See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF CIVIL AVIATION
RAJYA SABHA
STARRED QUESTION NO. : 246
TO BE ANSWERED ON THE 16th March 2026
TARGET SET UNDER NATIONAL MONETISATION PIPELINE 2.0
246. SHRI P. WILSON
Will the Minister of CIVIL AVIATION be pleased to state:-
(a) the targets set under National Monetisation Pipeline (NMP) 2.0, including details of
airports identified for monetisation/leasing and the rationale therefor;
(b) the airport-wise details of development works undertaken in the State of Tamil Nadu,
including Chennai airport aerobridge capacity, budget allocated, expenditure incurred,
timelines and reasons for delay, if any; and
(c) the details of inaugurated airports under the UDAN scheme that have suspended
operations due to low demand or financial unviability, State-wise and the details of budget
allocated, cumulative losses incurred and justification for their establishment?
ANSWER
Minister of CIVIL AVIATION (Shri Kinjarapu Rammohan Naidu)
(a) to (c): A statement is laid on the table of the House.
******STATEMENT REFERRED TO IN REPLY TO PARTS (A) to (C) OF RAJYA SABHA
STARRED QUESTION NO. 246* FOR REPLY ON 16.03.2026 REGARDING "TARGET
SET UNDER NATIONAL MONETISATION PIPELINE 2.0" ASKED BY SHRI P.
WILSON
(a): Under NMP 2.0 (FY26-FY30), monetisation target of Rs. 27,500 crore has been set for
Civil Aviation sector. This includes monetization of 26 airports of Airports Authority of
India (AAI) namely, Amritsar, Bhubaneswar, Raipur, Trichy, Varanasi, Kushinagar, Kangra,
Gaya, Aurangabad, Hubli, Tirupati, Agartala, Bhopal, Calicut, Coimbatore, Dehradun,
Imphal, Indore, Madurai, Patna, Rajahmundry, Ranchi, Surat, Udaipur, Vadodara and
Vijayawada, expected to contribute Rs. 14,950 crore to the monetisation target. Additionally,
Rs. 12,550 crore is targeted from divestment of AAI's holdings in one of its subsidiaries and
four Joint Venture (JV) airports. The monetisation proceeds would accrue to AAI for
reinvesting into creation of more assets and new airport projects.
(b): The airport-wise details of development works undertaken in the State of Tamil Nadu is
enclosed as Annexure.
Further, under RCS-UDAN, four airports at Salem, Vellore, Neyveli and Thanjavur have
been identified for development and operation of flights. An allocation of Rs. 134.39 crore
has been made, out of which Rs. 115.69 crore has already been incurred. Salem Airport was
developed and operationalised on 25.03.2018. Physical development works at Vellore and
Neyveli airports have been completed. Meanwhile, works relating to establishment of a civil
enclave at Thanjavur airport is being undertaken by AAI.
The timeline for completion of the airport projects depends upon several factors such as land
acquisition, availability of mandatory clearances including environmental clearances,
financial closure etc.
(c): No such airport has suspended operations due to low demand or financial unviability.
However, operations at some airports have been suspended due to the shortage/non-
availability of aircraft with airlines, runway works, weather related challenges etc.
The policy rationale for establishing and reviving these airports is based on the objectives of
the UDAN scheme, which aim to enhance regional air connectivity and make air travel
affordable for common citizens, particularly in Tier-II and Tier-III cities and remote regions
by utilising existing infrastructure such as underutilised airstrips and defence or State-owned
airfields by upgrading them for civil aviation operations.Annexure
Statement referred in part (b) of reply to Rajya Sabha Starred Question No. 246 for answer on
16.03.2026
Details of Development works at Airports in Tamil Nadu
Sl.No. Airport Expenditur Details of work carried out
e
1 Trichy 1,162.9 Cr Construction of a new terminal building and surface
car parking and associated works has been
completed.
2 Tuticorin 318.16Cr Construction of a new domestic terminal building
with three aerobridges, ATC Tower-cum-Technical
Block, Category-7 fire station and associated works
Extension of runway including blast pad, RESA,
taxiway, apron, GSE area, isolation bay, and other
associated works
3 Coimbatore 63.31Cr Construction of an additional apron and Runway
resurfacing is completed
4. Chennai 1,640.87Cr Modernization of Chennai Airport Phase-II, Part-1
(Terminal 2) is completed
Development of city-side traffic flow management
with plaza, pick-up lanes, and ancillary facilities at
Chennai Airport.
Reconstruction and strengthening of Taxi Tracks
with link taxi, part runway resurfacing has been
completed
Construction of MLCP at Chennai Airport.
5 Madurai 98.84Cr Construction of the new ATC cum Technical block is
completed.
*****