GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 373
TO BE ANSWERED ON 18.03.2026
SOUTH COAST RAILWAY ZONE HQ AT VISAKHAPATNAM
*373. SHRI Y S AVINASH REDDY:
Will the Minister of RAILWAYS be pleased to state:
(a) the year-wise details of fund allocation and expenditure for
establishment of South Coast Railway Zone HQ at Visakhapatnam since
its announcement;
(b) the current status of land acquisition and administrative infrastructure
development as on February 2026; and
(c) the details of the timeline for the phased operationalization of the zone?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): A Statement is laid on the Table of the House.
*****
§STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF STARRED
QUESTION NO.373 TO BE ANSWERED ON 18.03.2026 IN LOK SABHA
(a) to (c): For setting up headquarters of new South Coast Railway (SCoR),
52.2 Acre land at Mudasarlova, Visakhapatnam has been handed over by
Government of Andhra Pradesh to Railways in August 2024. Foundation
stone for new South Coast Zone has been laid in Jan 2025.
The work of “Setting up of South Coast Railways’ Zone HQ” has been
sanctioned at cost of ₹106.89 Cr. Tender for SCoR HQ office building has
been awarded and the construction for this new headquarters office
building has been taken up. Foundation work has been completed and
balance works are in progress. An allocation of ₹55.0 Cr. was made during
year 2025-26 and an expenditure of ₹32.31 Cr. has been incurred so far.
In addition, works costing about ₹157.93 Cr. for construction of associated
works, residential accommodation etc. have also been sanctioned.
In the meanwhile, to operationalise SCoR HQ, a Memorandum of
Understanding has been signed with Vishakhapatnam Metropolitan
Regional Development Authority (VMRDA)/Government of Andhra Pradesh
for hiring of building for makeshift SCoR HQ. This makeshift office
accommodation at “The Deck” at VMRDA is also ready for occupation.
Other steps taken to operationalise SCoR HQ are as under:
General Manager and Senior officers from various disciplines have
been posted.
Control Office setup has also been created at the makeshift SCoR
headquarter.
Options have been invited from non-gazetted staff for posting to the
new zone.
Contd...2/--2-
Further, to improve railway infrastructure in Andhra Pradesh state,
following steps have been taken:
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Andhra Pradesh is as under:
Period Outlay
2009-2014 ₹886 Cr./year (including Telangana)
2025-2026 ₹9,417 Cr. (more than 10 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Andhra Pradesh during 2009-14 and 2014-25 is as under:
New Track
Period Average Commissioning of new tracks
Commissioned
2009-14 363 Km 72.6 Km per year
2014-25 1,582 Km 143.82 Km per year (Nearly 2 times)
Projects sanctioned:
As on 01.04.2025, 39 projects (12 New Line and 27 Doubling), covering a
total length of 4,499 Km length, costing ₹70,232 Cr., falling fully/partly in
Andhra Pradesh, have been sanctioned, out of which 1,178 Km length has
been commissioned and an expenditure of ₹28,039 Cr. has been incurred
upto March 2025. The status of the work is summarized as:
Contd...3/--3-
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2025
(Km) till March, 2025 (₹ in Cr.)
(in Km)
New Line 12 1595 199 6,413
Multi- 27 2904 979 21,626
tracking/Doubling
Total 39 4,499 1,178 28,039
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Recently completed Projects:
Details of some of the recently completed projects falling fully/partly in the
State of Andhra Pradesh are as under:
SN Name of Project Cost
(₹ in Cr.)
1 Vijaywada – Gudivada – Bhimavaram - Narsapur, 4,688
Gudivada-Machlipatnam & Bhimavaram-Nidadavolu
doubling (221 Km)
2 Guntur-Tenali doubling (24 Km) 205
3 Nandyal-Yerraguntla new line (126 Km) 1,050
4 Jaggayyapeta-Mellacheruvu-Janpahad new line (48 Km) 737
5 Obulavaripalle-Krishnapattnam new line (113 Km) 2,300
6 Vizianagaram-Kottavalsa 3rd Line (35 Km) 285
7 Raichur-Guntakal doubling (81 Km) 388
Contd...4/--4-
8 Guntakal-Kalluru doubling (41 Km) 410
9 Yelahanka-Penukonda doubling (123 Km) 1,104
10 Gooty-Dharmavaram doubling (90 Km) 1,800
Ongoing Projects:
Some of the projects falling fully/partly in the State of Andhra Pradesh
which have been taken up are as under:
S.N Name of Project Cost
(₹ in Cr.)
1 Kotipalli-Narsapur new line (57 Km) 2,120
2 Nadikude-Srikalahasti new line (309 Km) 3,122
3 Rayadurg-Kalyandurg-Tumkur new line (207 Km) 2,496
4 Marikuppam-Kuppam new line (24 Km) 297
5 Malugur – Palasamudram new line (18 Km) 342
6 Malkangiri- Bhadrachalam - Pandurangapuram new 3,592
line (174 Km)
7 Kottavalasa-Koraput Doubling (189 Km) 2,500
8 Vijaywada- Gudur 3rd line (287 Km) 6,509
9 Guntakal- Guntur Doubling (401 Km) 4,306
10 Pennukonda-Dharmavarm Doubling (42 Km) 308
11 Gooty-Pendekallu Doubling(29 Km) 352
12 Duvvada - Simhachalam North 3rd & 4th line (21 Km) 356
13 Kottavalasa - Vizianagram 4th line (35 Km) 493
14 Gudur-Renigunta 3rd Line (83 Km) 877
15 Nergundi - Palasa- Vizianagaram 3rd line (385 Km) 4,963
Contd...5/--5-
In addition to these, to improve connectivity of Amravati, following projects
have been taken up:
Errupalem-Amravati- Namburu new line (57 Km)
Errupalem-Namburu (57 km) new line project has been sanctioned at a cost
of ₹2047 Cr. An outlay of ₹171 Cr. has been provided for this project for the
year 2025-26. Project is declared as “Special Railway Project” and
Competent Authority for Land Acquisition(CALA) is nominated for land
acquisition. Land acquisition has been taken up.
Guntakal- Guntur doubling (401 Km)
Guntakal- Guntur (401 Km) doubling project has been sanctioned at a cost
of ₹4306 Cr. An expenditure of ₹3974 Cr. has been incurred upto March
2025 and an outlay of ₹149 Cr. has been provided for this project for the
Financial Year 2025-26.
Sections Commissioned: 344 Km
Status of the project is as under:
Guntakal-Panyam (129 Km): Commissioned.
Guntur-Diguvametta (215 Km): Commissioned.
Panyam-Diguvametta (57 Km), status is as under:
SN Activities Scope Status
1 Major 14 9 Completed and work has been taken up in
Bridge balance 5 bridges.
2 Station 5 3 Completed and work has been taken up in
balance 2 stations.
Contd...6/--6-
Guntur- Bibinagar doubling (239 Km)
Guntur-Bibinagar (239 Km) doubling project has been sanctioned at a cost
of ₹2853 Cr. An expenditure of ₹103 Cr. has been incurred upto March 2025
and an outlay of ₹452 Cr. has been provided for this project for the
Financial Year 2025-26. Project is declared as “Special Railway Project”
and CALA is nominated for land acquisition.
In last three Years i.e. 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 65 surveys (15 New Line, 50 Doubling) covering a total length of
6,985 Km has been taken up falling fully/partly in the State of Andhra
Pradesh.
Sanction of any railway project depends upon many parameters/factors
which include the following:
• Anticipated traffic projections and remunerativeness of the
proposed route
• First and last mile connectivity provided by the project
• Connection of missing links and providing additional route
• Augmentation of congested/saturated lines
• Demands raised by State Governments/Central Ministries/Public
representatives,
• Railway’s operational requirements
• Socio-economic considerations
• Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Contd...7/--7-
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the projects.
*****