GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2988
TO BE ANSWERED ON 17.12.2025
STATION REDEVELOPMENT PROJECT FOR BULANDSHAHR DISTRICT
2988. DR. BHOLA SINGH:
Will the Minister of RAILWAYS be pleased to state:
(a) the status of station redevelopment works under the Amrit Bharat
Station Scheme across the country, zone wise;
(b) the criteria used for prioritising stations for redevelopment and
multimodal connectivity;
(c) whether safety infrastructure such as automated signalling, CCTV
based surveillance and crowd management systems is being upgraded
in high footfall stations;
(d) if so, the details of sanctioned works, sanctioned budget,
utilisation so far and the proposed timelines for stations falling in
Bulandshahr district of Uttar Pradesh; and
(e) the steps taken/being taken by the Government to ensure faster
tendering, improved contractor performance and timely execution of
redevelopment projects?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) Ministry of Railways has launched Amrit Bharat Station
Scheme for redevelopment of stations with a long-term approach.The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master
planning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement,
water booths
Provision of wider foot over bridge/air concourse
commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like
‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for
business meetings, landscaping, etc. keeping in view the
necessity at each station
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity,
phasing and feasibility and creation of city centre at the station in
the long term.So far, 1337 stations have been identified for development under
this scheme, out of which 157 stations including Bulandsahar and
Khurja Jn. stations of Bulandsahar district, are located in Uttar
Pradesh. The names of stations identified for development under Amrit
Bharat Station Scheme in Uttar Pradesh are as following:
State No. of Name of Stations
Stations
Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh Jn,
Pradesh Akbarpur Jn, Aligarh, Amethi, Amroha, Anand
Nagar Jn., Aonla, Ayodhya Dham Junction,
Azamgarh, Babatpur, Bachhrawan, Badaun,
Badshahnagar, Badshahpur, Baheri,
Bahraich, Balamau Jn., Ballia, Balrampur,
Banaras, Banda, Barabanki Jn, Bareilly,
Bareilly City, Barhni, Basti, Belthara Road,
Bhadohi, Bharatkund, Bhatni, Bhuteshwar,
Bijnor, Bulandsahar, Chandauli Majhwar,
Chandausi, Chilbila, Chitrakutdhamkarwi,
Chopan, Chunar Jn., Daliganj, Darshannagar,
Deoria Sadar, Dhampur, Dildarnagar, Etawah
Jn., Farrukhabad, Fatehabad, Fatehpur,
Fatehpur Sikri, Firozabad, Gajraula,
Garhmuktesar, Gauriganj, Ghatampur,
Ghaziabad, Ghazipur City, Gola Gokarnath,
Gomtinagar, Gonda, Gorakhpur, Govardhan,
Govindpuri, Gursahaiganj, Haidergarh, Hapur,
Hardoi, Hathras City, Idgah Agra Jn,State No. of Name of Stations
Stations
Izzatnagar, Janghai Jn, Jaunpur City,
Jaunpur Jn, Kannauj, Kanpur Anwarganj,
Kanpur Bridge Left Bank, Kanpur Central,
Kaptanganj Jn, Kasganj Jn, Kashi,
Khalilabad, Khorason road, Khurja Jn., Kosi
Kalan, Kunda Harnamganj, Lakhimpur,
Lalganj, Lalitpur Jn, Lambhua, Lohta,
Lucknow (Charbagh) NR, Lucknow city,
Lucknow Jn. (NER), Maa Belha Devi
Pratapgarh Junction, Maghar, Maharaja Bijli
Pasi, Mahoba Jn, Mailani Jn, Mainpuri Jn,
Malhaur, Manak Nagar, Manikpur Jn,
Mariahu, Mathura Jn, Mau Jn, Meerut City Jn,
Mirzapur, Modinagar, Mohanlalganj,
Moradabad Jn, Muzaffarnagar, Nagina,
Najibabad Jn, Orai, Panki Dham, Phaphamau
Jn, Phulpur, Pilibhit Jn, Pokhrayan, Prayag
Jn, Prayagraj Jn, Pt. Deen Dayal Upadhyay
Jn, Rae Bareli Jn, Raja Ki Mandi, Ramghat
Halt, Rampur Jn, Renukoot, Saharanpur Jn.,
Salempur, Seohara, Shahganj Jn,
Shahjahanpur, Shamli, Shikohabad Jn.,
Shivpur, Siddharth nagar, Sitapur Jn.,
Sonbhadra, Sri Krishna Nagar, Sultanpur Jn,
Suraimanpur, Swaminarayan Chappia, Takia,
Tulsipur, Tundla Jn., Ujhani, Unchahar,State No. of Name of Stations
Stations
Unnao Jn, Utraitia Jn, Varanasi Cantt.,
Varanasi City, Vindhyachal, Virangana
Lakshmibai Jhansi, Vyasnagar, Zafarabad
Development works at railway stations under Amrit Bharat Station
Scheme in Uttar Pradesh have been taken up at a good pace. Till now,
works of 22 stations (Ayodhya Dham, Balrampur, Bareilly City, Bijnor,
Fatehabad, Fatehpur, Gola Gokarnath, Gomtinagar, Govardhan,
Govindpuri, Hathras City, Idgah Agra Jn, Izzatnagar, Mailani, Panki
Dham, Pokhrayan, Ramghat Halt, Saharanpur Jn., Siddharth Nagar,
Suraimanpur, Swaminarayan Chappia, Ujhani) in Uttar Pradesh have
been completed under this scheme. The works at other stations have
also been taken up at good pace and progress of some of above
stations is as given below:
Bulandsahar station: The works of extension, raising and platform
surfacing of platform no. 1 have been completed. The works of
station building, entrance porch, improvement of existing station
building, platform shelters, circulating area, parking and
Divyangjan toilets have been taken up.
Khurja Jn. station: The structural work of station building, porch
and improvement of existing station building have been completed.
The finishing works of station building, porch, waiting hall,
executive lounge, Passenger Reservation System counter and
parking have taken up. Tulsipur station: The works of improvement of station building,
entrance porch, circulating area, parking area, improvement to
waiting room, toilet, platform shelter and signages have been
completed. The finishing works have been taken up.
Modinagar station: The work of improvement to station building
elevation, improvement to waiting area and toilets, 12 m wide Foot
Over Bridge, new platform shelters, have been completed and work
of minor finishing items of building, platform surfacing, signage,
improvement to circulating area and parking have been taken up.
Lucknow (Charbagh) station: The structural works of the second
entry station building, TTE Running Hostel, Store Depot have been
completed and masonry work including other finishing works,
concourse, Foot Over Bridge, second entry circulating area, main
entry external development and platform no. 10/11 works have
been taken up.
Prayagraj Junction station: Structural work of second entry side,
Rail Mail Service & arrival, parcel & arrival buildings and basement
plaza at second entry, Electrical substation have been completed
and finishing work of these structures have been taken up.
Extension work of Foot Over Bridge no. 2 has been completed.
Work of roof plaza and relocated structures have been taken up.
Ghaziabad station: Structural work of station building at main entry
side and second entry side, foundation work of Foot Over Bridge,
roof plaza, electrical substation at main entry side and second
entry side, Magistrate building, Government Railway Police and
Railway Protection Force buildings have been taken up.Stations are selected for development under Amrit Bharat Station
Scheme based on the proposals received from Zonal Railways,
stations located in major cities and places of tourist and pilgrimage
importance.
Further development / redevelopment / upgradation / modernisation of
stations including provision of passenger amenities at stations on
Indian Railways is a continuous and ongoing process and works in this
regard are undertaken as per requirement, subject to inter-se priority
and availability of funds. The priority for development / redevelopment
/ upgradation / modernisation of stations is accorded to higher
category of station over lower category of station while sanctioning
and executing the works.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check
for quality of works and audits.
Indian Railways digital initiatives like Indian Railways Projects
Sanctions and Management (IRPSM), Indian Railways E-Procurement
System (IREPS) and Indian Railways Works Contract Management
System (IRWCMS) have enhanced sanctioning, tendering and
monitoring capabilities.
Works are carried out adhering to the standards and specifications
laid down in various codes and manuals. Inspections/audits/checks are
carried out from time to time by various agencies/officials/multi-
disciplinary teams as per laid down instructions and actions for
correction including damages are taken immediately. This is a
continuous and ongoing process.Development / Upgradation / Modernisation of stations including
under Amrit Bharat Station Scheme is generally funded under Plan
Head-53 ‘Customer Amenities’. The details of allocation and
expenditure under Plan Head-53 are maintained Zonal Railway-wise
and not work-wise or station wise or state-wise. The fund
allocation of ₹ 12,118 crore has been made for the financial year
2025-26 under Plan Head–53 and expenditure (up to October, 2025)
of ₹ 7,253 crore has been incurred so far. Uttar Pradesh is covered
under the jurisdiction of five railway zones, namely East Central
Railway, North Central Railway, Northern Railway, North Eastern
Railway and West Central Railway. For these zones, an allocation of ₹
4,358 crore has been made for the financial year 2025-26, out of which
an expenditure (up to October, 2025) of ₹ 2,288 crore has been
incurred so far.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield
related challenges such as shifting of utilities (involving water/sewage
lines, optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close
proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time. Therefore, no time frame can be
indicated at this stage.
The installation of CCTV works are planned at all railway stations
except halt station.Ministry of Railways has planned to provide holding areas for crowd
management at 76 stations. The passenger holding area for crowd
management planning envisages a comfortable, well-organized space
with basic amenities like seating, drinking water, toilets, ticketing
facilities, information displays, security checks, etc. These amenities
are planned to be organised to manage large passenger footfall
efficiently during peak hours.
The passenger holding area established at New Delhi Railway Station
has significantly helped to ease congestion and enhance passenger
convenience, particularly during peak travel periods. The holding area
is equipped with a wide range of commuter-friendly facilities,
including an increased number of ticket counters, Automatic Ticket
Vending Machine(ATVMs), public announcement system, electronic
train information display boards, CCTV surveillance, luggage
scanners, Door Frame Metal Detector (DFMDs), uninterrupted power
supply, improved night-time lighting, High Volume Low Speed (HVLS)
fans, fire-fighting system, lightning protection system, RO drinking
water, and separate toilets for men, women and Divyangjans, along
with seating arrangements.
The provision of holding areas at other stations is at various stages of
planning/execution. Planning is an iterative process requiring
optimization and the time frame and other details for such
optimization cannot be indicated at this stage.
Safety:
Safety is accorded the highest priority on Indian Railways. As a
consequence of various safety measures taken over the years, there
has been a steep decline in the number of accidents. ConsequentialTrain Accidents have reduced from 135 in 2014-15 to 31 in 2024-25 as
shown in the graph below:
234
165
135
55 48
40
31
35
22
11
It may be noted that the Consequential Train Accidents during the
period 2004-14 was 1711 (average 171 per annum), which has declined
to 31 in 2024-25 and further to 11 in 2025-26 (upto November, 2025).
Another important index showing improved safety in train operations
is Accidents Per Million Train Kilometer (APMTKM) which has reduced
from 0.11 in 2014-15 to 0.03 in 2024-25, indicating an improvement of
approx. 73% during the said period.
The various safety measures taken to enhance safety in train
operations are as under:
stnediccA
niarT
laitneuqesnoC
fo
.oN1. On Indian Railways, the expenditure on Safety related activities
has increased over the years as under:
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26
(Act.) (Act.) (Act.)
39,463 87,327 1,01,651 1,14,022 1,16,470
2. Electrical/Electronic Interlocking Systems with centralized
operation of points and signals in place of old mechanical
signalling have been provided at 6,657 stations up to 30.11.2025 to
reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at
10,100 Level Crossing Gates up to 30.11.2025 for enhancing safety
at LC Gates.
4. Complete Track Circuiting of stations to enhance safety for
verification of track occupancy by electrical means has been
provided at 6,663 stations up to 30.11.2025.
5. Kavach is a highly technology intensive system, which requires
safety certification of highest order. Kavach was adopted as a
National ATP system in July 2020. Kavach is provided progressively
in phased manner. Initially, Kavach Version 3.2 was deployed on
1465 RKm of South Central Railway and 80 RKm of North Central
Railway. Kavach specification Version 4.0 was approved by RDSO
on 16.07.2024.
After extensive and elaborate trials, Kavach Version 4.0has been
successfully commissioned onPalwal–Mathura–Kota–Nagda section
(633Rkm) on Delhi–Mumbai route and on Howrah–Bardhaman
section (105RKm)on Delhi–Howrah route. Kavach implementationhas been taken up in balance sections of Delhi–Mumbai and Delhi–
Howrah route.
Further, Kavach implementation has been taken up on 15,512
RKm covering all GQ, GD, HDN and identified sections of Indian
Railways.
6. Detailed instructions on issues related with safety of Signalling, e.g.
mandatory correspondence check, alteration work protocol,
preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as
per protocol has been re-emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD)
to improve alertness of Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is
located two OHE masts prior to the signals in electrified territories
to alert the crew about the signal ahead when visibility is low due
to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in
fog affected areas which enables loco pilots to know the distance
of the approaching landmarks like signals, level crossing gates,
etc.
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Prestressed Concrete Sleeper (PSC)
Normal/Wide base sleepers with elastic fastening, fan shaped
layout turnout on PSC sleepers, Steel Channel/H-beam Sleepers on
girder bridges is used while carrying out primary track renewals.
12. Mechanisation of track laying activity through use of track
machines like PQRS, TRT, T-28 etc. to reduce human errors.13. Maximizing supply of 130m/260m long rail panels for increasing
progress of rail renewal and avoiding welding of joints, thereby
improving safety.
14. Ultrasonic Flaw Detection (USFD) testingof rails to detect flaws
and timely removal of defective rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic
Welding and adoption of better welding technology for rails i.e.,
Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring
System) and TRC (Track Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in
turnout renewal works.
19. Inspections at regular intervals are carried out to monitor and
educate staff for observance of safe practices.
20. Web based online monitoring system of track assets viz. Track
database and decision support system has been adopted to decide
rationalized maintenance requirement and optimize inputs.
21. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon
precautions, etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is
undertaken to ensure safe train operations.
23. Replacement of conventional ICF design coaches with LHB design
coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route
have been eliminated by January 2019.25. Safety of Railway Bridges is ensured through regular inspection of
Bridges. The requirement of repair/rehabilitation of Bridges is taken
up based upon the conditions assessed during these inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for
widespread passenger information in all coaches. Fire posters are
provided in every coach so as to educate and alert passengers
regarding various Do’s and Don’ts to prevent fire. These include
messages regarding not carrying any inflammable material,
explosives, prohibition of smoking inside the coaches, penalties
etc.
27. Production Units are providing Fire detection and suppression
system in newly manufactured Power Cars and Pantry Cars, Fire
and Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also
underway by Zonal Railways in a phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open
Lines) General Rules vide Gazette notification dated 30.11.2023,
wherein work of integrated maintenance/ repair/replacement of
assets is planned up to 52 weeks in advance on rolling basis and
executed as per plan.
The details of the Safety related works related to better
maintenance practices, Technological improvements, better
infrastructure and rolling stock etc. undertaken by Railways are
tabulated below:2014-15 to
2004-05 to 2014-25 Vs.
S.N. Item 2024-25
2013-14 2004-14
Technological Improvements
1. Use of high-quality 57,450 Km 1.43 Lakh Km More than 2
rails times
(60 Kg) (Km)
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8
(260m) (Km) times
3. Electronic 837 3,691 Stations More than 4
Interlocking Stations times
(Stations)
4. Fog Pass Safety As on As on 288 times
Devices (Nos.) 31.03.14: 31.03.25:
90 Nos. 25,939 Nos.
5. Thick Web Switches Nil 28,301 Nos.
(Nos.)
Better Maintenance Practices
1. Primary Rail 32,260 Km 49,941 Km 1.5 times
Renewal (Track Km)
2. USFD (Ultra Sonic 79.43 Lakh 2 Crore More than 2
Flaw detection) times
Testing of Welds
(Nos.)
3. Weld failures (Nos.) In 2013- In 2024-25: 90 %
14: 3699 370 Nos. reduction
Nos.4. Rail fractures (Nos.) In 2013- In 2024-25: More than
14: 2548 289 Nos. 88%
Nos. reduction
Better Infrastructure and Rolling Stock
1. New Track KM 14,985 Km 34,428 Km More than 2
added (Track Km) times
2. Flyovers 4,148 Nos. 13,808 Nos. More than 3
(RoBs)/Underpasses times
(RUBs) (Nos.)
3. Unmanned Level As on As on Removed
crossings 31.03.14: 31.03.24:Nil
(Nos.) on BG 8,948 (All eliminated
by 31.01.19)
4. Manufacture of LHB 2,337 Nos. 42,677 More than
Coaches (Nos.) 18 times
Implementation of Kavach:
Kavach is an indigenously developed Automatic Train Protection
(ATP) system. Kavach is a highly technology intensive system,
which requires safety certification of highest order (SIL-4).
Kavach aids the Loco Pilot in running of trains within specified
speed limits by automatic application of brakes in case Loco Pilot
fails to do so and also helps the trains to run safely during
inclement weather.
The first field trials on the passenger trains were started in
February, 2016. Based on the experience gained and IndependentSafety Assessment of the system by Independent Safety Assessor
(ISA), three firms were approved in 2018-19, for supply of Kavach
Version 3.2.
Kavach was adopted as National ATP system in July, 2020.
Implementation of Kavach System involves following Key
Activities:
(i) Installation of Station Kavach at each and every station,
block section.
(ii) Installation of RFID Tags throughout the track length.
(iii) Installation of telecom Towers throughout the section.
(iv) Laying of Optical Fibre Cable along the track.
(v) Provision of Loco Kavach on each and every Locomotive
running on Indian Railways.
Based on deployment of Kavach Version 3.2 on 1465 RKm on South
Central Railway and experience gained, further improvements were
made. Finally, Kavach specification Version 4.0 was approved by
RDSO on 16.07.2024.
Kavach version 4.0 covers all the major features required for the
diverse railway network. This is a significant milestone in safety for
Indian Railways. Within a short period, IR has developed, tested
and started deploying Automatic Train Protection System.
Major improvement in Version 4.0 includes increased Location
Accuracy, Improved Information of Signal Aspects in bigger yards,
Station to Station Kavach interface on OFC and Direct Interface to
existing Electronic Interlocking System. With these improvements,Kavach Version 4.0 is planned for large scale deployment over
Indian Railways.
After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 738 Route km on Palwal–Mathura–
Nagda section (633 Rkm) on Delhi–Mumbai route and Howrah–
Bardhaman section (105 Rkm) Delhi–Howrah route. Kavach
implementation has been taken up in balance sections of Delhi–
Mumbai and Delhi–Howrah corridors.
Progress of key items of Kavach on High density routes including
Delhi–Mumbai & Delhi–Howrah corridors are as under:
SN Item Progress
i Laying of Optical Fibre Cable 7129 Km
ii Installation of Telecom Towers 860 nos
iii Station Data Centre 767 stations
iv Installation of Track side 5672 RKm
equipment
v Provision of Kavach on Locos 4,154
Further, track side Kavach implementation work has been taken up
on 15,512 RKm covering all GQ, GD, HDN and identified sections of
Indian Railways.
Bids have been invited for equipping another 9,069 locomotives
with Kavach version 4.0. Kavach is being provided progressively in
a phased manner in locomotives. Specialized training programmes on Kavach are being conducted at
centralized training institutes of Indian Railways to impart training
to all concerned officials. By now more than 40,000 technicians,
operators and engineers have been trained on Kavach technology.
This includes 33,000 Loco Pilots and Assistant Loco Pilots. Courses
have been designed in collaboration with IRISET.
The fund utilized on Kavach works so far up to October, 2025 is Rs.
2,354.36 crores. The allocation of funds during the year 2025-26 is
Rs. 1,673.19 crores. Requisite funds are made available as per the
progress of works.
*****