GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5988
TO BE ANSWERED ON 01.04.2026
SILVERLINE PROJECT IN KERALA
5988. ADV. ADOOR PRAKASH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is considering a new high speed rail corridor in
Kerala as an alternative to the SilverLine project proposed by the State
and if so, the details thereof;
(b) whether the Government has received any communication from the
State Government regarding withdrawal from the proposed SilverLine
project and if so, the details thereof; and
(c) whether the Government has received any proposal from the State of
Kerala for Regional Rapid Transport System (RRTS) project and if so,
the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): To strengthen the railway network in Keralam, the following
surveys have been sanctioned :
SN Route Length (Km)
1 Shoranur-Mangalore 3rd & 4th Line 307
2 Coimbatore-Shoranur 3rd & 4th line 99
3 Shoranur – Ernakulam 3rd Line 106
4 Ernakulam-Kayankulam 3rd line (via 115
Kottayam)
5 Kayankulam-Thiruvanathapuram 3rd Line 105
6 Thiruvanathapuram-Nagercoil 3rd Line 71
7 Mararikulam - Alappuzha Doubling 13
Page 1 of 6
§After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines cannot be fixed.
SilverLine from Thiruvananthapuram to Kasaragod in Keralam was
proposed for construction by Kerala Rail Development Corporation Limited
(KRDCL), a Joint Venture company of State Government of Keralam (51%)
and Ministry of Railways (49%) for development. After survey, KRDCL has
submitted Detailed Project Report (DPR) of the Project to the Ministry of
Railways for approval. The proposed alignment was running parallel to and
in close proximity to Indian Railway (IR) lines. There were many
deficiencies in the DPR. Therefore, KRDCL has been advised by Southern
Railway to address those deficiencies and prepare revised DPR.
Further, Ministry of Housing & Urban Affairs (MoHUA) being nodal Ministry
for RRTS has informed that no Detailed Project Report (DPR) of RRTS
connectivity has been submitted to Central Government by the State
Government of Keralam.
Keralam
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projectsand safetyworks, falling fully/partly
inthe Stateof Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2025-26 ₹3,042 crore (more than 8
times)
Page 2 of 6Projects sanctioned:
As on 01.04.2025, 06 projects (02 new line and 04 doubling) of 266 km
length, costing ₹9,415crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Balanc Expenditure
projects Length Commission e to upto March
ed comple 2025
te ( ₹in Crore)
146 309
New line 02 0 km 146 km
km
Doubling / 120
04 26 km 94 km 2,941
multitracking km
266 3,250
Total 06 26 km 240 km
km
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in
Keralam are as under:
S. Cost (₹ in
Project
No. Crores)
1. Dindigul-Pollachi-Palghat & Pollachi-
1,360
Coimbatore gauge conversion (217 km)
2. Quilon-Tirunelveli-Tiruchendur gauge
1,122
conversion (357 km)
3. Mulanturutti-Kuruppantara doubling (24 km) 303
Page 3 of 64. Chenganur-Chingavanam doubling (27 km) 436
5. Ambalapuzha-Haripad doubling (18 km) 346
6. Kurruppanthara-Chingavanam doubling (27 km) 749
Ongoing Projects:
Some of the projects falling fully/partly in Keralam which have been taken
up are as under:
S. No. Project Cost (₹ in Crores)
1. Tirunnavaya –Guruvayur new line (35 138
Km)
2. Angamali-Sabarimala new line (111 3,801
km)
3. Ernakulam-Kumbalamdoubling (8 km) 595
4. Kumbalam-Thuravur Patch doubling 803
(16 km)
5. Trivandrum- Kanyakumari doubling (87 3,786
km)
6. Shoranur - Vallathol doubling (10 km) 367
7. Palakkad Town – Parli bypass line (2 164
Km)
8. Alappuzha- Ambalapuzha doubling (13 324
Km)
9. Turavur – Mararikulam doubling (21 451
km)
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 476 ha
Land Acquired 65 ha (14%)
Balance Land to be acquired 411 ha (86%)
Page 4 of 6Railway had deposited ₹1,975 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:-
S. Name of the project Total Land Balance
No. land acquired Land to be
required (in Ha) acquired
(in Ha) (in Ha)
1. Angamali - Sabarimala new line (111 416 24 392
km)
2. Ernakulam-Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam-Turavur Patch doubling 10 9 1
(16 km)
4. Shoranur - Vallathol doubling (10 km) 5 0 5
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Sanctioning of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Page 5 of 6Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
Page 6 of 6