GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
RAJYA SABHA
UNSTARRED QUESTION NO. 1065
ANSWERED ON 09.02.2026
RIVER-LINKING AND IRRIGATION PROJECTS IN MAHARASHTRA
1065 SHRI SANJAY RAUT:
Will the Minister of Jal Shakti be pleased to state:
(a) whether the Central Government has received proposals from the State Government of Maharashtra
seeking central financial assistance for river-linking and major irrigation projects to make the State drought-
free, including Daman Ganga–Ekdare–Godavari, Daman Ganga–Vaitarna–Godavari, Konkan–Godavari
Basin, Nal Ganga–Wainganga and Par–Godavari projects and the present status of their approval and fund
release;
(b) whether 29 irrigation projects have been included under the Pradhan Mantri Krishi Sinchayee Yojana and
their basin-wise progress; and
(c) whether ten out of thirteen Krishna and Godavari basin projects have been completed and the timeline for
completion of the remaining projects, including the ₹2,038 crore Nilwande-II proposal covering 64,260
hectares?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) The National Water Development Agency (NWDA) has prepared the Detailed Project Reports (DPRs)
of the Damanganga–Ekdare–Godavari, Damanganga–Vaitarna–Godavari, and Wainganga (Goshikurd)–
Nalganga (Purna–Tapi) intra-State link proposals at the request of the State Government. NWDA has also
prepared the Pre-Feasibility Report (PFR) of the North Konkan–Godavari Valley link proposal. The DPRs
and PFRs have been submitted to the State Government for further necessary action at their end.
(b) 29 irrigation projects of Maharashtra were included under Pradhan Mantri Krishi Sinchayee Yojana-
Accelerated Irrigation Benefit Program (PMKSY-AIBP). The status of the projects is given at Annexure.
(c) As per information furnished by the Government of Maharashtra, 13 projects included under
PMKSY-AIBP fall under the jurisdiction of the Maharashtra Krishna Valley Development Corporation
(MKVDC) and the Godavari Marathwada Irrigation Development Corporation (GMIDC), out of which 10
projects have been completed.
The Revised Cost Estimate (RCE) of the Upper Pravara Project (Nilwande-2) has been techno-
economically appraised in the 159th meeting of the Advisory Committee of the Department of Water
Resources, River Development & Ganga Rejuvenation on Irrigation, Flood Control and Multipurpose
Projects, at an estimated cost of ₹ 5023.24 crore.
***
1ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO. 1065 TO
BE ANSWERED IN RAJYA SABHA ON 09.02.2026 REGARDING “RIVER-LINKING AND
IRRIGATION PROJECTS IN MAHARASHTRA”
PMKSY-AIBP Completed Projects in Maharashtra
Sl. Name of Project River Basin Irrigation Potential
No. Created
(Th. Ha.)
1. Bawanthadi (IS) Godavari 27.71
2. Lower Panzara Tapi 6.79
3. Dongargaon Godavari 2.77
4. Warna Krishna 15.88
5. NandurMadhameshwar Ph-II Godavari 20.50
6. Upper Kundlika Godavari 2.80
7. Lower Dudhna Godavari 44.01
8. Khadakpurna Godavari 23.86
9. Dhom Balaakwadi Krishna 17.43
10. Wang project Krishna 5.75
11. Krishna Koyana Lift Krishna 106.74
12. Gadnadi West flowing rivers from Tapi to Tadri 5.18
13. Tillari West flowing rivers from Tapi to Tadri 6.60
14. Tarali Krishna 15.47
15. Arjuna West flowing rivers from Tapi to Tadri 7.34
16. Sangola Branch Canal Bhima 11.02
17. Bembla Godavari 51.73
18. Upper Pen Ganga Godavari 41.58
19. Lower Wardha Godavari 63.33
PMKSY-AIBP Ongoing Projects in Maharashtra
Sl. Name of Project River Basin Ultimate Irrigation Physical
No. Irrigation Potential Progress
Potential Created (%)
1. Jihe Kathapur Project Krishna 27.50 17.23 77
2. Bodwad Parisar Sinchan
Tapi 27.97 0.00 49.01
Yojana Stage-I
3. Lower Tapi stage-I Tapi 32.33 0.00 At initial stage
4. Waghur Tapi 38.57 32.06 93.00
5. West flowing rivers from
Aruna 11.70 9.10 98.00
Tapi to Tadri
6. Morna (Gureghar) Krishna 3.08 1.52 31.50
7. Lower Pedhi Tapi 16.00 0.00 64.75
8. West flowing rivers from
Nardave (Mahamadwadi) 12.28 1.09 72.59
Tapi to Tadri
9. Kudali Krishna 5.33 0.23 86.31
10. Gosikhurd (NP) Godavari 250.80 180.72 79.64
*****
2