UNSTARRED QUESTION NO. 4291
TO BE ANSWERED ON 18.03.2026
SANCTIONED RAILWAY PROJECTS IN UTTAR PRADESH
4291. SHRI JAI PRAKASH:
Will the Minister of RAILWAYS be pleased to state:
(a) the details and status of Railway projects sanctioned during the last
five years in Uttar Pradesh; and
(b) the details of the railway projects lagging behind their schedule
including the reasons thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) and (b): Budget allocation for infrastructure projects and safety works,
falling fully/partly in the State of Uttar Pradesh is as under:
Period Outlay
2009-14 ₹1,109 crore/year
2025-26 ₹19,858 crore (Nearly 18 times)
Track Construction:
The details of constructing of new tracks falling fully/partly in the State of
Uttar Pradesh during 2009-14 and 2014-25 is as under:
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 996 Km 199 Km/year
2014-25 5272 Km 479 Km per year (More than 2
times)
§Projects Sanctioned:
As on 01.04.2025, 49 projects (10 New Line, 02 Gauge Conversion and 37
Doubling) of 3,807 Km length, costing ₹62,360 crore falling fully/partly in
the State of Uttar Pradesh are sanctioned. The summary is as under:-
Category No of Total Length Exp
Projects Length Commissioned upto
(km) (km) Mar'25
(Rs. in Cr.)
New Line 10 1227 340 10517
Gauge Conversion 02 67 - 281
Doubling/Multitracking 37 2513 983 19813
Total 49 3807 1323 30611
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the
State of Uttar Pradesh are as under:
S. Cost
Project
No. (Rs. in Cr.)
1 Etawah-Mainpuri New Line (58 Km) 313
Bahraich-Nanpara-Nepal Ganj Gauge Conversion (56
2 342
Km)
3 Ballia-Ghazipur city Doubling (65 Km) 650
4 Ghazipur city-Tarighat New Line (17 Km) 1766
5 Gonda-Gorakhpur Loop Gauge Conversion (260 Km) 863
6 Gonda-Bahraich Gauge Conversion (60 Km) 318
7 Barabanki-Akbarpur Doubling (161 Km) 1700
Kaptanganj-Thawe-Chhapra Gauge Conversion (234
8 819
Km)
9 Pilibhit-Shahjahanpur Gauge Conversion (83 Km) 589
10 Indara-Dohrighat Gauge Conversion (34 Km) 213
11 Lucknow-Pilibhit Gauge Conversion (263 Km) 1634
12 Bhadoi-Janghai Doubling (31 Km) 168
13 Lahota-Bhadoi Doubling (39 Km) 184
14 Meerut-Muzaffarnagar Doubling (55 Km) 430
15 Phaphamau-Prayagraj Doubling (14 Km) 212S. Cost
Project
No. (Rs. in Cr.)
16 Muzaffarnagar–Tapri Doubling (52 Km) 525
17 Utretia-Raibareilly Doubling (66 Km) 662
18 Raibareilly-Amethi Doubling (60 Km) 668
19 Alamnagar-Utretia Doubling (20 Km) 358
20 Bhimsen—Jhansi Doubling (206 Km) 2620
Domingarh-Gorakhpur-Kusumhi - 3rd Line and
21 508
Gorakhpur-Nakaha Jungle Doubling (21 Km)
22 Malhaur-Daliganj Doubling (13 Km) 183
23 Ruma Chakeri- Chandari 3rd Line (13 Km) 177
Bareilly-Pilibhit-Tanakpur Gauge Conversion (102
24 313
Km)
25 Rosa-Sitapur Cantt-Burhwal Doubling (181 Km) 2094
26 Jaunpur- Akbarpur (Tanda) Doubling (77 Km) 676
27 Ramna- Renukut-Singrauli Doubling (160 Km) 2436
28 Janghai- Phaphamau Doubling (47 Km) 414
29 Varanasi-Madhosingh-Prayagraj Doubling (120 Km) 2018
30 Karaila Road- Shaktinagar Doubling (32 Km) 763
31 Deoband (Muzzafarnagar)-Roorkee (27 Km) 1289
32 Agra-Etawah New Line(110 Km) 427
33 Phephna-Indara, Mau-Shahganj Doubling (150 Km) 1778
Ongoing projects:
Some of the projects falling fully/partly in the State of Uttar Pradesh which
have been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Barabanki-Burhwal 3rd Line (27 Km) 426
2 Burhwal- Gonda Kacheri 4th line (56 Km) 796
3 Burhwal-Gonda 3rd Line (62 Km) 1118
4 Bahraich- Khalilabad New Line (240 Km) 4940
5 Katra-Ayodhya Dham Doubling (10 Km) 466
6 Pt. Deen Dayal Upadhyaya- Prayagraj 3rd Line (150 2649
Km)
7 Billi-Chunar Doubling (102 Km) 1424
8 Chhapra-Ballia Doubling (65 km) 1046
9 Unchhar-Amethi New Line (66 Km) 122910 Etah-Kasganj New Line ( 29 Km) 389
11 Gorakhpur- Valmikinagar Doubling (96 Km) 1121
12 Varanasi-Pt. Deen Dayal Upadhyaya 3rd and 4th Line 2464
(15 Km)
13 Jhansi-Khairar-Manikpur & Khairar-Bhimsen 4330
Doubling (431 Km)
14 Sahjanwa-Dohrighat New Line (81 Km) 1320
15 Kuberpur-Yamuna Bridge 3rd line (10 Km) 170
16 Prayagraj (Iradatganj)-Manikpur 3rd Line (84 km) 1508
17 Dilkusha-Malhaur 3rd Line (8 km) 164
18 Bypass/Chord line at Ayodhya Cantt. (between 97
Salarpur-Masodha) (6 Km)
19 Didarganj - Shahganj - Bilwai Chord line (6 km) 137
20 Varanasi Shivpur 3rd line (6 Km) 76
21 Jaunpur Jn.- Zafarabad Doubling (6 Km) 177
22 Bhatni - Aurnihar Doubling (117 km) 2529
23 Mathura-Jhansi 3rd line (274 km) 5924
24 Agra Fort and Bandikui Doubling (150 km) 988
25 Janghai-Pratapgarh- Amethi Doubling (87 km) 1197
26 Barabanki-Malhaur - 3rd & 4th Line (33 km) 407
27 Phaphamau-Unchahar Doubling (72 km) 971
28 Aunrihar - Varanasi City 3rd Line (31 Km) 76
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
ROB/RUBs
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
Railway. Such works are prioritised and taken up on the basis of its impact
on safety in train operations, mobility of trains & impact for road users and
feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto Jan’26) 14,024 Nos. ( including 1,702 Nos. of
ROBs/ RUBs in the state of Uttar
Pradesh)As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at cost of ₹
1,14,196 Cr on Indian Railways including 778 Nos. Road Over Bridge
(ROB)/Road Under Bridge (RUB) are sanctioned at cost of ₹ 15,170 Cr in
State of Uttar Pradesh which are at various stages of planning and
execution.
Completion of any ROB/RUB work depends on various factors like, fixing of
approach alignment, approval of General Arrangement Drawing (GAD), land
acquisition, removal of encroachment, shifting of infringing utilities,
statutory clearances from various authorities, law and order situation in
the area of project / work sites, number of working months in a year for
particular project / work sites due to climatic conditions etc. All these
factors affect the completion time of the projects / works.
Further, Railways have taken following measures to expedite the progress
of work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure drawings for various
combinations of span, skewness and width of road on Railway
portion has been done to avoid delays during the design approval.
This has been issued in the form of compendium, which can be
directly adopted for Road Over Bridge across Railway lines for
expeditious planning.Amrit Bharat Stations:
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.So far, 1,338 stations have been identified for development under this
scheme, out of which 157 stations are located in Uttar Pradesh. The names
of stations identified for development under Amrit Bharat Station Scheme
in Uttar Pradesh are as following:
State No. of Name of Stations
Stations
Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh Jn,
Pradesh Akbarpur Jn, Aligarh, Amethi, Amroha, Anand
Nagar Jn., Aonla, Ayodhya Dham Junction,
Azamgarh, Babatpur, Bachhrawan, Badaun,
Badshahnagar, Badshahpur, Baheri, Bahraich,
Balamau Jn., Ballia, Balrampur, Banaras, Banda,
Barabanki Jn, Bareilly, Bareilly City, Barhni,
Basti, Belthara Road, Bhadohi, Bharatkund,
Bhatni, Bhuteshwar, Bijnor, Bulandsahar,
ChandauliMajhwar, Chandausi, Chilbila,
Chitrakutdhamkarwi, Chopan, Chunar Jn.,
Daliganj, Darshannagar, Deoria Sadar, Dhampur,
Dildarnagar, Etawah Jn., Farrukhabad,
Fatehabad, Fatehpur, Fatehpur Sikri, Firozabad,
Gajraula, Garhmuktesar, Gauriganj, Ghatampur,
Ghaziabad, Ghazipur City, Gola Gokarnath,
Gomtinagar, Gonda, Gorakhpur, Govardhan,
Govindpuri, Gursahaiganj, Haidergarh, Hapur,
Hardoi, Hathras City, Idgah Agra Jn, Izzatnagar,
Janghai Jn, Jaunpur City, Jaunpur Jn, Kannauj,
Kanpur Anwarganj, Kanpur Bridge Left Bank,
Kanpur Central, Kaptanganj Jn, Kasganj Jn,Kashi, Khalilabad, Khorason road, Khurja Jn.,
Kosi Kalan, Kunda Harnamganj, Lakhimpur,
Lalganj, Lalitpur Jn, Lambhua, Lohta, Lucknow
(Charbagh) NR, Lucknow city, Lucknow Jn.
(NER), Maa Belha Devi Pratapgarh Junction,
Maghar, Maharaja Bijli Pasi, Mahoba Jn, Mailani
Jn, Mainpuri Jn, Malhaur, Manak Nagar, Manikpur
Jn, Mariahu, Mathura Jn, Mau Jn, Meerut City Jn,
Mirzapur, Modinagar, Mohanlalganj, Moradabad
Jn, Muzaffarnagar, Nagina, Najibabad Jn, Orai,
Panki Dham, Phaphamau Jn, Phulpur, Pilibhit Jn,
Pokhrayan, Prayag Jn, Prayagraj Jn, Pt. Deen
Dayal Upadhyay Jn , Rae Bareli Jn, Raja Ki
Mandi, Ramghat Halt, Rampur Jn, Renukoot,
Saharanpur Jn., Salempur, Seohara, Shahganj Jn,
Shahjahanpur, Shamli, Shikohabad Jn., Shivpur,
Siddharth nagar, Sitapur Jn., Sonbhadra, Sri
Krishna Nagar, Sultanpur Jn, Suraimanpur,
Swaminarayan Chappia, Takia, Tulsipur, Tundla
Jn., Ujhani, Unchahar, Unnao Jn, Utraitia Jn,
Varanasi Cantt., Varanasi City, Vindhyachal,
Virangana Lakshmibai Jhansi, Vyasnagar,
Zafarabad
Completed Stations:
Development works at railway stations under Amrit Bharat Station
Scheme in Uttar Pradesh have been taken up at a good pace. Till now,
works of 23 stations have been completed. The name of stations
completed in Uttar Pradesh are as following:No. of
State Name of stations
stations
Uttar 23 Ayodhya Dham Junction, Balrampur, Bareilly City,
Pradesh Bijnor, Fatehabad, Fatehpur, Gola Gokarnath,
Gomtinagar, Govardhan, Govindpuri, Hathras City,
Idgah Agra Jn, Izzatnagar, Khalilabad, Mailani Jn,
Panki Dham, Pokhrayan, Ramghat Halt, Saharanpur
Jn., Siddharth nagar, Suraimanpur, Swaminarayan
Chappia, Ujhani
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Badaun station: The works of parking area, toilet, platform shelter,
platform surfacing and waiting hall have been completed. The work of
improvement to station building has been taken up.
Ghaziabad station: The structural works of station building at main
entry side and second entry side, foundation work of new Foot Over
Bridge-B at Tundla end, roof plaza, extension work of existing Foot Over
Bridge-A, finishing work of electrical substation at main entry side and
second entry side, Magistrate building, Government Railway Police and
Railway Protection Force buildings have been taken up
Rampur station: The works of new station building, platform shelter,
platform surfacing, booking office, waiting hall and toilet have been
completed. The works of circulating area and Foot Over Bridge have
been taken up.
Shahjahanpur Station: The works of platform shelter and platform
surfacing at platform no. 1 and 2/3 have been completed. The works ofimprovement of station building, new station building at second entry,
circulating area and Foot Over Bridge have been taken up.
Shikohabad Junction station: The works of new station building,
platform surfacing of platform no. 1/2, improvement of circulating area,
parking and Divyangjan facilities have been completed. The work of 12
m Foot Over Bridge has been taken up
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category of
station/condition/traffic handled etc.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not work-wise, or station-
wise, or constituency wise or state-wise. Uttar Pradesh is covered under
the jurisdiction of five railway zones, namely East Central Railway,
Northern Railway, North Central Railway, North Eastern Railway and West
Central Railway. For these zones, an allocation of ₹ 3,794 crore has been
made for the financial year 2025-26, out of which an expenditure of ₹ 3,694
crore (up to February, 2026) has been incurred so far.
*****