GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6164
TO BE ANSWERED ON 01.04.2026
SUBURBAN TRAIN SERVICES IN MUMBAI
6164. SHRI SANJAY DINA PATIL:
PROF. VARSHA EKNATH GAIKWAD:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has taken note of plans to introduce about
150–160 additional suburban train services in Mumbai to ease
congestion on existing routes of the Central Railway and Western
Railway suburban networks and if so, the details thereof;
(b) whether any assessment has been carried out regarding peak-hour
overcrowding on major corridors including those connecting Mumbai
with Thane, Kalyan, Virar and Panvel and the expected impact of the
proposed additional services on passenger load and if so, the details
thereof;
(c) the details of the routes on which these new services are proposed to
be introduced, along with the timeline for their operationalisation; and
(d) whether the Government is also considering complementary
infrastructure upgrades such as additional rakes, signalling
improvements and platform capacity expansion to support the proposed
increase in suburban services in Mumbai and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) At present, 3234 EMU local services including AC EMU services
are operated by Western Railway and Central Railway. Western Railway
operates 1414 services including 133 AC services, while Central Railway
operates 1820 services including 94 AC services which inter-alia caters the
need of passengers of Mumbai, Thane, Kalyan, Virar and Panvel. To
§ Page 1 of 10increase train handling capacity at various stations in Mumbai area,
following works have been completed/taken up/planned at various stations:
SN Location Details
1 Bandra Terminus 3 Pit Lines have been completed
2 Mumbai Central Platform extension for 24 LHB coaches
3 Jogeshwari 2 additional platforms
4 Dadar 1 additional platform
5 Vasai road 6 platforms, 3 pit lines and 5 stabling lines
6 Panvel-Kalamboli 5 platforms, 4 pit lines and 2 sick lines
7 Kalyan 6 platforms and 4 pit lines
8 LTT 4 platforms and 2 pit lines
9 Parel 6 platforms, 5 pit lines, 6 stabling lines
10 Virar 25 stabling lines
11 Dahanu road 11 stabling lines
12 Mira road 25 stabling lines
Platform length extension:
In addition to above, Platform extension work at 34 stations to
accommodate 15 car EMUs have been taken up.
To improve the capacity of rail network in Mumbai suburban area, Mumbai
Urban Transport Project (MUTP)-II costing ₹8,087 crore, MUTP-III costing
₹10,947 crore and MUTP-IIIA costing ₹33,690 crore have been sanctioned.
These projects include following works in Mumbai Suburban Area:
SN Name of project Cost
(₹ in crore)
1 6th Line Mumbai Central-Borivali (30 km) 919
2 Extension of Harbour Line Goregaon-Borivali (7 826
km)
3 Virar-Dahanu Road 3rd & 4th Line (64 km) 3587
4 5th & 6th Line CSTM-Kurla (17.5 km) 891
5 Panvel-Karjat Suburban Corridor (29.6 km) 2782
6 Airoli-Kalwa (elevated) Suburban Corridor link 476
(3.3 km)
7 5th & 6th line Borivali-Virar (26 km) 2184
Page 2 of 108 4th line between Kalyan-Asangaon (32 km) 1759
9 3rd & 4th line between Kalyan-Badlapur 1510
(14.05 km)
10 Kalyan Yard-Segregation of Main Line & 866
Suburban
11 Vasai bye pass line (Double line) between 176
Naigaon and Juchandra (5.73 Km)
12 3rd and 4th line between Badlapur & Karjat 1324
(32.46 km)
13 4th line between Asangaon & Kasara (34.97 km) 794
14 Trespass Control (34 locations) 551
Completion of Railway project/s depends on various factors which include
the following:
● Land acquisition by State Government
● Forest clearance
● Shifting of infringing utilities
● Statutory clearances from various authorities
● Geological and topographical conditions of area
● Law and order situation in the area of project site
● Number of working months in a year for particular project site etc.
All these factors affect the completion time of the project/s.
New generation trains:
To enhance passenger carrying capacity, 238 rakes of 12 cars each with
doors have been sanctioned under MUTP-III & IIIA at a cost of ₹19,293
crore. The process for procurement of these rakes has been taken up.
Besides, introduction of train services including EMU services on any
route/section, which is an on-going process, depends on various factors
which include:
● Capacity of that section
● Availability of path
Page 3 of 10● Availability of required rolling stock
● Availability of matching infrastructure for rolling stock
● Maintenance requirement of railway tracks and other assets
Traffic pattern of the passengers on Indian Railways is monitored on
regular basis and to cater to additional demand, load of existing trains are
augmented, new trains are introduced, frequency of existing trains is
increased etc. subject to operational feasibility.
The steps taken for providing additional rakes over Mumbai Suburban Rail
Network are as under:-
1) During the year 2025-26, four 12-car rakes of AC EMU (2 each to CR
& WR) and one 15-car rake of Non-AC EMU to WR has been received
to operate on Mumbai Suburban Rail Network.
2) In addition to above, ICF, Chennai has taken up development of two
Non-AC EMU rakes with Automatic Doors closure mechanism, to be
put in service in Mumbai Suburban Area.
3) Procurement of 238 rakes of 12 car under MUTP-III & MUTP-IIIA by
MRVC.
Amrit Bharat Stations:
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their implementation
in phases to improve the stations. The master planning includes:
● Improvement of access to station and circulating areas
● Integration of station with both sides of city
● Improvement of station building
● Improvement of waiting halls, toilets, sitting arrangement, water
booths
Page 4 of 10● Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
● Provision of lift/escalators/ramp
● Improvement /Provision of platform surface and cover over platforms
● Provision of kiosks for local products through schemes like ‘One
Station One Product’
● Parking areas, Multimodal integration
● Amenities for Divyangjans
● Better passenger information systems
● Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1,338 stations have been identified for development under this
scheme, out of which 132 stations are located in Maharashtra. The names
of stations identified for development under Amrit Bharat Station Scheme
in Maharashtra are as following:
State No. of Name of Stations
Stations
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road, Akola,
Akurdi, Amalner, Amgaon, Amravati, Andheri,
Badnera, Balharshah, Bandra Terminus, Baramati,
Belapur, Bhandara Road, Bhokar, Bhusawal,
Borivali, Byculla, Chalisgaon, Chanda Fort,
Chandrapur, Charni Road, Chhatrapati
Page 5 of 10Sambhajinagar, Chhatrapati Shivaji Maharaj
Terminus, Chinchpokli, Chinchwad, Dadar (CR),
Dadar (WR), Dahisar, Daund, Dehu Road, Devlali,
Dhamangaon, Dharangaon, Dharashiv, Dharmabad,
Dhule, Diva, Dudhani, Gangakher, Godhani,
Gondia, Grant Road, Hadapsar, Hatkanangale,
Hazur Sahib Nanded, Himayatnagar, Hinganghat,
Hingoli Deccan, Igatpuri, Jalgaon, Jalna, Jeur,
Jogeshwari, Kalyan Jn, Kamptee, Kandivali,
Kanjur Marg, Karad, Katol, Kedgaon, Kinwat,
Kopargaon, Kurduwadi Jn, Kurla Jn, Lasalgaon,
Latur, Lokmanya Tilak Terminus, Lonand Jn,
Lonavla, Lower Parel, Malad, Malkapur, Manmad
Jn, Manwath Road, Marine Lines, Matunga, Miraj
Jn, Mudkhed Jn, Mumbai Central, Mumbra,
Murtizapur Jn, Nagarsol, Nagpur Jn, Nandgaon,
Nandura, Nandurbar, Narkher Jn, Nashik Road,
Netaji Subhash Chandra Bose Itwari Junction,
Pachora Jn, Palghar, Pandharpur, Panvel Jn,
Parbhani Jn, Parel, Parli Vaijnath, Partur, Phaltan,
Prabhadevi, Pulgaon Jn, Pune Jn, Purna Jn, Raver,
Rotegaon, Sainagar Shirdi, Sandhurst Road,
Sangli, Satara, Savda, Selu, Sewagram, Shahad,
Shegaon, Shivaji Nagar Pune, Shri Chhatrapati
Shahu Maharaj Terminus Kolhapur, Solapur,
Talegaon, Thakurli, Thane, Titvala, Tumsar Road,
Umri, Uruli, Vadala Road, Vidyavihar, Vikhroli,
Wadsa, Wardha, Washim, Wathar
Page 6 of 10Completed stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Maharashtra have been taken up at a good pace. Till now, works of 19
stations have been completed. The name of stations completed in
Maharashtra are as following:
State No. of Name of stations
stations
Maharashtra 19 Amgaon, Baramati, Byculla, Chanda Fort,
Chinchpokli, Devlali, Dhule, Himayatnagar,
Kedgaon, Lasalgaon, Lonand Jn, Matunga,
Murtizapur Jn, Nandura, Netaji Subhash Chandra
Bose Itwari Junction, Parel, Savda, Shahad,
Vadala Road
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
● Diva station: The works of improvement of station building,
circulating area and parking on East side, new entry gate, platform
raising and flooring of platform no. 5/6 and 7/8, platform shelter at
platform no. 7/8, new toilet block, sewage treatment plant on West
side, improvement of Foot Over Bridge at Kalyan end and Mumbai end
have been completed. The work of new 6 m Foot Over Bridge has
been taken up.
● Mumbra station: The works for improvement of platform surface,
seating arrangement, new toilet block, improvement of booking office,
circulating area, sewage treatment plant and flooring of Foot Over
Bridge have been completed. The work of escalator has been taken
up.
● Palghar station: The works of new platform shelter at platform no. 2/3,
platform surfacing, new coping blocks and tactile tile work at
Page 7 of 10platform no. 4 have been completed. The works of utility shifting and
12 m Foot Over Bridge have been taken up.
● Titwala station: The works for station building, entrance gate,
platform surfacing, improvement of ticket booking office, toilet block,
sewage treatment plant and improvement of two wheeler parking and
approach road on East and West side have been completed. The work
of new 6 m Foot Over Bridge has been taken up.
● Vikhroli station: The works for improvement of station building on
West side, platform surfacing, platform shelter, new toilet block at
Mumbai end, improvement of toilet block at Kalyan end and Foot Over
Bridge have been completed. The works of new booking office,
circulating area on East and West side and parking of East side have
been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations including provision of platform upgradation on Indian Railways is a
continuous and ongoing process and works in this regard are undertaken
as per requirement, subject to inter-se priority and availability of funds.
Development / redevelopment / upgradation / modernisation of a station is
carried out based on category of station/condition/traffic handled etc.
Ministry of Railways has planned to provide holding areas for crowd
management at 76 stations. The passenger holding area for crowd
management planning envisages a comfortable, well-organized space with
basic amenities like seating, drinking water, toilets, ticketing facilities,
information displays, security checks, etc. These amenities are planned to
be organised to manage large passenger footfall efficiently during peak
hours.
The passenger holding area established at New Delhi Railway Station has
been commissioned and it has significantly helped to ease congestion and
Page 8 of 10enhance passenger convenience, particularly during peak travel periods.
The holding area is equipped with a wide range of commuter-friendly
facilities, including an increased number of ticket counters, Automatic
Ticket Vending Machine (ATVMs), Public Announcement System (PAS),
electronic train information display boards, CCTV surveillance, luggage
scanners, Door Frame Metal Detector (DFMDs), uninterrupted power supply,
improved night-time lighting, High Volume Low Speed (HVLS) fans, fire-
fighting system, lightning protection system, RO drinking water, and
separate toilets for men, women and Divyangjans, along with seating
arrangements.
The provision of holding areas at other stations is at various stages of
planning/execution. Planning is an iterative process requiring optimization
and the time frame and other details for such optimization cannot be
indicated at this stage.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport clearance
etc. The progress also gets affected due to brownfield related challenges
such as shifting of utilities (involving water/sewage lines, optical fibre
cables, gas pipe lines, power/signal cables, etc.), infringements, operation
of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines,
etc. and these factors affect the completion time.
Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation and expenditure under Plan Head-53
are maintained Zonal Railway-wise and not work-wise or station-wise or
state-wise. Maharashtra is covered under the jurisdiction of four railway
Page 9 of 10zones, namely, Central Railway, South Central Railway, South East Central
Railway and Western Railway. For these zones, an allocation of ₹ 3,834
crore (Revised Estimate) has been made for the financial year 2025-26, out
of which an expenditure of ₹ 3,886 crore (up to February, 2026) has been
incurred so far.
Strengthening, upgradation, modernisation and improvement of Signalling
infrastructure is a continuous and ongoing process over Indian Railways.
Indian Railway is continuously modernizing current infrastructure of its
signalling system as under:
1. Electrical/Electronic Interlocking Systems with centralized
operation points and signals in place of old mechanical signalling
have been provided at 6665 stations as on 28.02.2026, out of which
Electronic Interlocking have been provided at 3870 stations,
including Mumbai Suburban section.
2. Automatic Block Signalling (ABS) that enhances line capacity
within existing track infrastructure has been provided at 6897
Route km upto 28.02.2026. Automatic signalling works in Diva-Vasai
& Panel-Pen sections in Mumbai Suburban are in progress.
*****