UNSTARRED QUESTION NO. 5101
ANSWERED ON 24/03/2026
REPAIR OF RURAL ROADS
5101. Shri Naresh Chandra Uttam Patel:
Shri Jitendra Kumar Dohare:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) whether there has been any delay in the repair of rural roads
damaged during the last year;
(b) if so, the details thereof particularly in respect of the Fatehpur
and Etawah Lok Sabha Constituencies;
(c) whether any complaints have been received from the affected
rural communities in this regard;
(d) if so, the details of the complaints received and the action taken
thereon so far; and
(e) the manner in which the Government examines the quality of
rural road repair works and ensures proper and transparent
utilisation of the funds allocated for the purpose?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a) & (b): PMGSY roads are constructed by the State Governments
with a design life for at least 10 years. As per PMGSY guidelines,
maintenance of roads constructed under the programme is the
responsibility of the State Governments, and all road works are
covered by initial five-year maintenance contracts to be entered into
along with the construction contract, with the same contractor, as
per the Standard Bidding Document. Maintenance funds to service
the contract are required to be budgeted by the State Governments
and placed at the disposal of the State Rural Roads Development
Agencies (SRRDAs) in a separate maintenance account. On expiry of
this 5 year post construction maintenance, PMGSY roads are required
to be placed under Zonal maintenance contracts consisting of 5 year
maintenance, including renewal as per cycle, from time to time.
Page 1 of 3Regional Review Meetings (RRMs) are conducted with the nodal
departments of the State governments, at regular intervals as a
measure to monitor the progress & for effective implementation of
the PMGSY scheme in the States. Also, Area Officer visits are
organised by the Ministry for physical inspection and verification of
all the programmes run by Department of Rural Development,
including PMGSY.
As reported by the State, there is no delay in the repair of works under
PMGSY.
(c) & (d): As per Para 15.1 of the Programme Guidelines, ensuring
the quality of road works is the responsibility of the State
Governments who are implementing the programme. However, as
reported by the State government of Uttar Pradesh, no complaints
have been received from rural communities pertaining to the quality
of PMGSY works with respect to Fatehpur and Etawah Lok Sabha
Constituencies during the last year.
(e): PMGSY envisages a three-tier Quality Assurance Mechanism to
ensure the quality of road works during construction. The first tier of
this mechanism is in-house quality control at the Programme
Implementation Unit (PIU) level. Second-tier is structured as an
independent quality monitoring at the State level through State
Quality Monitors (SQMs), in which provision of regular inspection of
PMGSY works has been envisaged. The third-tier is an independent
monitoring mechanism at the Central level. Under this tier,
independent National Quality Monitors (NQMs) are engaged for
inspections of PMGSY roads, selected at random. Action Taken
Reports of the road works graded as Satisfactory Requiring
Improvement (SRI) and Unsatisfactory (U) by the State Quality
Monitors are monitored by the respective State
Governments. Similarly, for works graded as Satisfactory Requiring
Improvement (SRI) and Unsatisfactory (U) on the basis of
observations of National Quality Monitors, Action Taken Reports are
monitored and processed by the National Rural Infrastructure
Development Agency (NRIDA).
Further, the digital governance & efficiency protocol used in
PMGSY helps the Ministry in monitoring the roads sanctioned under
PMGSY. Details are as follows:
OMMAS & PMIS: Online Management, Monitoring, and Accounting
System ensures transparency (OMMAS), and Project Monitoring and
Page 2 of 3Information System(PMIS) ensure real time tracking of project
progress.
SNA SPARSH: The transition to the SNA SPARSH fund flow
mechanism ensures "Just-in-Time" release of funds to the states.
e-MARG: Routine maintenance is processed through eMARG, where
payments are contingent upon Performance-Based Maintenance
Contracts (PBMC).
GPS Tracking: Deployment of GPS-enabled Vehicle Tracking Systems
(VTS) on machinery monitors on-site construction activity.
*****
Page 3 of 3