UNSTARRED QUESTION NO. 4324
TO BE ANSWERED ON 18.03.2026
UNDERPASSES AT PALAM AND SHAHBAD RAILWAY CROSSINGS
†4324. SHRI RAMVIR SINGH BIDHURI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the work for construction of underpasses has begun at Palam
Railway Crossing and Shahbad Railway Crossing under the Delhi-Rewari
section;
(b) if so, the time by which the said construction work is likely to be
completed; and
(c) the average time taken by the Government to construct an underpass
there?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c) : Sanctioning of works of Road over Bridge (ROB)/Road under
Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and dynamic
process of Indian Railway. Such works are prioritised and taken up on the
basis of its impact on safety in train operations, mobility of trains & impact
for road users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto Jan’26) 14,024 Nos. ( including 14 Nos. of ROBs/ RUBs
in the state of Delhi)
§As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at a cost of
₹ 1,14,196 Cr on Indian Railways including 19 Nos. Road Over Bridge
(ROB)/Road Under Bridge (RUB) at a cost of ₹ 719 Cr in State of Delhi which
are at various stages of planning and execution.
The work for construction of Road Under Bridge (RUB) in lieu of Level
Crossing (LC) No. 15 (Palam railway crossing) at km 18/0-1 on Delhi-Rewari
section has been sanctioned. General Arrangement Drawing (GAD) has
been approved. The contract for this work has been awarded. The work for
shifting of utilities has been taken up.
The work for construction of Road Under Bridge (RUB) in lieu of LC
No. 17 (Shahbad railway crossing) at Km 20/9-21/0 on Delhi-Rewari section
has been sanctioned. General Arrangement Drawing (GAD) has been
approved. The contract for this work has been awarded. The work for the
construction of RUB has been taken up.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
authorities, law and order situation in the area of project / work sites,
duration of working season in a year for the particular project / area due to
climatic conditions etc. All these factors affect the completion time of the
projects / works.
*****