Executive Summary:
The Government of India launched the Jal Jeevan Mission (JJM) in August 2019, aiming to provide Functional Household Tap Connections (FHTC) to all rural households by 2024, now extended to 2028. As of July 21, 2025, 80.94% of rural households have tap water. Phase II of Swachh Bharat Mission Grameen (SBMG) focuses on sustaining Open Defecation Free (ODF) status and solid and liquid waste management until 2025-26.
Key Points / Main Content:
Jal Jeevan Mission (JJM):
* Launched in August 2019 to provide FHTC to every rural household.
* Original target was 2024, now extended to 2028 with enhanced total outlay.
* As of 21.07.2025, 15.67 Crore (80.94%) out of 19.36 Crore rural households have tap water connections.
* 12.44 Crore additional rural households provided with tap water connections under JJM.
* Works for the remaining 3.69 Crore households are at various stages of completion.
* Challenges include: water scarcity, contaminants, terrain, delayed state share, lack of technical capacity, rising raw material prices, and statutory clearances.
* Government actions to address challenges: Special Assistance to States, nodal officer coordination, SPMUs and DPMUs setup, Nal Jal Mitra Programme, source recharging, and water conservation campaigns.
Swachh Bharat Mission Grameen (SBMG):
* Phase II (2020-21 to 2025-26) focuses on ODF sustainability and solid/liquid waste management (ODF Plus Model).
* 4,70,834 villages declared ODF Plus Model as of 21.07.2025.
Funding:
* Details of funds allocated and utilized for JJM and SBMG provided for the years 2022-23, 2023-24, and 2024-25.
Impact Analysis:
States/Union Territories:
* Impact: Responsible for reporting progress, planning, managing, operating, and maintaining water supply schemes. Face challenges like water scarcity, contamination, and funding delays.
* Action Required: Implement JJM and SBMG, address challenges, and report progress.
Rural Households:
* Impact: Aims to provide access to tap water and improved sanitation.
* Action Required: Participate in water conservation efforts and utilize provided facilities.
Implementing Agencies, Gram Panchayats, Local Communities:
* Impact: Involved in planning, managing, operating, and maintaining water supply schemes. May lack technical capacity.
* Action Required: Develop technical skills, manage schemes, and ensure long-term sustainability.
Central Government:
* Impact: Responsible for funding, monitoring, and providing support to states/UTs to achieve JJM and SBMG goals.
* Action Required: Provide financial assistance, coordinate with ministries/departments, and monitor progress.
Key Entities Referenced
Jal Jeevan Mission: A centrally sponsored scheme by the Government of India launched in August 2019, aiming at providing Functional Household Tap Connection (FHTC) to every rural household. Also referred to as JJM and Har Ghar Jal.
Swachh Bharat Mission Grameen: A nationwide campaign in India for cleanliness and sanitation. Phase II focuses on Open Defecation Free (ODF) sustainability and solid and liquid waste management in villages; also referred to as SBMG.
Ministry of Jal Shakti: A ministry of the Government of India responsible for water resources and sanitation.
Shri Rajesh Verma: Member of Parliament who raised a question about the Jal Jeevan Mission in Lok Sabha.
Rural India: The rural areas of India which are the target of the tap water connections initiative.
MGNREGS: Mahatma Gandhi National Rural Employment Guarantee Scheme, used in convergence with other schemes to support source recharging.
Jal Shakti Abhiyan: Catch the Rain: A campaign launched in 2019 to encourage water conservation at the grassroots level with people's participation; also referred to as JSA: CTR.
Nal Jal Mitra Programme: A program implemented for ensuring the availability of skilled local persons at the village level to bridge the gap in the availability of technical skill sets and of HR for program management.
GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF DRINKING WATER AND SANITATION
LOK SABHA
UNSTARRED QUESTION NO. 731
ANSWERED ON 24.07.2025
TAP WATER CONNECTIONS UNDER JAL JEEVAN MISSION
731. SHRI RAJESH VERMA:
SHRI RAVINDRA DATTARAM WAIKAR:
SMT. SHAMBHAVI:
SHRI NARESH GANPAT MHASKE:
DR. SHRIKANT EKNATH SHINDE:
Will the Minister of JAL SHAKTI be pleased to state:
(a) whether the Government is on track to complete tap water connections in rural India by 2025
and if so, the details of the progress made so far under the Jal Jeevan Mission (JJM);
(b) the current percentage of rural households with access to tap water and the number of
households yet to be covered;
(c) the major challenges faced in achieving full tap water coverage and the steps taken/being
taken by the Government to address these challenges;
(d) the status of sanitation-related goals under the Swachh Bharat Mission and the initiatives
undertaken to sustain Open Defecation Free (ODF) villages; and
(e) the details of the funds allocated and utilised for tap water connections and sanitation
programmes during the last three years?
ANSWER
MINISTER OF STATE FOR JAL SHAKTI
(SHRI V. SOMANNA)
(a) & (b) Government of India had launched Jal Jeevan Mission (JJM), a centrally sponsored
scheme in August 2019, aiming at providing Functional Household Tap Connection (FHTC) to
every rural household by 2024.
At the start the Mission, only 3.23 Crore (16.7%) rural households were reported to have tap water
connections. So far, as reported by States/ UTs as on 21.07.2025, under Jal Jeevan Mission (JJM) –
Har Ghar Jal around 12.44 Crore additional rural households have been provided with tap water
connections. Thus, as on 21.07.2025, out of 19.36 Crore rural households in the country, more than
15.67 Crore (80.94%) households are reported to have tap water supply in their homes and works
for the remaining 3.69 Crore households are at various stages of completion as per plan of the
respective State/ UT.
To achieve the goal of the Mission with focus on quality of infrastructure and Operation &
Maintenance of rural piped water supply schemes for long term sustainability and citizen centric
Page 1 of 2water service delivery, Hon'ble Finance Minister during her budget speech 2025-26 has announced
extension of Jal Jeevan Mission until 2028 with enhanced total outlay.
(c) States have informed that lack of dependable drinking water sources in water-stressed, drought
prone and desert areas, presence of geo-genic contaminants in ground water, uneven geographical
terrain, scattered rural habitations, delay in release of the matching State share in some States, lack
of technical capacity with implementing agencies, Gram Panchayats and local communities to plan,
manage, operate & maintain the water supply schemes, rising price of raw materials, delay in
obtaining statutory/ other clearances, etc. are few of problems being faced in the implementation of
the Mission.
To address the challenges holistically and overcome these, Government of India has taken a number
of steps, inter alia including implementation of Special Assistance to States for Capital Expenditure
through M/o Finance for financial assistance as 50-year interest free loan for capital investment
projects; nomination of a nodal officer in the Department for coordinating with Central nodal
Ministries/ Departments/ agencies to facilitate the States in obtaining Statutory/ other clearances;
setting up of State Programme Management Units (SPMUs) and District Programme Management
Units (DPMUs) and implementation of “Nal Jal Mitra Programme” for ensuring availability of
skilled local persons at village level to bridge the gap in availability of technical skill sets and of HR
for programme management;
Under the Mission, States have been advised for source recharging, viz. dedicated bore well
recharge structures, rainwater recharge, rejuvenation of existing water bodies, reuse of greywater,
etc., in convergence with other schemes such as MGNREGS, Integrated Watershed Management
Programme (IWMP), 15th Finance Commission tied grants to RLBs/ PRIs, State schemes, CSR
funds, etc.
Further, Jal Shakti Abhiyan: Catch the Rain (JSA: CTR) campaign aiming to encourage water
conservation at grass-root levels with people's participation was launched in 2019 in 256 water
stressed districts of the country. Moreover, recognizing the importance of sustainable water
management especially for drinking water availability, JSA-CTR was implemented with the theme
“Source Sustainability for Drinking Water” in 2023. Similarly, in 2024, JSA was implemented
with the theme "Nari Shakti se Jal Shakti" and in 2025, JSA is being implemented with the theme
“People's Action for Water Conservation - Towards Intensified Community Connect” emphasizing
the pivotal role played by community especially women in the field of water conservation.
(d) Phase II of Swachh Bharat Mission (Grameen) [SBM(G)] is being implemented during the
period from 2020-21 to 2025-26, with the focus on Open Defecation Free (ODF) sustainability and
to cover all the villages with solid and liquid waste management i.e. converting the villages from
ODF to ODF Plus (Model). As reported by the States, 4,70,834 villages have been declared ODF
Plus (Model) as on 21.07.2025.
(e) The details of the funds allocated and utilized under Jal Jeevan Mission and Swachh Bharat
Mission (Grameen) [SBM(G)] during the last three years are as under:
(Rs. in crore)
Jal Jeevan Mission Swachh Bharat Mission (Grameen)
Year Allocated Utilized Allocated Utilized
2022-23 55,000.00 54,839.79 5000.00 4925.14
2023-24 70,000.00 69,992.37 7000.00 6802.58
2024-25 22,694.00 22,638.44 7192.00 3622.00
*****
Page 2 of 2