GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6111
TO BE ANSWERED ON 01.04.2026
ROB PROJECTS IN JALANDHAR LOK SABHA CONSTITUENCY
6111. SHRI CHARANJIT SINGH CHANNI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether it is a fact that several Rail Over Bridge (ROB) projects in the
Jalandhar Lok Sabha Constituency in Punjab have remained pending
beyond the stipulated completion timeline and if so, the details thereof;
(b) the details of pending railway bridge works including their sanctioned
cost, present stage of construction and the reasons for delay;
(c) whether the Jalandhar Cantt. Railway Station redevelopment and
operational works have also been delayed despite earlier
announcements and project approvals and if so, the details thereof; and
(d) the revised timeline fixed by the Government for completion of these
bridge projects and full operationalisation of the said station along with
the steps taken/being taken to expedite the works?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d):Sanctioning and execution of works of Road Over Bridges/ Road
Under Bridges (ROBs/RUBs) is a continuous and ongoing process on Indian
Railways. Such works are prioritized and taken up on the basis of its
impact on safety and mobility in train operations and impact on road users.
No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
§ Page 1 of 62014-26 (Upto Jan’26) 14,024 Nos. (including 434 Nos. in
the State of Punjab)
As on 01.02.2026, 4,802 no. ROBs/RUBs are sanctioned at a cost of ₹
1,14,196 Cr on Indian Railways including 120 Nos. Road Over Bridge
(ROB)/Road Under Bridge (RUB) at a cost of ₹ 1,848 crore in the State of
Punjab which are at various stages of planning and execution. In
Jalandhar Lok Sabha Constituency, 19 Nos. ROBs/RUBs works are
sanctioned at a cost of ₹ 301 Cr. The details are as under:
# Name of work ROB/ Remarks
RUB
1 LC No. C-8 at km. 9/2-3 on RUB Work held up due to law and
Phillaur- Lohian Khas order issues in the area.
section.
2 LC No. C-48 at km. 30/0-1 on RUB
Jalandhar-Nakodar section.
3 LC No. C-28 at km. 19/4-5 on RUB
Jalandhar-Nakodar section.
4 LC No. C-13 on Jalandhar- RUB
Pathankot Section
5 LC No.C-19 on Jalandhar- RUB
Pathankot Section
6 LC No.C-43 on Jalandhar- RUB
Hoshiarpur Section
7 LC No. B-67A on Jalandhar ROB Preparation of GAD has
Cantt-Jalandhar City been taken up.
8 LC No. S-4 between ROB Preparation of GAD has
Jalandhar-Jamsherkhason been taken up.
Jalandhar City –Nakoder.
9 LC no. S-79 on Ludhiana- RUB Work of railway portion
Jalandhar section completed. Work of
approacheshas been taken
up
10 LC No.S-78 at KM 410/23-25 ROB Preparation of GAD has
on Ludhiana-Jalandhar been taken up.
section
11 LC no. S-70 at Km.426.236 RUB Work has been taken up.
on Sahnewal-Amritsar Box casting is complete.
section
12 LC No.S-88 at KM 389/29-31 ROB Preparation of GAD has
Ludhiana-Jalandhar section. been taken up.
Page 2 of 613 LC No.S-84 at KM398/970 on RUB GAD has been approved.
Ludhiana-Jalandhar section Work has been taken up
14 LC no. S-63 at Km 433/27-28 RUB Preparation of GAD has
on Jalandhar-Beas section been taken up.
15 LC No.S-90 at KM387/641 in RUB Preparation of GAD has
Ludhiana-Jalandhar section been taken up.
16 LC NO.S-85 at KM 396/488 in RUB Preparation of GAD has
Ludhiana-Jalandhar section been taken up.
17 LC NO.S-86 at KM 394/114 in RUB Preparation of GAD has
Ludhiana-Jalandhar section been taken up.
18 LC NO.S-87 at KM391/447 in RUB Preparation of GAD has
Ludhiana-Jalandhar section been taken up.
19 LC C-7 at KM 4/13-14 in RUB Preparation of GAD has
Jalandhar-Nakodar section. been taken up.
Completion of any ROB/RUB work depends on various factors like,
fixing of approach alignment, approval of General Arrangement Drawing
(GAD), land acquisition, removal of encroachment, shifting of infringing
utilities, statutory clearances from various authorities, law and order
situation in the area of project / work sites, number of working months in a
year for particular project / work sites due to climatic conditions etc. All
these factors affect the completion time of the projects / works.
Railways have taken following measures to expedite the progress of
work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure drawings for various combinations
of span, skewness and width of road on Railway portion has been
done to avoid delays during the design approval. This has been issued
Page 3 of 6in the form of compendium, which can be directly adopted for Road
Over Bridge across Railway lines for expeditious planning.
Station Re-development
Jalandhar Cantt. railway station has been identified for redevelopment
under Amrit Bharat Station Scheme. The redevelopment works of Jalandhar
Cantt. railway station has been sanctioned.
At Jalandhar Cantt. Station, the structural works for the main entry
station building, second entry station building, improvement of platform
surface, structural work of platform shelters, structural work of through
roof, and structural work of foot over bridge and air concourse have been
completed. The works for the finishing of main entry building, second entry
building, platform shelters, foot over bridge, air concourse, through roof
and improvement of circulating area have been taken up.
Amrit Bharat Station Scheme involves preparation of master plans
and their implementation in phases to improve the stations. The master
planning, keeping in view the necessity at each station includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
Page 4 of 6• Amenities for Divyangjans
• Better passenger information systems
• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity, phasing and
feasibility and creation of city centre at the station in the long term.
The name of stations identified under Amrit Bharat Station Scheme in
Punjab is as following:
State No. of Name of Stations
Stations
Punjab 30 Abohar, Amritsar, Anandpur Sahib, Beas,
Bhatinda Jn,
Dhandari Kalan, Dhuri, Fazilka, Firozpur Cantt,
Gurdaspur, Hoshiarpur, Jalandhar Cantt Jn,
Jalandhar City Jn, Kapurthala, Kot Kapura Jn,
Ludhiana Jn, Malerkotla, Mansa, Moga,
Muktsar, Nangal Dam, Pathankot Cantt.,
Pathankot City, Patiala, Phagwara Jn, Phillaur
Jn, Rup Nagar, Sahibzada Ajit Singh Nagar
Mohali, Sangrur, Sirhind
Till now, works of 03 stations (i.e. Anandpur Sahib, Muktsar, Sahibzada
Ajit Singh Nagar Mohali) have been completed in Punjab.
The activities for development at other stations have also been taken up
at good pace in Punjab and progress of some of the stations is as given
below:
Sirhind station: The works of improvement of station building,
entrance porch, AC waiting room with toilet, improvement of second
Page 5 of 6class waiting room, toilet block, circulating area, parking, entry/exit
gate, lighting and signage have been completed. The works of lift and
12 m Foot Over Bridge have been taken up.
Gurdaspur station: The works of station building, platform shelter,
improvement of platform surface, waiting room, toilet, circulating
area, porch and lighting have been completed. The works of new
platform no. 2, booking cum waiting hall, circulating area, parking,
entry/exit gate on main entry and second side and 12 m Foot Over
Bridge have been taken up.
Patiala station: The works of improvement of station building,
entrance porch, platform shelter, improvement of waiting hall, retiring
room, toilet, circulating area, parking, entry/exit gate and signage
have been completed. The works of platform surfacing, development
of second entry, lift and 12 m Foot Over Bridge have been taken up.
Development / Upgradation of stations is complex in nature involving
safety of passengers & trains and requires various statutory clearances
such as fire clearance, heritage, tree cutting, airport clearance etc. The
progress also gets affected due to brownfield related challenges such as
shifting of utilities (involving water/sewage lines, optical fibre cables, gas
pipe lines, power/signal cables, etc.), infringements, operation of trains
without hindering passenger movement, speed restrictions due to works
carried out in close proximity of tracks and high voltage power lines, etc.
and these factors affect the completion time.
*****
Page 6 of 6