GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3059
TO BE ANSWERED ON 11.03.2026
SEVOKE-RANGPO RAILWAY PROJECT
3059. SHRI RAJU BISTA:
Will the Minister of RAILWAYS be pleased to state:
(a) the current status/completion stage of the Sevoke Rangpo Railway
Project including the expected date of its completion;
(b) whether any feasibility studies/surveys/proposals have been undertaken
by the Railways for providing rail connectivity from the Sevoke Rangpo
stations to Gangtok, Kalimpong and Darjeeling and if so, the details and
present status thereof; and
(c) the details of the amount of funds incurred on the Sevoke Rangpo
Railway Project till date and the estimated total cost of the project
upon completion?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Ministry of Railway has taken up the work of Sevoke-Rangpo (44
Km.) new line project to connect Sikkim. The latest estimated cost of the
project is ₹11,973 crore. An expenditure of ₹8,358 crore has been incurred
upto March, 2025, with an outlay of ₹2,940 crore for the year 2025-26.
Sevoke-Rangpo project is one of the most difficult railway projects as the
terrain passes through young Himalayas, which are full of geological
surprises and numerous problems. This section predominantly involves
tunnelling of 39 Km length (14 tunnels).
§Status of Tunnels:
Sr. Tunnel No Length(km) Between Status
No Stations
1 T-1 4.2 Sivok-Riyang Completed
2 T-2 0.9 Sivok-Riyang Completed
3 T-3 1.2 Sivok-Riyang Completed
4 T-4 3.9 Sivok-Riyang Completed
5 T-5 2.1 Sivok-Riyang Completed
6 T-6 3.9 Riyang- Completed
Rangpo
7 T-7 3.1 Riyang- Completed
Rangpo
8 T-8 4.1 Riyang- Work taken up
Rangpo
9 T-9 0.5 Riyang-Melli Completed
10 T-10 5.3 Melli-Rangpo Work taken up
11 T-11 3.2 Riyang- Completed
Rangpo
12 T-12 1.4 Riyang- Completed
Rangpo
13 T-13 2.6 Riyang- Completed
Rangpo
14 T-14 1.9 Melli-Rangpo Completed
Status of Major Bridges:
Sr Bridge No(River Length(m) Between Status
No Name) Stations
1 Br-02(Andheri Jhora) 174.6 Sivok- Completed
Riyang2 Br-03(Kali-Jhora) 369.4 Sivok- Completed
Riyang
3 Br-04(Sweti-Jhora) 70.1 Sivok- Completed
Riyang
4 Br-05(Riyang-Khola) 61 Sivok- Completed
Riyang
5 Br-06(Rambi-Khola) 138 Sivok- Completed
Riyang
6 Riyang- Completed
Br-08(Gail Khola) 76.2
Rangpo
7 Br-09(Teesta River) 229.2 Riyang- Work taken up
Melli
8 Br-10(Melli Yard) 133 Melli Work taken up
9 Br-13( Bhalu Khola) 30.5 Riyang- Completed
Rangpo
10 Br-14(Tar Khola) 67.1 Riyang- Completed
Rangpo
11 Br-15(Tumlong 238.8 Riyang- Completed
Khola) Rangpo
12 Br-16(SukhiyaKhola) 207 Riyang- Work taken up
Rangpo
13 Br-17(Rangpo Chu) 426.8 Rangpo Work taken up
Status of Stations:
Sr No Station Status
1 Sivok Completed
2 Riyang Work taken up
3 Teesta Bazaar Work taken up
4 Melli Work taken up5 Rangpo Work taken up
There are several challenges that affected the completion of the project
works. Some of these are as under:
i. Encounter of difficult rock strata in tunnels T8 & T10.
ii. Proposal for diversion of Forest land, 3.26 Ha (for Riyang Yard) and
3.12 Ha (for Melli Yard & Bridge-9) are pending with The Government
of West Bengal since March, 2024 which has affected the completion
of the project.
Survey for Rangpo – Gangtok New Line (40 Km) has been completed and
preparation of Detailed Project Report (DPR) has been taken up. Further,
Darjeeling is already connected to existing Indian Railway Network and
Rail connectivity to Kalimpong is served by Teesta Bazar Station,
Northeast Frontier Railway which is nearly 14 km away.
After preparation of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines depend upon appraisals and approvals by
various stakeholders.
Further, during the last three years i.e. 2022-23, 2023-24, 2024-25 and the
current financial year 2025-26, 23 surveys (14 New Line, and 9 Doubling) of
total length 2,519 Km falling fully/ partly in North East Region have been
sanctioned.
Completion of Railway project/s depends on various factors which include
the following: Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned authorities
for expeditious land acquisition, forestry and Wildlife clearances and
for resolving other issues pertaining to projects.
*****