GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4204
TO BE ANSWERED ON 18.03.2026
SARDARSHAHAR TO HANUMANGARH RAIL LINE SURVEY (RAJASTHAN)
†4204. SHRI AMRA RAM:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the survey for the construction of a new railway line from
Sardarshahar to Hanumangarh in Rajasthan along with the action taken
in thereon;
(b) whether the proposed rail connectivity from Jaipur to Hanumangarh and
Sri Ganganagar and further up to international border with Pakistan are
strategically important after the completion of the construction of
railway line from Fatehpur to Ratangarh thus providing direct service for
transportation or movement of materials and troops from Agra and
Jaipur saving both time as well transportation costs; and
(c) whether the Government proposes to conduct a survey and begin
construction of the said railway lines and if so, the details thereof and if
not, the reasons therefor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Sardarshahar and Hanumangarh are existing railway stations on
Indian Railway Network and already connected via Ratangarh and
Sadulpur. Also, Jaipur to Hanumangarh and Sri Ganganagar are already
having rail connectivity via Ringas, Sikar, Fatehpur Sekhawati, Churu and
Sadulpur.
...2/-
§-:2:-
Surveys for Sardarshahar - Hanumangarh New line (149 km) and Ratangarh
– Fatehpur Sekhawati (39 Km) new line were conducted but the projects
have low traffic projections.
Rajasthan
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Rajasthan is as under:-
Period Outlay
2009-14 ₹682 crore/year
2025-26 ₹9,960 crore (Nearly 15 times)
Track Construction:
The details of constructing new track falling fully/partly in the State of
Rajasthan during 2009-14 and 2014-25 is as under:-
Period New Track Average commissioning of new
Commissioned tracks
2009-14 798 Km 159.60 Km/year
2014-25 3,815 Km 346.82 Km/year (More than 2
times)
Project Sanctioned:
As on 01.04.2025, 28 projects (13 New Lines, 05 Gauge Conversion and 10
Doubling), covering a total length of 3,409 Km, costing ₹43,918 crore,
falling fully/partly in Rajasthan are sanctioned. The summary is as under:-
...3/--:3:-
Category No. of Total Length Expenditure
projects Length Commissioned (₹ in Cr)
(in Km) (in Km)
New Lines 13 981 196 5769
Gauge
5 1252 788 6829
Conversion
Doubling/
10 1176 254 6357
Multitracking
Total 28 3,409 1,238 18,954
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railway’s website.
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the
State of Rajasthan are as under:
S.No. Name of Project Latest Cost
(₹ in crore)
1 Bangurgram-Ras New Line (28 km) 175
2 ThaiyatHamira-Sonu New Line (58 Km) 350
3 Suratpura- Sriganganagar Gauge Conversion (241 896
Km)
4 Sadulpur-Bikaner &Ratangarh-Degana Gauge 886
Conversion (438 Km)
5 Jaipur -Churu & Sikar-Loharu Gauge Conversion 1105
(320 Km)
6 Bhagat ki Kothi-Luni Doubling (28 Km) 128
...4/--:4:-
S.No. Name of Project Latest Cost
(₹ in crore)
7 Rani-Keshav Ganj Doubling (59 Km) 290
8 Guriya-Marwar &Karjoda-Palanpur Doubling (49 Km) 251
9 Rani-Marwar Doubling (52 Km) 346
10 Abu Road-Swaroop Ganj Doubling (26 Km) 195
11 Abu Road-Sarotra Road Doubling (24 Km) 152
12 Alwar-Bandikui Doubling (60 Km) 450
13 Ajmer-Bangurgram Doubling (48 Km) 375
14 Bangurgram-Guriya Patch Doubling (47 Km) 395
15 Degana-Rai ka Bagh Doubling (146 Km) 809
16 Bina-Kota Doubling (283 Km) 2476
17 Nimach-Chittaurgarh Doubling (56 Km) 560
18 Dausa-Gangapur City Doubling (93 Km) 950
19 Phulera-Degana Doubling (108 Km) 702
20 Churu-Ratangarh Doubling (43 Km) 423
Ongoing projects:
Some of the projects falling fully/partly in the State of Rajasthan which
have been taken up are as under:
S.No. Name of Project Cost
(₹ in crore)
1 Nimach-Badi Sadri New Line (48 Km) 495
2 Taranga Hill-Abu Road New Line (116 Km) 2798
...5/--:5:-
S.No. Name of Project Cost
(₹ in crore)
3 Ramganjmandi-Bhopal New Line (277 Km) 5073
4 Pushkar-Merta New Line (51 Km) 800
5 Ringus-Khatu Shyam Ji New Line (17 Km) 254
6 Merta city-Ras New Line & Bye Pass at Merta Road 947
Station (56 Km)
7 Gwalior-Sheopurkalan Gauge Conversion with 2913
extension to Kota (284 Km)
8 Dholpur-Sirmuttra Gauge Conversion with 747
extension to Gangapur City (145 Km)
9 Mavli-DevgarhMadariya Gauge Conversion (83 Km) 969
10 Mathura-Jhansi 3rd Line (274 Km) 5924
11 Agra Fort-Bandikui Doubling (150 Km) 988
12 Sawaimadhopur-Jaipur Doubling (131 Km) 1204
13 Churu-Sadulpur& Luni-Bhildi Doubling (330 Km) 3554
14 Ajmer-Chanderiya Doubling (178 Km) 1635
15 Bye Pass line at Sawaimadhopur (14 Km) 304
16 Rewari-Khatuwas Doubling (28 Km) 352
17 Khatuwas-Narnaul Doubling (24 Km) 313
18 Bye Pass line at Marwar (4 Km) 71
19 Bypass line at Churu (5 Km) 63
20 Bypass line at Samdari (1 Km) 26
21 Ramdevra-Pokhran new line (13 Km) 189
22 Lalgarh-Bikaner East Cabin doubling (11 Km) 279
23 Ringas-Sikar Doubling (50 Km) 470
24 Umra-Debari Doubling (25 Km) 492
...6/--:6:-
In last three years, 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 59 surveys (25 new line & 34 doubling) of total length 5,666 Km
falling fully/partly in the State of Rajasthan have been sanctioned.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway's own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
...7/--:7:-
Train Connectivity
Presently, Hanumangarh and Sriganganagar are connected to Jaipur by 08
Express train services each. These services are listed below:-
● Jaipur to Hanumangarh
SN Train Number and Name
1 20497/20498 Rameswaram - Firozpur Cant Express
2 54703/54704 Bathinda - Jaipur Express
3 14701/14702 Shri Ganganagar - Bandra Terminus Express
4 22981/22982 Kota - Shri Ganganagar Express
● Jaipur to Sriganganagar
SN Train Number and Name
1 20471/20472 Sriganganagar - Puri Express
2 14701/14702 Sriganganagar - Bandra (T) Express
3 22981/22982 Kota - Sriganganagar Express
4 22997/22998 Jhalawar City - Sriganganagar Express
Besides, introduction of train services on any route/section, which is an on-
going process, depends on various factors which include:
● Capacity of that section.
● Availability of path.
● Availability of required rolling stock.
● Availability of matching infrastructure for rolling stock.
● Maintenance requirement of railway tracks and other assets.
*****