GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 3980
ANSWERED ON 17/03/2026
ROAD PROJECTS UNDER PMGSY
3980. Shri Arun Bharti:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) the current status of Pradhan Mantri Gram Sadak Yojana-III
(PMGSY-III) in Bihar including the total road length sanctioned
and completed as of January 2026;
(b) the details and number of PMGSY road and bridge projects
currently underway in the Jamui Lok Sabha Constituency;
(c) the details of any delays in these projects in Jamui due to forest
clearances, land acquisition and contractor issues;
(d) the total funds released to Bihar under PMGSY during the last
two years and the utilization status thereof; and
(e) the steps taken to ensure the post-construction maintenance of
PMGSY roads, including the use of green technologies?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a): Under Pradhan Mantri Gram Sadak Yojana-III (PMGSY-III), a
total of 733 roads of 6,162 km & 709 bridges have been sanctioned
to the State of Bihar at the Value of Projects of Rs. 7,121 crore, out
of which, 631 roads of 5,411 km & 398 bridges have been completed
till 31.01.2026.
(b) & (c): As on 11.03.2026, a total of 9 roads of 18 km & 2 bridges
sanctioned under PMGSY-I are pending in Jamui Lok Sabha
Constituency in the State of Bihar. As per information received from
the State Government of Bihar, 09 works (07 roads and 02 bridges)
are pending in Jamui district under PMGSY-I due to forest clearance
and land issues. The details of works pending in Jamui district under
PMGSY-I due to forest clearance and land issues are given at
Annexure-I.
Page 1 of 3(d): During last two financial years, a total of Rs. 2,158.82 crore
central share has been released under PMGSY to the State of Bihar
& Rs. 4,128.64 crore expenditure (incuding the state share) has been
incurred by the State.
(e): In terms of the Rural Road Manual published by the Indian Road
Congress(IRC), roads constructed under Pradhan Mantri Gram Sadak
Yojana (PMGSY) are constructed with a design life of at least 10
years. As per PMGSY guidelines, maintenance of roads constructed
under the programme is the responsibility of the State Governments.
All PMGSY road works are covered by initial five-year maintenance
contracts to be entered into along with the construction contract,
with the same contractor, as per the Standard Bidding Document.
Maintenance funds to service the contract are required to be
budgeted by the State Governments and placed at the disposal of the
State Rural Roads Development Agencies (SRRDAs) in a separate
maintenance account. On expiry of this 5-year post-construction
maintenance, PMGSY roads are required to be placed under Zonal
maintenance contracts consisting of 5-year maintenance, including
renewal as per cycle, from time to time.
As a measure of enhancing the focus on maintenance of roads
during the defect liability period (five years from the date of
completion of the road) and streamlining the delivery of routine
maintenance of PMGSY roads, Electronic Maintenance of PMGSY
roads (eMARG), has been implemented in all the States. Payment to
the contractor is to be made through eMARG which is based on the
existing condition of road, its cross drainage works and traffic assets.
Further, States have entered into a Memorandum of
Understanding with the Ministry of Rural Development, Government of
India for providing adequate funds for the DLP and post DLP period.
The utilization of maintenance funds is reviewed in meetings held with
the States at various levels.
The Ministry has brought out a new Technology Vision
Document in 2022 for promoting green/ new technologies in PMGSY
roads construction. The implementation of these technologies is
based on Indian Road Congress (IRC) guidelines and evaluations
undertaken by premier technical institutions in the country. The
National Rural Infrastructure Development Agency (NRIDA) organizes
workshops, trainings, field demonstrations for States/ UTs to
encourage cross-learning and adoption of these technologies for
saving natural resources, enhancing speed of construction and also
for utilizing local waste.
*****
Page 2 of 3Annexure-I
Annexure referred to in reply to part (c) of Lok Sabha Unstarred
Question No. 3980 for answer on 17.03.2026
Details of works pending in Jamui district under PMGSY-I due to
forest clearance and land issues
S Bloc Pack Sanc Work Road Name / Sanct Roa Brid Road Expendi Stage of
r k age tione Type Bridge Name ion d ge Length ture (in Progress
. Nam No. d Cost Len Len Compl lakh)
N e Year (in gth gth eted
o lakh) (Km (Mtr (in km)
. s) s)
1 Chakai BR15R22013 - ROAD L056-Karhi To 49.54 0.75 0 0 0 Pending -
95 2014 Laparia Land
(TRACK40) Acquisition
2 Chakai BR15R32017 - ROAD L175-Baljori 116.73 2.138 0 1.053 44.56 Pending -
86 2018 Patjori Road to Forest
Dubariyatila Clearance
(TRACK175)
3 Chakai BR15R42017 - ROAD L170-Nontara 69.31 1.5 0 0 0 Pending -
02 2018 to Kitakasha Forest
(TRACK170) Clearance
4 Chakai BR15R32016 - ROAD L188-Bone 130.18 2.35 0 2.35 48.53 Pending -
55 2017 Road Baratarn Land
to Babudih Acquisition
(TRACK188)
5 Chakai BR15R42017 - ROAD L059-L058 To 170.1 3.486 0 0.3 91.17 Pending -
11 2018 Bhalua Forest
(TRACK43) Clearance
6 Jhajha BR15R32017 - ROAD L146-Narganjo 412.68 8.164 0 6.5 244.48 Pending -
93 2018 Simultala Main Forest
Rd. To Clearance
Barakoila Via
Pachkathia To
Paijhama
Adibasi Tola
(TRACK99)
7 Jhajha BR15R- 2020 - Bridge HL RCC Bridge 121.81 0 16.04 0 68.1 Pending -
505 2021 Over Salkhan Forest
Jorat Road Clearance
Narganjo To
Bakhoribathan
Road
8 Sono BR15R32016 - ROAD L133- 64.68 1.218 0 0.9 36.39 Pending -
83 2017 sonocharkapth Land
arPWD road Acquisition
hiratanr
(TRACK106)
9 Sono BR15R- 2020 - Bridge Construction 571.7 0 144.04 0 468.76 Progress
511 2021 of HL RCC
Bridge over
Barner in Itwa
to Barabak
Road
Total 1706.73 19.606 160.08 11.103 1001.99
*****
Page 3 of 3