Executive Summary:
This document details the achievements of the Namami Gange Mission as of July 31, 2025, in response to Lok Sabha Unstarred Question No. 2032. It outlines progress in sewage treatment infrastructure, industrial pollution abatement, river water quality monitoring, biodiversity conservation, and public awareness campaigns. The report also addresses reasons for project delays and total expenditures incurred.
Key Points / Main Content:
Sewerage Infrastructure:
* 212 sewerage infrastructure projects sanctioned with a total cost of ₹34,526 crores, targeting a treatment capacity of 6,540 MLD.
* 167 STP projects completed and operational, creating a treatment capacity of 3,781 MLD.
Industrial Pollution Abatement:
* Three CETPs sanctioned (Jajmau, Banther, and Mathura).
* Mathura and Jajmau CETPs have been completed.
* Inspections of GPIs are ongoing, with 2682 compliant, 517 non-compliant (26 issued closure notices, 491 issued show cause notices), 523 temporarily closed, and 278 permanently closed.
* Reduction in BOD load from 26 TPD in 2017 to 13.73 TPD in 2023.
* Reduction in effluent discharge from 349 MLD in 2017 to 249.31 MLD in 2023.
River Quality Monitoring:
* The PRAYAG online dashboard is operational for continuous monitoring of river water quality and STP performance.
* Minimum e-flow norms are being successfully implemented and monitored by the CWC.
* Biological Water Quality predominantly ranged from Good to Moderate at 50 locations along River Ganga and its tributaries, and 26 locations along River Yamuna and its tributaries.
Biodiversity Conservation:
* Seven Biodiversity Parks sanctioned in Uttar Pradesh, and 5 priority wetlands sanctioned in Uttar Pradesh, Bihar and Jharkhand.
* Afforestation of 33,024 hectares with an expenditure of approximately ₹414 crores.
* 160 lakhs IMC fingerlings have been released into the Ganga since 2017.
* Species restoration programs have shown improvements in biodiversity.
* Increase in the dolphin population from an estimated 2,500-3,000 in 2009 to approximately 6,327 individuals as per the 2021-2023 survey.
Public Awareness and Participation:
* Ganga Knowledge Portal developed as a centralized repository for water resource management resources.
* 139 District Ganga Committees constituted, conducting regular meetings (over 4,377 meetings held).
* Ganga Task Force raised in Uttar Pradesh for tasks like plantation, public awareness, and patrolling.
* Comprehensive public awareness campaigns are being conducted.
River Quality Improvement:
* As per CPCB reports, river stretches in Uttarakhand and Jharkhand do not fall under polluted stretches. Stretches in Uttar Pradesh, Bihar and West Bengal fall under Priority Class V BOD, Priority Class IV BOD, and Priority Class IV BOD, respectively.
* Dissolved Oxygen levels are within acceptable limits for primary bathing water quality.
Project Delays:
* Reasons for delays include identifying suitable land for STPs and obtaining statutory clearances.
* NMCG actively monitors project status through review meetings.
Expenditure:
* ₹19,679.84 crore disbursed under the Namami Gange Programme from FY 2014-15 up to June 30, 2025.
Impact Analysis:
Government of India (Ministry of Jal Shakti):
* Impact: Accountable for the progress and outcomes of the Namami Gange Mission.
* Action Required: Continue monitoring project progress, address reasons for delays, and ensure effective implementation of the mission.
National Mission for Clean Ganga (NMCG):
* Impact: Responsible for implementing and overseeing the Namami Gange Mission.
* Action Required: Continue monitoring project progress, address reasons for delays, and ensure effective implementation of the mission.
State Governments (Uttar Pradesh, Bihar, Jharkhand, West Bengal, Uttarakhand):
* Impact: Involved in the implementation of projects within their respective states.
* Action Required: Facilitate land acquisition, expedite statutory clearances, and support the implementation of projects.
Polluting Industries (GPIs):
* Impact: Subject to inspections and regulations to reduce industrial pollution.
* Action Required: Ensure compliance with environmental regulations and take corrective actions for non-compliance.
Local Communities:
* Impact: Benefit from improved water quality, biodiversity, and public awareness.
* Action Required: Participate in public awareness campaigns and support efforts to clean and conserve the Ganga River.
Key Entities Referenced
Namami Gange Mission: A program by the Government of India to clean and rejuvenate the Ganga River.
River Ganga: A major river in India, the focus of the Namami Gange Mission.
National Mission for Clean Ganga NMCG: The implementing agency for the Namami Gange Mission.
Sewage Treatment Plants STPs: Facilities constructed or upgraded under the Namami Gange Mission to treat sewage and reduce pollution in the Ganga River.
Uttar Pradesh: A state in India where several projects related to Ganga rejuvenation are being implemented.
Bihar: A state in India where projects related to Ganga rejuvenation are being implemented.
Jharkhand: A state in India where projects related to Ganga rejuvenation are being implemented.
Central Pollution Control Board CPCB: An organization that monitors and assesses the pollution levels of rivers in India, including the Ganga.
GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 2032
ANSWERED ON 31.07.2025
TARGETS ACHIEVED UNDER NAMAMI GANGE MISSION
2032. SHRI E TUKARAM
Will the Minister of JAL SHAKTI be pleased to state:
(a) whether the Government has achieved key targets under the Namami Gange Mission so far and if so,
the details thereof;
(b) the number of Sewage Treatment Plants (STPs) constructed or upgraded and the total sewage
treatment capacity created under the mission till date;
(c) the major reasons for delays, if any, in completion of approved projects; and
(d) the total expenditure incurred under the said mission till date?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) Yes. The achievements of the National Mission for Clean Ganga (NMCG) for improving the water
quality along the river Ganga and its tributaries are as under:
1. A total of 212 number of sewerage infrastructure projects costing ₹ 34,526 crores have been
taken up for remediation of polluted river areas with treatment capacity of 6,540 Million
Liters per Day (MLD). 136 STP projects with a capacity of 3,780 MLD have been completed
and made operational;
2. For industrial pollution abatement, 3 nos. of Common Effluent Treatment Plants (CETPs)
have been sanctioned, i.e., Jajmau CETP (20 MLD), Banther CETP (4.5 MLD), and Mathura
CETP (6.25 MLD). Two projects, Mathura CETP (6.25 MLD) and Jajmau CETP (20 MLD),
have been completed;
3. Annual inspection of Grossly Polluting Industries (GPIs): Inspection of GPIs started in
2017. In 2024, 4246 Grossly Polluting Industries (GPIs) have been inventoried in the 7th
round of inspection. All the GPIs have been inspected. So far, out of 4,000 GPIs on which
action has been completed, 2682 GPIs are compliant, 517 are non-compliant, 523 GPIs are
temporarily closed, and 278 GPIs are permanently closed. Among the non-compliant (517
GPIs), 26 GPIs have been issued notice for closure and 491 GPIs have been issued show
1cause notice. The Eighth round of the inspection has started. These efforts have resulted in
reduction in BOD load from 26 tons per day (TPD) in 2017 to 13.73 TPD in 2023, and about
28.6 % reduction in effluent discharge from 349 MLD in 2017 to 249.31 MLD in 2023.
4. At NMCG, an on-line dashboard “PRAYAG” has been operationalized for continuous
monitoring of river water quality; the performance of Sewage Treatment Plants (STPs) etc. on
the Ganga and Yamuna River;
5. NMCG successfully implemented the minimum e-flow norms notified in October 2018,
ensuring continuous environmental flow in the river Ganga. Regular compliance is being
effectively monitored by the Central Water Commission (CWC).
6. Biodiversity Conservation: Seven Biodiversity Parks in seven districts (Mirzapur,
Bulandshahar, Hapur, Budaun, Ayodhya, Bijnore and Pratapgarh) of Uttar Pradesh and 5
priority wetlands in Uttar Pradesh (3), Bihar (1) and Jharkhand (1) have been sanctioned;
7. NMCG, through the State Forest Department, has implemented a forestry intervention project
along the main stem of river Ganga. 33,024 hectares area have been afforested with an
expenditure of about ₹ 414 crores;
8. A total of 160 lakhs of Indian Major Carp (IMC) fingerlings have been ranched in the Ganga
since 2017 to conserve fish biodiversity and prey base for river Dolphins, and ensure the
livelihood of fishers in the Ganga basin under the special project implemented by Central
Inland Fisheries Research Institute (CIFRI);
9. Science-based species restoration programme, rescue, and rehabilitation programme for
aquatic species like Dolphins, Otters, Hilsa, Turtles, and Ghariyal in collaboration with Wild
Life Institute of India (WII), Dehradun and State Forest Department, have shown marked
improvements in biodiversity with increased sightings of Dolphins, Otters, Hilsa, Turtles, and
other riverine species;
10. “Ganga Knowledge Portal” is a pioneering initiative developed in-house by the National
Mission for Clean Ganga, serving as a centralized repository for comprehensive resources on
water resource management. This platform is engineered to facilitate access for students,
research scholars, stakeholders, and the general public to a vast array of materials (1072
documents), including journals, publications, books, technical articles, research reports; data
sets (District River Maps, STP performance and river atlas) and coffee table books. By
concentrating on the intricacies of water resource challenges, Ganga Knowledge portal aims
to enhance awareness and foster informed decision-making in this critical sector;
211. A total no. of 139 District Ganga Committees (DGC) have been constituted which conducts
4M (Monthly, Mandated, Minuted, and Monitored) meetings regularly. As of July 2025,
more than 4,377 meetings have been conducted;
12. Ganga Task Force (GTF) was raised in the state of Uttar Pradesh to assist NMCG in
carrying out its mandated tasks, such as (a) Plantation of trees to check soil erosion; (b)
Management of Public Awareness / Participation campaigns; (c) Patrolling of Sensitive Rivers
Areas for Biodiversity protection; (d) Patrolling of Ghats, etc.;
13. Comprehensive public awareness campaigns have been undertaken to instill a sense of
responsibility and engagement among the public in efforts to clean and conserve the Ganga
River. These include - Ganga Utsav, Nadi Utsav, regular cleanathons and plantation drives,
Ghat Par Yoga, Ganga Aartis, etc. The efforts are also supported by dedicated cadres of
Ganga saviours, such as Ganga Praharis, Ganga VicharManch, etc.
14. Improvement in river Quality: Measurable outcomes of the implementation of the NGM is
provided through the reports of the Central Pollution Control Board (CPCB) on pollution
assessment of rivers of India. As per the report, the Priority River Stretches (PRSs) on the
river Ganga, based on the assessment carried out in 2022 (using 2019 and 2021 data), are as
under:
a. Uttarakhand does not fall under polluted stretches (BOD < 3 mg/l);
b. In Uttar Pradesh, stretches from Farrukhabad to Allahabad and Mirzapur to Ghazipur
fall under Priority Class V (BOD 3–6 mg/l);
c. In Bihar, stretches along Buxar, Patna, Fatwah, and Bhagalpur fall under Priority Class IV
(BOD 6–10 mg/l);
d. Jharkhand does not fall under polluted stretches (BOD < 3 mg/l);
e. In West Bengal, the stretch from Behrampur to Haldia falls under Priority Class IV (BOD
6–10 mg/l).
Further, the value of Dissolved Oxygen (DO), which is an indicator of river health, has
been found to be within the acceptable limits of the notified primary bathing water quality
criteria and is satisfactory to support the ecosystem of the river along almost the entire stretch of
the river Ganga.
As per the biomonitoring conducted during 2024–25 at 50 locations along River Ganga
and its tributaries, and 26 locations along River Yamuna and its tributaries, the Biological Water
3Quality (BWQ) predominantly ranged from ‘Good’ to ‘Moderate’. The presence of diverse
benthic macro-invertebrate species indicates the ecological potential of the rivers to sustain
aquatic life.
15. Improvement in ecological status of river: The population of Dolphins in the river Ganga
has shown a marked increase over the past decade. From an estimated baseline of 2,500–3,000
individuals in 2009, the population rose to approximately 3,500 in 2015 and further to around
6,327 individuals as per the nationwide survey conducted during 2021–2023. This represents
more than a twofold increase since 2009. In the Ganga basin, the 2021–2023 assessment
across 17 tributaries confirmed dolphin presence in multiple rivers where they were
previously unrecorded, such as the Rupnarayan, Girwa, Kauriyala, Babai, Rapti, Bagmati,
Mahananda, Ken, Betwa, and Sind.
(b) As of 30th June 2025, a total of 167 Sewage Treatment Plants (STPs) have been made operational,
resulting in the creation of a total sewage treatment capacity of 3,781 Million Litres per Day (MLD).
(c) The major reasons for delays in the completion of projects are following:
i. Identification of suitable land for the establishment of new Sewage Treatment Plants (STPs)
ii. The issuance of statutory clearances such as right of way for sewage-related networks,
obtaining permissions for road cutting, No Objection Certificates (NoCs) from competent
authorities like forest and revenue departments;
In order to address and overcome these challenges, the National Mission for Clean Ganga
(NMCG) has been actively involved in closely monitoring the status of the projects. NMCG regularly
conducts comprehensive review meetings under the chairmanship of the competent authority and through
the Central Monitoring Committee (CMC) to evaluate progress, identify potential roadblocks, and ensure
timely resolutions.
(d) Under the Namami Gange Programme, from Financial Year 2014–15 up to 30th June 2025, the
National Mission for Clean Ganga (NMCG) has disbursed a total of ₹19,679.84 crore to various agencies
for the implementation of approved projects and interventions.
*****
4