Executive Summary & Key Takeaways
**Executive Summary**
The document details the status of Phase-IV of the Pradhan Mantri Gram Sadak Yojana (PMGSY), answering questions raised in Lok Sabha Starred Question No. 145 on February 10, 2026. It provides updates on road sanctions, construction progress, and the utilization of the e-MARG platform for monitoring purposes. Action items include the submission of proposals by states and monitoring progress by various stakeholders.
**Key Points / Main Content**
* **PMGSY-IV Overview:**
* Launched for constructing 62,500 km of all-weather roads to connect 25,000 unconnected habitations.
* Implementation period: Financial Years 2024-2025 to 2028-2029.
* **Road Sanctions and Progress (as of February 10, 2026):**
* 2,882 road works sanctioned, covering 10,577.70 km.
* Rajasthan: 1,216 road works sanctioned, covering 3,218.97 km, plus one bridge.
* Tendering is underway in various states/UTs.
* **Evaluation and Impact Assessment:**
* Independent studies conclude that PMGSY has improved access to education, healthcare, and employment.
* Road access has been provided to around 6,96,620 facilities.
* **Prioritization Criteria:**
* Prioritizes unconnected habitations with population sizes based on specific criteria, including tribal and economically disadvantaged areas.
* **e-MARG Platform:**
* Used for monitoring, quality control, and maintenance of rural roads.
* Digitally manages road inspections with real-time updates and geo-tagged photos.
* Integrates citizen feedback and grievance redressal.
* **Annexures:**
* Contain district-wise details of road length sanctioned under PMGSY-IV for Uttarakhand, Chhattisgarh, Himachal Pradesh, Jammu & Kashmir, Rajasthan, and Sikkim.
* Provide details of habitations surveyed by Andhra Pradesh under PMGSY-IV.
* Detail road works sanctioned in Udaipur and Salumbar districts of Rajasthan.
* Provide habitations survey status details for Bapatla, Shahdol and Nawarangpur and Hazaribagh, Ramgarh.
**Impact Analysis**
* **Central Government:**
* **Impact:** Responsible for overall coordination and funding of PMGSY-IV.
* **Action Required:** Continue close coordination with state governments and monitor the progress of road construction.
* **State Governments:**
* **Impact:** Implementing agencies responsible for submitting proposals, tendering, and executing road construction.
* **Action Required:** Expedite the submission of proposals, finalize tendering processes, and ensure timely completion of road works.
* **Local Communities:**
* **Impact:** Beneficiaries of improved road connectivity, with better access to essential services and economic opportunities.
* **Action Required:** Provide feedback through available grievance redressal mechanisms.
* **Project Implementation Units and State Authorities:**
* **Impact:** Oversee construction quality, maintenance, and monitoring.
* **Action Required:** Utilize e-MARG platform for continuous monitoring and quality control, address citizen grievances promptly.
Key Entities Referenced
Pradhan Mantri Gram Sadak Yojana (PMGSY) : A rural road connectivity scheme launched in 2000 and expanded through several phases.
PMGSY-IV : Phase IV of the Pradhan Mantri Gram Sadak Yojana, aiming to provide all-weather road connectivity to unconnected habitations.
Ministry of Rural Development : The central ministry responsible for the Pradhan Mantri Gram Sadak Yojana.
e-MARG : An electronic governance platform used for monitoring, quality control and maintenance of rural roads constructed under PMGSY.
Rajasthan : One of the states to where a lot of detail is dedicated in this document.
See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
STARRED QUESTION NO. 145
ANSWERED ON 10/02/2026
STATUS OF PHASE-IV OF PMGSY
*145. Shri Balabhadra Majhi:
Shri Dineshbhai Makwana:
Will the Minister of RURAL DEVELOPMENTbe pleased to state:
(a) the status of roads sanctioned for the targeted 25,000
unconnected habitations underPhase-IV of the Pradhan Mantri
Gram Sadak Yojana (PMGSY), State and district-wise
includingNabarangpur, Baptala and Shahdol Parliamentary
Constituencies;
(b) the total number of roads sanctioned, length of roads
completed and works executed alongwith the cost thereof
under the scheme, State and district-wise including Udaipur,
Salumber,Dungarpur and Pratapgarh districts of Rajasthan;
(c) the physical and financial progress achieved so far in the
construction of all-weather ruralroads under PMGSY-IV since
its approval in September 2024 in the country, State and
district-wise, in Himachal Pradesh and in Nabarangpur,
Baptala, Hazaribagh, Ramgarh, ShahdolParliamentary
Constituencies;
(d) the manner in which the impact of road upgradation
undertaken under PMGSY-II andPMGSY-III on access to
schools, health centres and transport facilities has been
assessed in thecountry, State and district-wise including
Baptala Lok Sabha Constituency of Andhra Pradesh;
(e) the criteria adopted for identification of „Growth Centres‟ under
PMGSY-IV, State anddistrict-wise including the said Lok Sabha
Constituencies and whether any priority has beenaccorded to
the tribal areas of Shahdol therein, if so, the details thereof;
and
(f) the manner in which the e-MARG platform is being utilized for
monitoring, quality controland maintenance of rural roads
constructed under PMGSY particularly in Nabarangpur,
Dumka,Hazaribagh and Ramgarh Lok Sabha Constituencies?
ANSWER
MINISTER OF RURAL DEVELOPMENT
(SHRI SHIVRAJ SINGH CHOUHAN)
Page 1 of 28(a) to (f): A statement is laid on the Table of the House.
Page 2 of 28STATEMENT REFERRED TO IN REPLY TO PARTS (a) to (f) OF LOK
SABHA STARRED QUESTION NO. *145 TO BE ANSWERED ON
10.02.2026REGARDING “STATUS OF PHASE-IV OF PMGSY”
(a): The Pradhan Mantri Gram Sadak Yojana (PMGSY) was
launched in 2000, as a one time special dispensation, for providing
connectivity to eligible unconnected habitations in the country. The
new phase, PMGSY-IV has been launched for construction of 62,500
km of all-weather roads (single lane) to provide connectivity to
about 25,000 unconnected habitations of population size 500+ in
plains, 250+ in NE & Hill states/UTs, special category areas (Tribal
Schedule V, Aspirational Districts/ Blocks, Desert areas) and 100+
in Left Wing Extremism (LWE) affected districts (areas notified by
MHA) in 9 States, as per Census 2011. PMGSY Phase-IV is being
implemented from Financial Years 2024–2025 to 2028–2029. The
Central Government is working in close coordination with the States
to facilitate submission of proposals under PMGSY IV.
So far under PMGSY-IV, 2882 road works covering a length of
10,577.70 km have been sanctioned. The district wise details of
road length sanctioned under PMGSY -IV is given in Annexure –I.
For the State of Odisha under PMGSY-IV, an Empowered
Committee meeting was held on 24.12.2025 to consider 827 roads
covering a total length of 1701.84 km. The proposal is presently
under consideration in the Ministry of Rural Development. This
includes proposals from Nabarangpur district comprising 138 road
works covering a length of approximately 324 km, which were
placed before the Empowered Committee.
For the state of Andhra Pradesh, Pre-Empowered Committee
meeting to examine the proposals will be scheduled soon. So far
the state has uploaded Detailed Project Reports for road works
totalling around 477 km on OMMAS. The details of habitations
surveyed by the state under PMGSY-IV are given in Annexure II.
For the state of Madhya Pradesh, Pre-Empowered Committee
meeting was held on 28.10.25 for 868 road works covering a length
of 1849 km. The compliance report from the state is awaited.
Under PMGSY-IV, the Detailed Project Report proposals from
the State of Jharkhand are still awaited. The Ministry has been
coordinating with the state to facilitate the submission of eligible
proposals under this Phase at the earliest.
Page 3 of 28(b): Under PMGSY-IV for the state of Rajasthan, 1216 road works
covering a length of 3218.97 km and one bridge have been
sanctioned. The details of roads sanctioned in Udaipur, Salumber,
Dungapur and Pratapgarh districts of Rajasthan are given in
Annexure III.
(c): Under PMGSY-IV, works covering a total road length of
10,577.70 km, comprising 2,880 roads and one bridge, have been
sanctioned so far. Tendering of the sanctioned works is presently at
various stages across the states/UTs. So far, the UT of Jammu &
Kashmir has begun awarding the works and in remaining
states/UTs it is under process. Hence, the physical and financial
progress will start getting reported after finalisation of tendering
process by the states/UTs. The current status of PMGSY-IV is given
below:-
Sr.No. Name of No. of Road Road Length No. of Bridge
State/UT works Sanctioned Works
Sanctioned (km) Sanctioned
1 Chhattisgarh 774 2,426.875 0
2 Himachal 294 1,538.058 0
Pradesh
3 Jammu And 316 1,781.334 0
Kashmir
4 Rajasthan 1,216 3,218.971 1
5 Sikkim 96 384.267 0
6 Uttarakhand 184 1,228.198 0
Total 2,880 10,577.703 1
District-wise details may be accessed at programme website
https://pmgsy.dord.gov.in ->Progress Monitoring->State MPR
Abstract Report.
(d): Various independent evaluation studies on PMGSY
conducted by NITI Aayog, Indian Institute of Management,
Ahmedabad (IIM-A), World Bank, International Labour Organization
(ILO), and Birla Institute of Technology & Science (BITS), Pilani
Page 4 of 28have concluded that PMGSY has improved access to education and
health care facilities, facilitated employment generation in both
farm and non-farm sectors, helped farmers in getting better farm
prices and so on. PMGSY roads have provided better education
opportunities to children, particularly the girl child to continue their
education beyond the elementary school level. Health facilities are
being made accessible to people. Women have been the major
beneficiaries, with higher numbers of childbirth taking place in
government hospitals and also their participation in financial
decision-making has increased which is reflected in their
enhancedmarket accessibility.
Under PMGSY, road access has been provided to about
6,96,620 facilities of which 1,38,637 are agricultural markets,
1,46,784 are educational centres, 82,806 are medical centres and
3,28,393 are connected to transportation hubs (including Bapatla
Lok Sabha Constituency of Andhra Pradesh), and so on.
Under PMGSY-II, as against the target of 50,000 km, 49,777.70
km and 759 bridges have been sanctioned out of which 49,093.10
km and 750 bridges have been completed. In Bapatla district, 6 road
works covering a length of 53 km have been sanctioned and all the
road works have been completed.
Under PMGSY-III, as against the target of 1,25,000 km,
1,22,322.5 km and 3211 bridges have been sanctioned out of which
1,03,554.80 km and 1776 bridges have been completed. In Bapatla
district, 12 road works covering a length of 82 km and 3 bridges
have been sanctioned out of which 8 road works covering a length
of 54.9 km have been completed.
(e): The primary objective of PMGSY-IV is to provide all-weather
road connectivity to about 25,000 unconnected habitations of
population size 500+ in plains, 250+ in Hill States/UTs and North-
Eastern Region (NER), Special Category Areas (Tribal Schedule-V
Areas, Desert Areas, Aspirational Blocks/ Districts) and 100+ in
LWE affected Districts (areas notified by MHA) in 9 States as per
Census 2011.
Under PMGSY-IV, a mobile application, named "PMGSY Gram
Sadak Survey App”, has been developed to identify possible
alignments of roads to unconnected eligible habitations. PM Gati
Shakti portal with a wider database is available for detailed analysis
of data received from the transect walk and facilitates developing
Page 5 of 28the preliminary Detailed Project Reports. The data captured is then
verified at the State level before uploading on Geo Sadak. The State
Rural Roads Development Agencies are to ensure that the vetted
proposals meet the objectives of PMGSY-IV.
The unconnected habitations to be covered under PMGSY-IV
are to be prioritized as per details given below:
Priority Population Size
No.
I (a) Under Dharti Aaba Janjatiya Gram Utkarsh Abhiyan
-500 or more population and 50% or more ST population as
per census 2011
- 50 or more ST population in 250 + population category in
Aspirational Districts as per census 2011
I (b) Under Pradhan Mantri Anusuchit Jaati Abhyuday Yojna
(PM-AJAY)
-500 or more population and 40% or more SC population as
per census 2011
II Eligible population size as per PMGSY-IV and under
convergence schemes of Central Government with rural
road component (as specified by DoRD from time-to-time)
III 1000+
IV 500-999
V 250-499
VI 100-249
The details of survey of habitations conducted for
Nabarangpur, Baptala, Hazaribag, Ramgarh and Shahdol districts
under PMGSY-IV are given in Annexure IV.
(f): The Electronic Maintenance of Rural Roads (e-MARG) platform
is an end-to-end e-governance system used for monitoring, quality
control and maintenance of rural roads constructed under the
Pradhan Mantri Gram Sadak Yojana (PMGSY) across the country,
including in Nabarangpur Lok Sabha Constituency of Odisha and
Dumka, Hazaribagh and Ramgarh Lok Sabha Constituencies of
Jharkhand. The platform primarily covers the five-year Defect
Liability Period (DLP) and subsequent maintenance through
Performance-Based Maintenance Contracts.
Page 6 of 28Under e-MARG, road inspections are carried out digitally using
mobile applications by field engineers and quality monitors, with
geo-tagged and time-stamped photographs uploaded to the system.
Inspection findings are updated in real time, enabling Project
Implementation Units and state authorities to continuously monitor
road condition and maintenance quality. The platform uses
automated performance evaluation based on inspection data to
assess compliance with prescribed maintenance standards,
thereby, ensuring transparency and uniformity in quality control.
Further, the system links maintenance payments to verified
performance, with online processing of bills based on inspection
outcomes. e-MARG also provides centralized dashboards and geo-
referenced data for district, state and national-level monitoring and
integrates citizens’ feedback through QR codes and grievance
redressal mechanisms, thereby, enhancing transparency,
accountability and sustained upkeep of rural roads.
Under the Defect Liability Period (DLP), an expenditure of Rs.
7.07 crore covering 285 roads has been incurred through e-MARG in
Dumka district, Rs. 6.24 crore covering 315 roads in Hazaribagh
district, and Rs. 56 lakhs covering 51 roads in Ramgarh district of
Jharkhand. In Nabarangpur district of Odisha, an expenditure of Rs.
13.54 crore covering 329 roads has been incurred under DLP
through e-MARG.
*****
Page 7 of 28Annexure-I
Annexure referred to in reply to part (a) of Lok SabhaStarred Q.No.
145due for reply on 10.02.2026
Districtwise details of road length sanctioned in Uttarakhand under
PMGSY-IV
Sr.No. Name of No of Road Road Length No of Bridge
District works Sanctioned works
Sanctioned Sanctioned
1 Almora 29 203.535 0
2 Bageshwar 23 125.316 0
3 Chamoli 11 59.075 0
4 Dehradun 5 52.875 0
5 Haridwar 1 3.175 0
6 Nainital 17 94.085 0
7 Pauri 32 204.792 0
8 Pithoragarh 13 101.135 0
9 Rudraprayag 7 49.175 0
10 Tehri 31 215.510 0
11 Uttarkashi 15 119.525 0
TOTAL 184 1,228.198 0
District wise details of road length sanctioned in Chhattisgarh under
PMGSY-IV
Sr.No. Name of No of Road Road Length No of Bridge
District works Sanctioned works
Sanctioned Sanctioned
1 Bastar 87 236.950 0
2 Bijapur 44 158.740 0
3 Bilaspur 27 81.540 0
4 Dantewada 12 43.160 0
5 Dhamtari 2 11.450 0
6 Jashpur 77 197.260 0
7 Kanker 40 115.060 0
8 Kawardha 48 104.055 0
9 Korba 55 162.810 0
10 Koria 83 396.470 0
11 Mahasamund 44 96.495 0
12 Raigarh 14 42.850 0
Page 8 of 2813 Rajnandgaon 5 13.800 0
14 Surguja 26 65.560 0
15 Sukma 12 56.280 0
16 Bemetra 2 3.500 0
17 Balod 6 7.420 0
18 Balodabazar 1 3.360 0
19 Gariaband 7 18.080 0
20 Balrampur 58 142.545 0
21 Surajpur 76 314.640 0
22 Kondagaon 33 119.800 0
23 Mungeli 6 9.650 0
24 Gaurella 9 25.400 0
Pendra
Marwahi
TOTAL 774 2,426.875 0
District wise details of road length Sanctioned in Himachal Pradesh
under PMGSY-IV
Sr.No. Name of No of Road Road Length No of Bridge
District works Sanctioned works
Sanctioned Sanctioned
1 Bilaspur 4 18.210 0
2 Chamba 65 326.640 0
3 Hamirpur 2 7.143 0
4 Kangra 12 28.480 0
5 Kinnaur 8 63.970 0
6 Kullu 65 404.220 0
7 Lahul And 2 29.645 0
Spiti
8 Mandi 23 114.370 0
9 Shimla 97 473.515 0
10 Sirmaur 11 58.070 0
11 Solan 3 8.695 0
12 Una 2 5.100 0
TOTAL 294 1,538.058 0
District wise details of road length sanctioned in Jammu & Kashmir
Page 9 of 28under PMGSY-IV
Sr.No. Name of No of Road Road Length No of Bridge
District works Sanctioned works
Sanctioned Sanctioned
1 Anantnag 7 19.500 0
2 Baramula 13 41.940 0
3 Budgam 14 47.897 0
4 Doda 31 239.105 0
5 Jammu 6 36.300 0
6 Kathua 15 129.569 0
7 Kupwara 14 46.810 0
8 Poonch 40 204.403 0
9 Pulwama 14 54.220 0
10 Rajouri 41 256.963 0
11 Udhampur 20 133.931 0
12 Bandipora 9 47.935 0
13 Ganderbal 8 22.550 0
14 Kishtwar 20 93.210 0
15 Kulgam 13 30.900 0
16 Ramban 24 155.620 0
17 Reasi 21 181.881 0
18 Samba 3 29.500 0
19 Shopian 3 9.100 0
TOTAL 316 1,781.334 0
District wise details of road length sanctioned in Rajasthan under
PMGSY-IV
Sr.No. Name of No of Road Road Length No of Bridge
District works Sanctioned works
Sanctioned Sanctioned
1 Ajmer 5 7.060 0
2 Alwar 2 2.135 0
3 Banswara 50 90.100 0
4 Baran 12 35.970 0
5 Barmer 261 748.100 0
6 Bhilwara 4 5.600 0
7 Bikaner 57 213.240 0
8 Dungarpur 50 82.770 0
9 Hanumangarh 1 2.120 0
Page 10 of 2810 Jaipur 2 4.700 0
11 Jaisalmer 28 94.550 0
12 Jalor 117 284.930 0
13 Jhalawar 4 6.675 0
14 Jodhpur 113 276.270 0
15 Nagaur 4 8.550 0
16 Pali 15 31.665 0
17 Pratapgarh 11 17.420 1
18 Rajsamand 1 1.000 0
19 Sikar 8 15.750 0
20 Sirohi 60 146.600 0
21 Sri 1 3.000 0
Ganganagar
22 Udaipur 84 171.355 0
23 Balotra 161 487.410 0
24 Beawar 3 4.800 0
25 Didwana 9 15.850 0
Kuchaman
26 Kotputli Behror 1 1.200 0
27 Phalodi 113 383.870 0
28 Salumbar 39 76.281 0
TOTAL 1,216 3,218.971 1
District wise details of road length sanctioned in Sikkim under
PMGSY-IV
Sr.No. Name of No of Road Road Length No of Bridge
District works Sanctioned works
Sanctioned Sanctioned
1 East 20 63.070 0
2 North 8 57.483 0
3 South 25 88.209 0
4 West 13 66.010 0
Sikkim
5 Pakyong 15 58.296 0
6 Soreng 15 51.199 0
96 384.267 0
*****
Page 11 of 28Annexure-II
Annexure referred to in reply to part (a) of Lok SabhaStarred Q.No. 145due for reply on
10.02.2026
Details of habitations surveyed by the state of Andhra Pradesh under PMGSY-IV
Sr.No Name Name Of Approval Total Connected Un- Approved Pending Rejected Eligible
of State District (Status Survey Survey Connected Un- Un- Un- Total
By NRIDA) Survey Connected Connected C onnected
Survey By Survey Survey By
State By State State
Grand Total 4391 413 3978 475 24 3479 413
Approved 1826 0 1826 236 0 1590 201
Pending 1643 413 1230 22 24 1184 0
Verification 922 0 922 217 0 705 212
1 Andhra Anantapur Approved 31 0 31 17 0 14 17
Pradesh
2 Andhra Anantapur Pending 26 9 17 0 0 17 0
Pradesh
3 Andhra Anantapur Verification 33 0 33 22 0 11 22
Pradesh
4 Andhra Chittoor Approved 30 0 30 3 0 27 1
Pradesh
5 Andhra Chittoor Pending 328 37 291 2 0 289 0
Pradesh
6 Andhra Chittoor Verification 34 0 34 4 0 30 4
Pradesh
7 Andhra Y S R Kadapa Approved 37 0 37 10 0 27 8
Pradesh
8 Andhra Y S R Kadapa Pending 11 11 0 0 0 0 0
Pradesh
9 Andhra Y S R Kadapa Verification 16 0 16 1 0 15 0
Pradesh
10 Andhra East Godavari Approved 1 0 1 0 0 1 0
Pradesh
11 Andhra East Godavari Pending 1 0 1 0 0 1 0
Pradesh
12 Andhra Guntur Pending 1 0 1 0 0 1 0
Pradesh
13 Andhra Guntur Verification 1 0 1 0 0 1 0
Pradesh
14 Andhra Krishna Approved 9 0 9 2 0 7 2
Pradesh
15 Andhra Krishna Pending 38 4 34 0 0 34 0
Pradesh
16 Andhra Krishna Verification 19 0 19 3 0 16 3
Pradesh
17 Andhra Kurnool Approved 19 0 19 4 0 15 4
Pradesh
18 Andhra Kurnool Pending 13 3 10 0 0 10 0
Pradesh
19 Andhra Kurnool Verification 16 0 16 5 0 11 5
Pradesh
20 Andhra Nellore Approved 22 0 22 5 0 17 5
Pradesh
21 Andhra Nellore Pending 57 2 55 0 0 55 0
Pradesh
22 Andhra Nellore Verification 16 0 16 9 0 7 9
Pradesh
Page 12 of 2823 Andhra Prakasam Approved 51 0 51 7 0 44 7
Pradesh
24 Andhra Prakasam Pending 24 8 16 0 10 6 0
Pradesh
25 Andhra Prakasam Verification 80 0 80 30 0 50 29
Pradesh
26 Andhra Srikakulam Approved 284 0 284 12 0 272 12
Pradesh
27 Andhra Srikakulam Pending 18 11 7 0 0 7 0
Pradesh
28 Andhra Srikakulam Verification 97 0 97 9 0 88 9
Pradesh
29 Andhra Visakhapatnam Approved 4 0 4 0 0 4 0
Pradesh
30 Andhra Visakhapatnam Verification 1 0 1 0 0 1 0
Pradesh
31 Andhra Vizianagaram Approved 80 0 80 9 0 71 9
Pradesh
32 Andhra Vizianagaram Pending 16 14 2 0 0 2 0
Pradesh
33 Andhra Vizianagaram Verification 37 0 37 4 0 33 4
Pradesh
34 Andhra West Godavari Approved 9 0 9 0 0 9 0
Pradesh
35 Andhra West Godavari Pending 2 1 1 0 0 1 0
Pradesh
36 Andhra West Godavari Verification 2 0 2 0 0 2 0
Pradesh
37 Andhra Parvathipuram Approved 194 0 194 41 0 153 13
Pradesh Manyam
38 Andhra Parvathipuram Pending 218 35 183 11 11 161 0
Pradesh Manyam
39 Andhra Parvathipuram Verification 61 0 61 18 0 43 17
Pradesh Manyam
40 Andhra Anakapalli Approved 5 0 5 1 0 4 1
Pradesh
41 Andhra Anakapalli Pending 70 3 67 4 0 63 0
Pradesh
42 Andhra Anakapalli Verification 6 0 6 1 0 5 0
Pradesh
43 Andhra Alluri Approved 675 0 675 91 0 584 91
Pradesh Sitharama Raju
44 Andhra Alluri Pending 188 138 50 0 2 48 0
Pradesh Sitharama Raju
45 Andhra Alluri Verification 279 0 279 61 0 218 61
Pradesh Sitharama Raju
46 Andhra Kakinada Approved 3 0 3 3 0 0 1
Pradesh
47 Andhra Kakinada Pending 19 0 19 0 0 19 0
Pradesh
48 Andhra Kakinada Verification 4 0 4 1 0 3 1
Pradesh
49 Andhra Eluru Approved 18 0 18 5 0 13 5
Pradesh
50 Andhra Eluru Pending 79 8 71 2 0 69 0
Pradesh
51 Andhra Eluru Verification 18 0 18 13 0 5 12
Pradesh
Page 13 of 2852 Andhra Ntr Approved 1 0 1 1 0 0 0
Pradesh
53 Andhra Ntr Pending 3 2 1 1 0 0 0
Pradesh
54 Andhra Ntr Verification 6 0 6 1 0 5 1
Pradesh
55 Andhra Bapatla Approved 2 0 2 0 0 2 0
Pradesh
56 Andhra Bapatla Pending 8 0 8 0 0 8 0
Pradesh
57 Andhra Bapatla Verification 4 0 4 0 0 4 0
Pradesh
58 Andhra Palnadu Approved 8 0 8 1 0 7 1
Pradesh
59 Andhra Palnadu Pending 18 10 8 0 0 8 0
Pradesh
60 Andhra Palnadu Verification 4 0 4 4 0 0 4
Pradesh
61 Andhra Tirupati Approved 150 0 150 9 0 141 9
Pradesh
62 Andhra Tirupati Pending 32 31 1 0 0 1 0
Pradesh
63 Andhra Tirupati Verification 81 0 81 2 0 79 2
Pradesh
64 Andhra Annamayya Approved 28 0 28 2 0 26 2
Pradesh
65 Andhra Annamayya Pending 440 68 372 2 1 369 0
Pradesh
66 Andhra Annamayya Verification 9 0 9 3 0 6 3
Pradesh
67 Andhra Sri Sathya Sai Approved 135 0 135 7 0 128 7
Pradesh
68 Andhra Sri Sathya Sai Pending 12 12 0 0 0 0 0
Pradesh
69 Andhra Sri Sathya Sai Verification 54 0 54 22 0 32 22
Pradesh
70 Andhra Nandyal Approved 7 0 7 0 0 7 0
Pradesh
71 Andhra Nandyal Pending 7 3 4 0 0 4 0
Pradesh
72 Andhra Nandyal Verification 3 0 3 0 0 3 0
Pradesh
73 Andhra Dr BR Approved 23 0 23 6 0 17 6
Pradesh Ambedkar
Konaseema
74 Andhra Dr BR Pending 14 3 11 0 0 11 0
Pradesh Ambedkar
Konaseema
75 Andhra Dr BR Verification 41 0 41 4 0 37 4
Pradesh Ambedkar
Konaseema
*****
Page 14 of 28Annexure-III
Annexure referred to in reply to part (b) of Lok SabhaStarred Q.No.
145due for reply on 10.02.2026
Details of road works sanctioned in Udaipur district of Rajasthan under PMGSY-IV
Total
Pavement
Package Cost
Sl.No District Block Year Road Name Length (in
Number (in
Kms.)
lakhs)
2025
RJ32P4- L023-GHODAN
1 Udaipur Bargaon - 0.7 47.44
16 KALAN TO GEL
2026
2025
RJ32P4-
2 Udaipur Devla - L022-AR KYARIYA 2.1 157.35
06
2026
2025
RJ32P4- L023-AR HALDURA
3 Udaipur Devla - 3.2 228.56
06 PHALLA
2026
2025
RJ32P4- L027-AR THAMLA
4 Udaipur Devla - 1.5 118.36
06 BERI
2026
2025
RJ32P4- L025-AR HULRI
5 Udaipur Devla - 3.2 233.06
06 GHATI
2026
2025
RJ32P4- L037-AR Upla
6 Udaipur Girwa - 2 149.96
03 Kheda
2026
2025
RJ32P4- L036-AR Naliya
7 Udaipur Girwa - 1.1 85.44
03 Fala
2026
2025
RJ32P4- L021-AR Dagliya
8 Udaipur Girwa - 1.8 138.15
01 Fala
2026
2025
RJ32P4- L026-AR Solanki
9 Udaipur Girwa - 1.8 134.21
04 Fala
2026
2025
RJ32P4- L027-AR Umariya
10 Udaipur Girwa - 0.6 42.03
04 Kand
2026
2025
RJ32P4-
11 Udaipur Girwa - L034-AR Gawadi 1.5 134.78
03
2026
2025
RJ32P4- L033-AR
12 Udaipur Girwa - 1.8 142.07
02 Segawaton ka Fala
2026
2025
RJ32P4- L028-AR Nichali
13 Udaipur Girwa - 1.3 116.11
02 Himali
2026
Page 15 of 282025
RJ32P4- L030-AR
14 Udaipur Girwa - 1.1 85.91
02 Sonawaton ka Fala
2026
2025
RJ32P4- L029-AR Upali
15 Udaipur Girwa - 2.3 180.18
02 Himali
2026
2025
RJ32P4-
16 Udaipur Girwa - L022-AR Talai Fala 1.3 98.08
01
2026
2025
RJ32P4-
17 Udaipur Girwa - L024-AR Khed 4.8 383.56
03
2026
2025
RJ32P4- L023-AR Bindra
18 Udaipur Girwa - 1.1 96.32
01 Fala
2026
2025
RJ32P4- L025-AR Ratliya
19 Udaipur Girwa - 1.5 122.48
04 Kheda
2026
2025
RJ32P4- L032-AR Hakriya
20 Udaipur Girwa - 2.2 175.1
02 Fala
2026
2025
RJ32P4- L040-AR
21 Udaipur Gogunda - 0.575 43.45
16 Bheelwara
2026
2025
RJ32P4- L027-obra kalan to
22 Udaipur Gogunda - 0.8 50.74
16 bheelwara
2026
2025 L034-Amba road
RJ32P4-
23 Udaipur Gogunda - km 1 to solmakiya 2.1 156.25
16
2026 ka was
2025
RJ32P4-
24 Udaipur Gogunda - L022-AR Dang 1.5 105.53
16
2026
2025
RJ32P4- L029-AR
25 Udaipur Jhadol - 2.21 170.9
08 BHANWARIA
2026
2025
RJ32P4-
26 Udaipur Jhadol - L025-AR KUNDAL 2.6 185.36
08
2026
2025
RJ32P4- L023-AR
27 Udaipur Jhadol - 2.1 150.91
07 SAHIWARA
2026
2025 L021-AR
RJ32P4-
28 Udaipur Jhadol - DUNGARIYA 2.21 176.37
07
2026 PHALLA
2025
RJ32P4- L042-AR Gati
29 Udaipur Jhadol - 2.2 165.66
08 Vasala
2026
2025
RJ32P4- L027-AR KAMLI
30 Udaipur Jhadol - 1.5 113.49
07 BADLI
2026
Page 16 of 282025
RJ32P4- L022-AR
31 Udaipur Jhadol - 1.5 117.46
08 GADRIYAWAS
2026
2025
RJ32P4- L028-AR HITRI
32 Udaipur Jhadol - 2 149.9
07 PHALLA
2026
2025
RJ32P4-
33 Udaipur Jhadol - L033-AR KOLYARA 2.5 188.93
08
2026
2025
RJ32P4- L026-AR
34 Udaipur Jhadol - 1.34 101.2
07 NICCHALA PHALLA
2026
2025
RJ32P4- L035-AR karchha
35 Udaipur Kherwara - 0.9 62
12 kalan
2026
2025
RJ32P4- L023-AR
36 Udaipur Kherwara - 1.7 126.48
12 Meethimahuri
2026
2025
RJ32P4-
37 Udaipur Kherwara - L024-AR Palia 2 150.83
12
2026
2025
RJ32P4-
38 Udaipur Kherwara - L033-AR Suberi 3.7 286.83
12
2026
2025
RJ32P4- L029-AR
39 Udaipur Kherwara - 1.5 109.55
19 Khanmeen
2026
2025
RJ32P4- L031-AR Samited
40 Udaipur Kherwara - 1.2 90.47
12 Fala
2026
2025
RJ32P4-
41 Udaipur Kherwara - L028-AR Kandal 1.34 105.61
12
2026
2025
RJ32P4-
42 Udaipur Kotra - L023-AR JALIBORE 3 227.41
09
2026
2025
RJ32P4- L025-AR SADATON
43 Udaipur Kotra - 2 149.22
09 KA PHALA
2026
2025
RJ32P4- L022-AR
44 Udaipur Kotra - 2.1 156.45
09 CHAMPAWAS
2026
2025
RJ32P4- L025-AR
45 Udaipur Kurabad - 1.5 112.53
05 Patookhera
2026
2025 L022-AR
RJ32P4-
46 Udaipur Kurabad - RamajKheda 1.4 108.06
05
2026 Rigliya Fala
2025
RJ32P4-
47 Udaipur Kurabad - L023-AR Dhimda 0.8 59.65
05
2026
Page 17 of 282025
RJ32P4-
48 Udaipur Kurabad - L024-AR Kakodiya 2.5 192.1
05
2026
2025
RJ32P4-
49 Udaipur Nayagaon - L027-AR Maliphala 3.79 292.6
15
2026
2025
RJ32P4-
50 Udaipur Nayagaon - L037-AR Kharkaya 1.73 147.42
15
2026
2025 L029-AR Nai
RJ32P4-
51 Udaipur Nayagaon - Sukhapada Mangali 0.8 60.85
15
2026 Fala
2025
RJ32P4-
52 Udaipur Nayagaon - L035-AR Suraj Pura 0.93 69.9
15
2026
2025
RJ32P4-
53 Udaipur Nayagaon - L028-AR Matai Fala 1.3 98.55
15
2026
2025
RJ32P4- L032-AR Ramdeoji
54 Udaipur Nayagaon - 0.9 50.4
15 Temple
2026
2025
RJ32P4-
55 Udaipur Nayagaon - L021-AR Aamli Fala 1 75.95
15
2026
2025
RJ32P4- L032-AR SHISHAV
56 Udaipur Phalasiya - 5.9 445.75
10 PHALLA
2026
2025
RJ32P4- L033-AR UPALI
57 Udaipur Phalasiya - 3 227.05
10 GORANWAS
2026
2025
RJ32P4-
58 Udaipur Phalasiya - L031-AR PATIYA 2 151.27
11
2026
2025
RJ32P4- L026-AR AMBA
59 Udaipur Phalasiya - 2 151.3
11 PHALLA
2026
2025
RJ32P4-
60 Udaipur Phalasiya - L025-AR TINDORI 3 226.88
11
2026
2025
RJ32P4- L028-AR PAN
61 Udaipur Phalasiya - 2.5 189.3
10 TALAI PHALLA
2026
2025
RJ32P4- L030-AR UPLA
62 Udaipur Phalasiya - 2.5 188.78
11 PHALLA
2026
2025
RJ32P4- L024-AR RANA
63 Udaipur Phalasiya - 2 150.88
11 BORA
2026
2025
RJ32P4-
64 Udaipur Phalasiya - L022-AR KHADRA 3 227.31
11
2026
Page 18 of 282025
RJ32P4- L027-AR GORNA
65 Udaipur Phalasiya - 3 227.34
10 PHALLA
2026
2025
RJ32P4-
66 Udaipur Rishbhdeo - L030-AR Nai Basti 3 224.47
13
2026
2025
RJ32P4- L031-AR Bhagora
67 Udaipur Rishbhdeo - 3.5 262.12
13 Fala
2026
2025
RJ32P4- L026-AR Garada
68 Udaipur Rishbhdeo - 5 346.56
13 Fala
2026
2025
RJ32P4-
69 Udaipur Rishbhdeo - L029-AR Rapeta 2.5 199.75
14
2026
2025
RJ32P4-
70 Udaipur Rishbhdeo - L027-AR Pagara 0.81 45.22
13
2026
2025
RJ32P4- L033-Barna to
71 Udaipur Rishbhdeo - 3 214.47
14 Ahari Fala
2026
2025
RJ32P4-
72 Udaipur Rishbhdeo - L024-AR Parji Fala 2.05 157.77
14
2026
2025
RJ32P4- L034-AR Gogan
73 Udaipur Rishbhdeo - 0.67 49.53
13 Fala
2026
2025
RJ32P4-
74 Udaipur Rishbhdeo - L025-AR Pagatfala 2 152.44
14
2026
2025
RJ32P4- L032-Balewadi to
75 Udaipur Rishbhdeo - 2.2 165.03
14 Ahari Fala
2026
2025
RJ32P4-
76 Udaipur Rishbhdeo - L022-AR Kopcha 2 139.71
13
2026
2025
RJ32P4-
77 Udaipur Rishbhdeo - L028-AR Boojh Fala 3.5 259.14
14
2026
L026-Brahamno ka
2025
RJ32P4- Kalwana to
78 Udaipur Sayra - 3.4 257.91
18 Bheelwara via
2026
Chanderi
2025 L027-Palidana
RJ32P4-
79 Udaipur Sayra - baguni road to 2 145.37
17
2026 Dang
2025
RJ32P4- L021-MDR 147 to
80 Udaipur Sayra - 1.8 129.17
17 Chhapara
2026
RJ32P4- 2025 L023-Visma Hayla
81 Udaipur Sayra 1.9 151.28
18 - Road to Mamadev
Page 19 of 282026
2025
RJ32P4- L028-MDR 147 to
82 Udaipur Sayra - 0.7 49.85
17 Sathi Ka Hoda
2026
L032-DHOL
2025
RJ32P4- PUNAWALI ROAD
83 Udaipur Sayra - 1.4 101.21
17 TO PARTA JI KI
2026
BHAGAL
2025
RJ32P4- L024-Jemli Road to
84 Udaipur Sayra - 2.9 212.44
18 Jogidas Ji Ka Guda
2026
Grand Total: 171.355 12927.43
Details of road works sanctioned in Salumbar district of Rajasthan under PMGSY-
IV
Total
Pavement
Package Cost
Sl.No District Block Year Road Name Length (in
Number (in
Kms.)
lakhs)
2025
RJ48P4- L026-AR renth
1 Salumbar Jaisamand - 2.4 172.16
09 guriya
2026
2025
RJ48P4- L025-AR kaviti
2 Salumbar Jaisamand - 0.9 69.31
01 kheda
2026
2025
RJ48P4- L028-SH 32 to
3 Salumbar Jaisamand - 1 70.42
01 khakhal
2026
2025
RJ48P4- L023-AR wadi
4 Salumbar Jaisamand - 4 288.6
01 fala
2026
2025
RJ48P4- L024-oda to
5 Salumbar Jaisamand - 2 154.84
01 damar
2026
2025
RJ48P4- L027-kantora to
6 Salumbar Jaisamand - 2.5 184.03
02 ghanchopad
2026
2025
RJ48P4- L022-AR hawna
7 Salumbar Jaisamand - 2.5 185.53
01 pani
2026
2025
RJ48P4- L029-bobus to
8 Salumbar Jaisamand - 1.3 93.04
01 limbawali
2026
2025
RJ48P4- L024-Sajnot to
9 Salumbar Jhallara - 2.1 165.65
03 Nayaghar
2026
2025 L033-AR Dhaora
RJ48P4-
10 Salumbar Jhallara - to Bada Dolpura 0.501 38.78
03
2026 Adivasi Basti
Page 20 of 282025
RJ48P4- L025-Lauwa to
11 Salumbar Jhallara - 1.15 84.06
03 Meena Basti
2026
2025 L029-Jhallara
RJ48P4-
12 Salumbar Jhallara - Dhariyawad Road 1 72.14
03
2026 to Damor Fala
L030-Payra
2025
RJ48P4- Gated Road to
13 Salumbar Jhallara - 1.15 90.09
03 Chudawala Sagar
2026
Fala
2025
RJ48P4- L023-Bori Gated
14 Salumbar Jhallara - 1.93 153.87
03 Road to Salotara
2026
L032-Sheshpur
2025
RJ48P4- Kenar Road to
15 Salumbar Jhallara - 1.25 93.04
03 Budel Fala
2026
Prabhu
2025 L028-AR
RJ48P4-
16 Salumbar Jhallara - Hadmatiya Kalan 0.8 60.65
03
2026 to Dhala Fala
2025 L023-AR dholiya
RJ48P4-
17 Salumbar Lasadiya - to Nimadi Negad 4 309.2
04
2026 fala
2025
RJ48P4- L036-AR
18 Salumbar Lasadiya - 3 205.4
05 Bhanawat pura
2026
2025
RJ48P4- L033-AR pipla
19 Salumbar Lasadiya - 2 148.5
04 pani
2026
2025 L028-Kun Panund
RJ48P4-
20 Salumbar Lasadiya - Road to Ghati 3 243.14
06
2026 fala
2025 L029-Lasadiya
RJ48P4-
21 Salumbar Lasadiya - Dhariyawad Road 3 214.49
04
2026 to Bharbhada
2025 L021-Gundawat
RJ48P4-
22 Salumbar Lasadiya - ghati to dangela 3 211.35
04
2026 Road
2025 L024-Salumber
RJ48P4-
23 Salumbar Lasadiya - Bansi Road KM 6 2.6 198.13
05
2026 to kaladata
2025
RJ48P4-
24 Salumbar Lasadiya - L034-AR gangari 3 220.23
05
2026
2025
RJ48P4-
25 Salumbar Lasadiya - L035-AR Paoti 0.9 65.72
06
2026
2025 L025-mader
RJ48P4-
26 Salumbar Lasadiya - tiraha road to 1 77.44
06
2026 palota
27 Salumbar Lasadiya RJ48P4- 2025 L022-AR 2 147.44
Page 21 of 2805 Karnagarh to Bibi
-
2026 fala
2025 L032-Shobhji ka
RJ48P4-
28 Salumbar Lasadiya - guda school to 1.55 118.96
05
2026 khejadiya fala
2025 L031-Bor ka pani
RJ48P4-
29 Salumbar Lasadiya - Road to 2 147.96
05
2026 Nalmohadi
2025
RJ48P4- L031-AR Jhalar
30 Salumbar Salumbar - 0.65 48.73
07 Fala
2026
2025
RJ48P4-
31 Salumbar Salumbar - L025-AR Bhagal 1.5 111.67
07
2026
2025
RJ48P4-
32 Salumbar Salumbar - L022-AR jaitpura 3.85 284.83
07
2026
2025
RJ48P4-
33 Salumbar Salumbar - L026-AR Dhaniria 0.7 51.94
07
2026
2025
RJ48P4- L028-AR Suron
34 Salumbar Salumbar - 0.6 41.3
07 ka Kua
2026
2025
RJ48P4- L024-AR Baman
35 Salumbar Salumbar - 3 224.53
07 Magari
2026
2025 L022-Main road
RJ48P4-
36 Salumbar Sarada - khodi mahudi to 1.8 121.39
08
2026 bangla fala
2025 L021-khodi
RJ48P4-
37 Salumbar Sarada - mahudi school to 2.45 195.39
08
2026 rijudarra
2025 L022-Palodara
RJ48P4-
38 Salumbar Semari - kalyanppur Road 2.2 162.23
08
2026 to Bhopa fala
2025
RJ48P4-
39 Salumbar Semari - L023-AR Dol fala 2 142.41
08
2026
Grand Total: 76.281 5668.59
Page 22 of 28Details of road works sanctioned in Dungarpur district of Rajasthan under PMGSY-
IV
Pavement
Package Total
Sl.no District Block Year Road Name Length (in
Number Cost
Kms.)
2025
RJ14P4-
1 Dungarpur Aspur - L366-AR Bhagela 1.3 96.35
01
2026
2025
RJ14P4- L367-AR Kayda
2 Dungarpur Aspur - 1.15 86.91
01 Fala
2026
2025
RJ14P4-
3 Dungarpur Aspur - L368-AR Era Fala 1.55 109.35
01
2026
2025
RJ14P4- L369-AR
4 Dungarpur Aspur - 1.4 85.98
01 Vannaliya Fala
2026
2025 L024-AR to
RJ14P4-
5 Dungarpur Bichhiwara - Nayatalab 1.05 95.66
02
2026 (Chundawara)
2025
RJ14P4- L021-AR to
6 Dungarpur Bichhiwara - 2 170.24
02 Kherapal
2026
2025
RJ14P4- L023-AR Udardiya
7 Dungarpur Chikhali - 2.5 198.48
03 to sathiya fala
2026
2025 L039-Main Road
RJ14P4-
8 Dungarpur Chikhali - doongarsaran to 0.725 45.08
03
2026 Dholi
L031-CHIKHALI
2025
RJ14P4- AMBARA MAIN
9 Dungarpur Chikhali - 1.66 120.2
03 ROAD TO
2026
BAMANIYA FALA
2025 L041-Main Road
RJ14P4-
10 Dungarpur Chikhali - Dariyati Bansiya 1.5 104.63
03
2026 to Mali
2025 L026-AR
RJ14P4-
11 Dungarpur Chikhali - Katarapada to 0.99 60.22
04
2026 mandir fala
2025 L036-AR chack
RJ14P4-
12 Dungarpur Chikhali - chadiyala to 1.625 68.78
04
2026 kaliyari
2025 L038-Main Road
RJ14P4-
13 Dungarpur Chikhali - doongarsaran to 1.8 117.1
03
2026 Kolani
2025 L035-Nai basti
RJ14P4-
14 Dungarpur Chikhali - badgama bujwara 1.4 93.53
04
2026 road to bhadar
Page 23 of 282025 L037-Main Road
RJ14P4-
15 Dungarpur Chikhali - Sira wali mangari 2 140.01
03
2026 to gudiya fala
L040-AR
2025
RJ14P4- Salakhadi se
16 Dungarpur Chikhali - 1.8 126.27
04 kehodiafala tak
2026
sampark sadak
L021-CHIKHALI
2025
RJ14P4- AMBARA MAIN
17 Dungarpur Chikhali - 0.89 72.2
03 ROAD TO MAHUDI
2026
FALA
2025 L033-kunwa
RJ14P4-
18 Dungarpur Chikhali - doongarsaran 1.85 117.99
04
2026 road to bujwara
2025 L034-AR Galalpura
RJ14P4-
19 Dungarpur Chikhali - se ahari fala tak 0.675 46
04
2026 sampark sadak
2025 L022-DARIYATI
RJ14P4-
20 Dungarpur Chikhali - BANSIYA TO 1.88 119.32
04
2026 BANJARA BASTI
2025
RJ14P4- L025-AR debra to
21 Dungarpur Chikhali - 2 137.14
03 bamaniya
2026
2025
RJ14P4- L028-AR to
22 Dungarpur Dovada - 1.35 110.09
05 Dharuda (Khara)
2026
2025 L025-AR to
RJ14P4-
23 Dungarpur Dovada - Dungra Fala (Veeri 3 231.89
05
2026 With Chak
2025
RJ14P4- L027-AR to Ray
24 Dungarpur Dovada - 1.8 128.65
05 Fala (Dara)
2026
2025 L026-AR to
RJ14P4-
25 Dungarpur Dovada - Suthariya 1.25 94.62
05
2026 (Manpur)
2025 L023-AR to Katara
RJ14P4-
26 Dungarpur Dovada - Ghati (Lolakpur 3 218.55
05
2026 With Chak)
2025
RJ14P4- L022-AR to Uta
27 Dungarpur Dovada - 1.7 141.32
05 Fala (Selaj)
2026
2025 L024-AR to
RJ14P4-
28 Dungarpur Dovada - Bhukhara Fala 1.25 100.49
05
2026 (Selaj)
2025 L021-AR to
RJ14P4-
29 Dungarpur Dovada - Lambired 2.7 200.01
05
2026 (Baiyora)
L024-Bhura Ghati
2025
RJ14P4- to Deva Bhai
30 Dungarpur Galiyakoat - 1 66.18
06 House Road to
2026
Garasiya
Page 24 of 282025 L023-AR
RJ14P4-
31 Dungarpur Galiyakoat - MAHUWARA TO 1.5 100.12
06
2026 DOLARIYA FALA
2025 L026-AR MODRA
RJ14P4-
32 Dungarpur Galiyakoat - DOULATPURA TO 0.55 39.04
06
2026 GARASIYA FALA
2025
Gamdi RJ14P4-
33 Dungarpur - L022-AR to Ramali 1.4 92.59
Ahara 07
2026
2025
Gamdi RJ14P4- L021-AR to Gadidi
34 Dungarpur - 2.9 297.67
Ahara 07 Fala
2026
L025-AR to
2025
RJ14P4- Valkunda
35 Dungarpur Jothari - 1.4 119.68
08 (Bheelwa
2026
Pachela)
2025
RJ14P4- L021-AR to Vadli
36 Dungarpur Jothari - 1.1 98.41
08 (Mal)
2026
2025
RJ14P4- L028-AR to Bhitiya
37 Dungarpur Jothari - 1.75 127.75
08 Fala (Balwanya)
2026
2025
RJ14P4- L024-AR to Dungri
38 Dungarpur Jothari - 1.2 94.96
08 (Pagara Surata)
2026
2025
RJ14P4- L027-AR to Jundi
39 Dungarpur Jothari - 0.85 72.63
08 Fala (Ariwat)
2026
2025 L026-AR to New
RJ14P4-
40 Dungarpur Jothari - Basti Fala 1.65 118.65
08
2026 (Ariwat)
2025
RJ14P4- L023-AR to
41 Dungarpur Jothari - 1.9 148.27
08 Suthariya (Mal)
2026
2025 L021-AR to
RJ14P4-
42 Dungarpur Paldeval - Harizen Basti 1.75 122.97
09
2026 (Dewal khas)
2025
RJ14P4- L022-AR to Koted
43 Dungarpur Paldeval - 2.05 156.39
09 Fala (Tari Obri)
2026
2025
RJ14P4- L023-AR to Dara
44 Dungarpur Paldeval - 2 142.72
09 Fala (Tari Obri)
2026
2025
RJ14P4- L024-AR to Ahari
45 Dungarpur Paldeval - 1.5 111.52
09 Fala (Tari Obri)
2026
2025
RJ14P4-
46 Dungarpur Sabla - L416-AR Hilawadi 3 168.5
10
2026
RJ14P4- 2025 L417-AR
47 Dungarpur Sabla 1.6 93.93
10 - Chhaplawa Dhani
Page 25 of 282026
2025
RJ14P4- L418-AR Hamiya
48 Dungarpur Sabla - 1.8 121.06
10 Fala
2026
2025 L026-SAMPARK
RJ14P4-
49 Dungarpur Sagwara - SADAK 2.2 183.01
11
2026 HADPALIYA FALA
2025
RJ14P4- L036-Danvadli to
50 Dungarpur Simalwara - 1.875 103.73
11 ran bhatiya
2026
Grand Total: 82.77 6016.84
Details of road works sanctioned in Pratapgarh district of Rajasthan under
PMGSY-IV
Pavement
Package Total
Sl.No District Block Year Road Name Length (in
Number Cost
Kms.)
RJ33P4- 2025 - L023-AR
1 Pratapgarh Dhariawad 0.68 52.95
01 2026 Aamli Fala
RJ33P4- 2025 - L025-AR Bodi
2 Pratapgarh Dhariawad 1.84 134.85
01 2026 Magri
RJ33P4- 2025 - L026-AR
3 Pratapgarh Dhariawad 1 66.86
01 2026 Meghwal Fala
RJ33P4- 2025 - L027-AR
4 Pratapgarh Dhariawad 3.5 238.39
01 2026 Khedi Fala
RJ33P4- 2025 - L031-AR
5 Pratapgarh Dhariawad 0.6 54.25
01 2026 Kundi Fala
RJ33P4- 2025 - L034-AR
6 Pratapgarh Dhariawad 1.2 135.67
01 2026 Kutada Fala
RJ33P4- 2025 - L035-AR
7 Pratapgarh Dhariawad 0.65 126.75
01 2026 Jagalwa
RJ33P4- 2025 - L037-AR Medi
8 Pratapgarh Dhariawad 1 64.64
01 2026 Fala
Peepal RJ33P4- 2025 -
9 Pratapgarh L022-Umbada 4.85 469.45
Khoont 02 2026
Peepal RJ33P4- 2025 - L021-
10 Pratapgarh 1.1 100.42
Khoont 02 2026 Barovonpara
Peepal RJ33P4- 2025 - L023-
11 Pratapgarh 1 80.38
Khoont 02 2026 jhapapara
Grand Total: 17.42 1524.62
*****
Page 26 of 28Annexure-IV
Annexure referred to in reply to part (e) of Lok SabhaStarred Q.No.
145due for reply on 10.02.2026
Sr.No State District Approval Total Connected Un- Approved Pending Rejected Eligible
Name Name (Status By Survey Survey Connected Un- Un- Un- Total
NRIDA) Survey Connected C onnected C onnected
Survey Survey Survey
By State By State By State
Grand Total 14 0 14 0 0 14 0
Approved 2 0 2 0 0 2 0
Pending 8 0 8 0 0 8 0
Verification 4 0 4 0 0 4 0
1 Andhra Bapatla Approved 2 0 2 0 0 2 0
Pradesh
2 Andhra Bapatla Pending 8 0 8 0 0 8 0
Pradesh
3 Andhra Bapatla Verification 4 0 4 0 0 4 0
Pradesh
Sr.No State District Approval Total Connected Un- Approved Pending Rejected Eligible
Name Name (Status Survey Survey Connected Un- Un- Un- Total
By NRIDA) Survey Connected C onnected Connected
Survey Survey Survey
By State By State By State
Grand Total 79 0 79 79 0 0 78
Approved 77 0 77 77 0 0 77
Pending 1 0 1 1 0 0 0
Verification 1 0 1 1 0 0 1
1 Madhya Shahdol Approved 77 0 77 77 0 0 77
Pradesh
2 Madhya Shahdol Pending 1 0 1 1 0 0 0
Pradesh
3 Madhya Shahdol Verification 1 0 1 1 0 0 1
Pradesh
Sr.No State District Approval Total Connected Un- Approved Pending Rejected Eligible
Name Name (Status Survey Survey Connected Un- Un- Un- Total
By NRIDA) Survey Connected C onnected C onnected
Survey Survey Survey
By State By State By State
Grand Total 451 15 436 431 0 5 330
Approved 178 0 178 178 0 0 175
Pending 104 15 89 84 0 5 0
Verification 169 0 169 169 0 0 155
1 Odisha Nawarangpur Approved 178 0 178 178 0 0 175
2 Odisha Nawarangpur Pending 104 15 89 84 0 5 0
3 Odisha Nawarangpur Verification 169 0 169 169 0 0 155
Page 27 of 28Sr.No State District Approval Total Connected Un- Approved Pending Rejected Eligible
Name Name (Status By Survey Survey Connected Un- Un- Un- Total
NRIDA) Survey Connected Connected Connected
Survey By Survey By Survey By
State State State
Grand Total 243 0 243 242 0 1 208
Approved 209 0 209 209 0 0 184
Pending 3 0 3 2 0 1 0
Verification 31 0 31 31 0 0 24
1 Jharkhand Hazaribagh Approved 209 0 209 209 0 0 184
2 Jharkhand Hazaribagh Pending 3 0 3 2 0 1 0
3 Jharkhand Hazaribagh Verification 31 0 31 31 0 0 24
Sr.No State District Approval Total Connected Un- Approved Pending Rejected Eligible
Name Name (Status Survey Survey Connected Un- Un- Un- Total
By NRIDA) Survey Connected Connected C onnected
Survey By Survey Survey By
State By State State
Grand Total 3 0 3 3 0 0 3
Approved 1 0 1 1 0 0 1
Pending 0 0 0 0 0 0 0
Verification 2 0 2 2 0 0 2
1 Jharkhand Ramgarh Approved 1 0 1 1 0 0 1
2 Jharkhand Ramgarh Verification 2 0 2 2 0 0 2
*****
Page 28 of 28