under:
Period Metro Commissioned
1972 to 2014 ( 42 years) 28 km
2014 to 2025 ( 11 years) 45 km
Presently, 4 metro corridors of total 52 km are under construction in and
around Kolkata out of which 20 Km is held up due to land acquisition and
utility shifting issues pertaining to State Government. The status of these
corridors is as given below:
(i) Joka – Esplanade (14 km):- Joka - Majerhat (7.74 km) has been
commissioned and balance work from Majerhat to Esplanade (6.62 km)
has been taken up. However, progress of the work is affected due to the
§following issues:
S.No. Location Issues
1. Khidderpur Metro 1. 837 square meter permanent and 1702
Station sq.m. temporary land of Kolkata Armed
Police (KAP) was required for utility
shifting and road traffic diversion for
which proposal was sent to State
Government on 24.08.2020.
2. Multiple meetings with officials of
Government of West Bengal (GoWB) were
held.
3. State Government finally accorded
approval on 09.07.2025 after almost 5
years.
2. Dr. B.C. Roy 1. For construction of Esplanade Metro
Market Station, temporary shifting of
unauthorised 528 Shops at B.C. Roy
Market on Defence land was required. The
proposal for NOC of temporary shifting of
market was submitted in February, 2022.
2. Shops for temporary shifting were
also constructed.
3. The State Government has been
requested to facilitate shifting. Regular
coordination with PWD is being done also,
a meeting was held with Hon’ble Mayor of
Kolkata on 30.07.2025.
4. Issue is pending for more than 3.5
years.
§(ii) New Garia - Dum Dum Airport (32 km): New Garia – Belaghata (9.8
km) has been commissioned and balance work from Belaghata to Dum
Dum Airport (22.2 km) has been taken up. However, progress of the work
is affected due to the following issues:
S.No. Location Issues
1. Chingrighata Crossing 1. Temporary traffic diversion at
(Between Beleghata – Chingrighata crossing for launching
Gour Kishore Ghosh of viaduct segments is required for 3
station) + 3 nights (8 hours each) on each side
of road alternately. The proposal was
submitted to Government of West
Bengal (GoWB) in February, 2025.
2. The diversion road as desired
by Kolkata traffic police has already
been constructed in February, 2025.
3. Multiple meetings were held
with various State Government and
Kolkata police officials for NOC.
4. The NOC is still awaited even
after about 10 months.
(iii) Noapara – Barasat (18 km): Noapara- Jai Hind Airport (6.77 km) has
been commissioned and work from Jai Hind Airport to Michael Nagar is in
progress. However, work from New Barrackpore to Barasat (7.5 Km) is
held up due to land acquisition and encroachment issues by State
authorities.
S.No. Location Issues
1. New 1. Land acquisition (23000 sq. m) and
Barrackpore removal of heavy encroachments (1277
§to Barasat hutments, 764 shops) are involved in this
section.
2. The matter is not yet resolved by
GoWB.
(iv) Baranagar- Barrackpore - Dakshineshwar (14.5 km):Baranagar-
Dakshineshwar(2 km) has been commissioned and balance work from
Baranagar to Barrackpore (12.5 Km) is held up due to pending utility
shifting in the alignment by state government authorities.
S.No. Location Issues
1. Baranagar 1. The original alignment along the B.T
to road was agreed in 2011 as per MoU between
Barrackpore Metro Railway, RVNL and Kolkata Municipal
Corporation.
2. As per MoU, existing pipeline was to be
replaced by new 64 inch pipeline by the State
Government.
3. Shifting of 64 inch pipeline was
completed in 2012.
4. Now, the State Government is insisting
for construction of a new 90 inch pipeline
costing about ₹1400 crore.
5. The demand is not covered under the
cost of the project and MoU provisions.
6. NOC is still awaited from GoWB.
§Bihar:
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the State of Bihar is as under:
Period Outlay
₹1,132 Cr./year
2009-14
₹10,066 Cr. (Nearly 9 times)
2025-26
The details of commissioning/laying of new track falling fully/partly in the
State of Bihar during 2009-14 and 2014-25 is as under :-
New Track Average Commissioning of new
Period
Commissioned tracks
318 Km 63.6 Km
2009-14
1,899 Km 172.6 (More than 2.5 times)
2014-25
As on 01.04.2025, 52 projects (31 New Lines, 01 Gauge Conversions and
20 Doubling), of a total length of 4,663 km, costing ₹86,107 crore, falling
fully/partly in Bihar, are sanctioned, out of which 1,250 km length has
been commissioned and an expenditure of ₹29,353 crore has been
incurred upto March’ 2025. The summary is as under:-
Total Length Total Exp
No of
Length Commissioned upto
Category sanctioned
NL/GC/DL till Mar'25 Mar'25
Projects
(in Km) (in Km) (₹ in Cr)
New Lines 31 2,691 516 16,814
Gauge
1 69 52 544
Conversion
§Doubling/Multi-
20 1,904 446 11,995
tracking
Total 52 4,663 1,014 29,353
Details of some of the recently completed projects falling fully/partly in
Bihar are as under:-
SN. Project Cost
(In Crores of
Rs)
1 Munger Bridge (19 km) 2,774
2 Kosi Bridge (22 Km) 516
3 Patna Bridge (40 Km) 3,555
4 Hajipur-Bachwara Doubling (72 km) 930
5 Kiul-Gaya Doubling (123 km) 1,200
6 KarotaPatner-Mankatha - Surface triangle (8 129
km)
7 Rampurhat-Mandarhill New Line and 1,500
Rampurhat-Murarai- 3rd line (160 km)
8 Jaynagar-Darbhanga-Narkatiaganj and 1,193
Narkatiaganj-Bhikhna Tori Gauge Conversion
(295 Km)
9 Sakri-Laukaha Bazar-Nirmali & Saharsa- 2,113
Forbesganj Gauge Conversion (206 Km)
10 Bakhtiyarpur Flyover (4 Km) 402
§11 Katareah-Kursela Patch Doubling incl. bridge on 222
river Kosi (7 km)
12 Araria-Galgalia New Line (111 Km) 4, 415
Some of the projects falling fully/partly in the State of Bihar which have
been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Sitamarhi-Sheohar New Line (28 Km) 567
2 Sakri-Hasanpur New Line (76 Km) 735
3 Khagaria-Kusheshwarsthan New Line (42 Km) 1,511
4 Neora-Daniawan–Biharsharif - Barbigha- 2,200
Shekhpura New Line (166 Km)
5 Koderma-Tilaiya New Line (65 Km) 1,626
6 Hajipur-Sagauli New Line (151 Km) 2,087
7 Araria-Supaul New Line (96 Km) 1,605
8 Vikramshila-Katareah New Line with Bridge over 2,090
River Ganga(26 Km)
9 Pirpainti-Jasidih New Line (97 Km) excluding 2,140
Hansdiha-Godda New Line (30 Km)
10 Sonnagar – Patratu multitracking (291 Km) 5,148
11 Samastipur – Darbhanga Doubling (38 Km) 624
12 Rampur Dumra - Tal-Rajendra Pul-Additional 1,677
bridge and doubling (14 Km)
§13 Sagauli-Valmiknagar Doubling (110 Km) 1,280
14 Muzaffarpur-Sagauli Doubling (101 Km) 1,465
15 Barauni- Bachwara 3rd & 4th line (32 Km) 124
16 Son Nagar – Andal Multi tracking (749 Km) 12,334
17 Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km) 2,192
18 Bakthiyarpur-Fatuha 3rd and 4th line (24 Km) 931
During last three years (i.e. 2022-2023, 2023-24, 2024-25 and current
financial year 2025-26), total 92 Nos. of Surveys (16 New Line, 76
Doubling) falling fully/partly in the State of Bihar having a total length of
4,530 Km have been sanctioned.
Zonal Railway wise details of Railway projects are made available in
public domain on Indian Railway’s website.
Sanction of any railway project depend upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
§Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
§