GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 1318
ANSWERED ON - 11/02/2026
STATUS OF THE GOLDEN QUADRILATERAL AND NORTH–SOUTH AND
EAST–WEST CORRIDOR PROJECTS
1318. SHRI PARIMAL NATHWANI:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:-
(a) the present status of the Golden Quadrilateral (GQ) and North–South and East–West
(NS–EW) Corridor projects to provide quadrilateral road connectivity across the country;
(b) details of the stretches completed, under construction and pending, corridor-wise and
State-wise;
(d) the reasons for delay, cost escalation or modification in alignment, if any, particularly
in the NS–EW Corridor; and
(e) the steps taken by Government to complete the remaining stretches and ensure
uniform four/six-lane connectivity along these corridors along with the revised timelines?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (e) The work on Golden Quadrilateral (GQ) covering Delhi-Mumbai-Chennai -
Kolkata – Delhi and East-West & North-South covering Porbader to Silchar and Srinagar to
Kanyakumari has been completed except at few locations/stretches as per the details annexed.
Various factors such as issues related to land acquisition, delays in pre-construction
activities, financial difficulties faced by contractors, force majeure events, and scarcity of
construction materials etc. have resulted in delays and cost overrun in certain projects.
To overcome these challenges and expedite project execution, various initiatives have
been undertaken. These include streamlining and expediting the land acquisition process
through Bhoomi Rashi portal, revamping the Parivesh Portal to expedite forest and
environmental clearances, enabling online approval of General Arrangement Drawings
(GAD) for Road over Bridges (ROBs) and Road under Bridges (RUB) from the Railways,
and conducting review meetings at various levels with all stakeholders, including State
Governments. The Government is taking all necessary steps for timely completion of these
projects.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) TO (e) OF RAJYA SABHA
UNSTARRED QUESTION NO. 1318 ANSWERED ON 11/02/2026 ASKED BY SHRI
PARIMAL NATHWANI REGARDING ‘STATUS OF THE GOLDEN QUADRILATERAL
AND NORTH–SOUTH AND EAST–WEST CORRIDOR PROJECTS’
Status of Golden Quadrilateral, North - South Corridor and East - West Corridor
projects
Status
GQ/ NS/
Lane (Completed/
SN EW State Stretch/Project Name Length
Configuration Under
Projects
Construction)
Balance work of construction
of 4 lane Road from Km
140.700 to Km 190.587
East- (Narimbanglo - Jatinga
Under
1 West Assam Junction – Harangajao) of NH- 49.2 4L
Construction
Corridor 54 (New NH-27 EW) in the
State of Assam under
Bharatmala Pariyojana on
Hybrid Annuity Mode
Construction of Tunnel (Pkg-I)
North-
from Marog to Digdol in Under
2 South J&K 4.4 4L
Ramban to Banihal section of construction
Corridor
NH-44 in J&K
Construction of Tunnel (Pkg-II)
North-
from Digdol to Khuni- Nallah Under
3 South J&K 3.2 4L
in Ramban-Banihal section of construction
Corridor
NH-44 in J&K
Construction of Viaduct (Pkg-
North-
III) from Makarkot (Ramsoo) Under
4 South J&K 6.0 4L
to Sherbibi in Ramban-Banihal construction
Corridor
section of NH-44 in J&K
East- Binnaguri Bypass km 17.500 to
West Under
5 West km 23.00 on NH-31D (New 5.5 4L
Bengal Construction
Corridor NH-27)
Dhupguri (km 83.34) –
East- Appointed date
West Falakata (km113.200) section
6 West 29.9 4L yet to be
Bengal of NH-31D (PKG-2B) (New
Corridor declared
NH-27)
Falakata (km 113.200) –
East-
West Salsalabari (km 154.854) Under
7 West 41.7 4L
Bengal section of NH-31D (PKG-2A) Construction
Corridor
(New NH-27)
*****