**Executive Summary**
This document is a response to a parliamentary question (No. 2017) regarding the upgrade of the Kolkata Metro's air-conditioning and ventilation systems, set to be answered on February 11, 2026. The upgrade, sanctioned at Rs. 1,201 Crores, aims to modernize the metro's environmental control and ventilation infrastructure to meet contemporary standards. Implementation will be planned meticulously to minimize service disruptions. The document further details the current status of ongoing metro corridor constructions around Kolkata, highlighting issues causing delays.
**Key Points / Main Content**
* **Upgradation Project:**
* Rs. 1,201 Crores have been sanctioned for the project.
* Includes state-of-the-art Tunnel Ventilation System, Environment Control System, and related Power Supply Systems.
* Aims to provide better passenger comfort and energy efficiency.
* Will replace water-cooled chillers with air-cooled chillers, saving 18 Cr liters of water annually.
* **Kolkata Metro History:**
* The first underground section opened in 1984.
* Original ECS and ventilation were designed for lower temperatures, non-AC trains, and lower ridership.
* **Ongoing Construction Projects:**
* 52 km of metro corridors are under construction.
* 20 km are held up due to land acquisition and utility shifting issues.
* *Joka - Esplanade (14 km)*: Majerhat-Esplanade (6.26 km) affected due to land acquisition.
* *New Garia - Dum Dum Airport (32 km)*: Belaghata-Dum Dum Airport (22.2 km) affected due to land acquisition.
* *Noapara - Barasat (18 km)*: Jai Hind Airport-Michael Nagar is in progress. New Barrackpore-Barasat (7.5 km) is held up due to land acquisition and encroachment issues.
* *Baranagar - Dakshineshwar (14.5 km)*: Baranagar-Barrackpore (12.5 km) is held up due to pending utility shifting.
* **Specific Issues Causing Delays:**
* Khidderpur Metro Station: Land required for utility shifting and road traffic diversion, pending since 2020, was only approved in July 2025.
* Dr. B.C. Roy Market: Temporary shifting of unauthorized shops required for Esplanade Metro Station, NOC pending since February 2022.
* Chingrighata Crossing: Temporary traffic diversion requires NOC pending for about 10 months as of the document's writing.
* New Barrackpore to Barasat: Land acquisition and removal of heavy encroachments are unresolved.
* Baranagar to Barrackpore: NOC for pipeline shifting is still awaited from the Government of West Bengal.
**Impact Analysis**
**Stakeholder: Commuters**
* **Impact**: Upgraded systems will improve comfort, safety, and environmental standards. There is a potential for service disruptions during the upgrade implementation.
* **Action Required**: Be aware of potential service disruptions and follow advisories.
**Stakeholder: Government of West Bengal**
* **Impact**: Necessary land acquisition, utility shifting, and approvals (NOC) are pending, causing delays to the metro projects.
* **Action Required**: Expedite pending land acquisition, utility shifting, and issue necessary approvals (NOC) for the various metro projects.
**Stakeholder: Kolkata Metro Railway**
* **Impact**: Responsible for implementing the upgrade and managing potential service disruptions. The upgrade requires state government support.
* **Action Required**: Meticulously plan the upgrade to minimize service disruptions. Regular follow up with State PWD and other relevant departments regarding utility shifting and land acquisition.
Key Entities Referenced
Kolkata Metro: India's oldest metro system undergoing a major upgradation of its air-conditioning and ventilation systems on the Blue Line.
Ministry of Railways: The central ministry responsible for addressing the upgradation of the Kolkata Metro.
West Bengal: The state where land acquisition and utility shifting issues are impacting the progress of the Kolkata Metro expansion.
Lok Sabha: Parliamentary house where the unstarred question regarding the Kolkata Metro upgradation was raised.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2017
TO BE ANSWERED ON 11.02.2026
UPGRADATION OF KOLKATA METRO STATION
2017. SHRI JAGANNATH SARKAR:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware that the air-conditioning and ventilation
systems of the Kolkata Metro’s Blue Line underground stations, installed
over 40 years ago, are undergoing a major upgradation and if so, the
details thereof;
(b) whether the Government plans to sanction Rs. 500 crores for the said
upgradation project and if so, the details thereof;
(c) the details of the proposed works including the replacement of water-
cooled chillers with air-cooled chillers, expected savings in groundwater
and overall project timelines; and
(d) whether the commuters are likely to face service disruptions during the
implementation period and if so, the details thereof and the steps being
taken by the Government to minimize inconvenience?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): The Kolkata Metro, India’s oldest metro system, opened its first
underground section in 1984. The original Environmental Control System
(ECS) and ventilation were designed considering lower ambient
temperatures, non-AC trains, and lower ridership. After more than four
decades of service to the nation, its environmental control and ventilation
infrastructure including air-conditioning, tunnel airflow systems, and smoke
extraction mechanisms is being significantly modernized to meet
contemporary comfort, safety, and environmental standards.
Contd.2/..
§-2-
The up-gradation works have been sanctioned at a total cost of Rs.1,201
Crores, which includes state-of-art system of Tunnel Ventilation System,
Environment Control (commonly known as Air-conditioning System) System
along with its related Power Supply Systems and other Electrical works.
It will provide better passenger comfort by cooler, better-ventilated
platforms and tunnel environments, at the same time will be energy-efficient.
Modern tunnel ventilation will enhance safety by smoke control and safe
passenger evacuation.
For cooling fifteen stations of blue line, Kolkata Metro Railway uses 18 Cr
liters of water annually for the use of water-cooled chillers. After installation
of air-cooled chillers, this water will be saved.
Implementation of the up-gradation work is planned meticulously, to avoid
service disruptions and minimize inconvenience to the passengers.
Metro project in Kolkata started in 1972. The details of the Metro
commissioned since then are as under:
Period Metro Commissioned
1972 to 2014 (42 years) 28 km
2014 to 2025 (11 years) 45 km
Presently, 4 metro corridors of total 52 km are under construction in and
around Kolkata out of which 20 km is held up due to land acquisition and
utility shifting issues pertaining to State Government. The status of these
corridors is as given below:
Contd.3/..-3-
(i) Joka - Esplanade (14 km):- Joka - Majerhat (7.74 km) has been
commissioned and balance work from Majerhat to Esplanade (6.26 km)
has been taken up. However, progress of the work is affected due to the
following issues:
SN Location Issues
1. Khidderpur For utility shifting and road traffic diversion, 837
Metro sqm permanent and 1,702 sqm temporary land of
Station State Government (Kolkata Armed Police) is
required. The proposal of this land was sent to
State Government on 24.08.2020.
Several meetings were held with officials of
Government of West Bengal (GoWB) for transfer
of above land.
After lot of persuasion, State Government finally
accorded approval in July 2025 only after almost
5 years.
2. Dr. B.C. For construction of Esplanade Metro Station,
Roy Market temporary shifting of unauthorised 528 Shops at
B.C. Roy Market on Defence land is required.
The proposal for NOC of temporary/permanent
shifting of these shops was submitted to State
Government in February 2022. Shops for
temporary shifting of these unauthorized shops
have also been constructed by Railway.
The State Government has been requested to
facilitate shifting. Regular follow up with State
PWD is also being done.
Issue is pending for more than 3.5 years.
Contd.4/..-4-
(ii) New Garia - Dum Dum Airport (32 km): New Garia - Belaghata (9.8 km)
has been commissioned and balance work from Belaghata to Dum Dum
Airport (22.2 km) has been taken up. However, progress of the work is
affected due to the following issues:
SN Location Issues
1. Chingrighata Temporary traffic diversion at Chingrighata
Crossing crossing for launching of viaduct segments
(Between is required for 3 nights each on either side
Beleghata – of the road (8 hours on every night).
Gour Kishore The proposal was submitted to Government
Ghosh stations) of West Bengal (GoWB) in December 2024.
The diversion road as desired by Kolkata
traffic police has already been constructed
in February 2025.
Since then, several meetings have been
held with various State Government and
Kolkata police officials for NOC.
The NOC is still awaited even after about 10
months.
(iii) Noapara - Barasat (18 km): Noapara - Jai Hind Airport (6.77 km) has
been commissioned and work from Jai Hind Airport to Michael Nagar
is in progress. However, work from New Barrackpore to Barasat (7.5
km) is held up due to land acquisition and encroachment issues by
State authorities.
Contd.5/..-5-
SN Location Issues
1. New Land acquisition (23,000 sq. m) and
Barrackpore to removal of heavy encroachments (1277
Barasat hutments, 764 shops) are involved in this
section.
The matter is not yet resolved by GoWB.
(iv) Baranagar - Barrackpore - Dakshineshwar (14.5 km): Baranagar -
Dakshineshwar (2 km) has been commissioned and balance work from
Baranagar to Barrackpore (12.5 km) is held up due to pending utility
shifting in the alignment by state government authorities. The details
are as below:
SN Location Issues
1. Baranagar The original alignment along the B.T road was
to agreed in 2011 as per MoU among Metro
Barrackpore Railway, RVNL and Kolkata Municipal
Corporation.
As per MoU, existing pipeline was to be
replaced by new 64 inch diameter pipeline by
the State Government.
Shifting of this pipeline was completed in
2012.
However, NOC is still awaited from
Government of West Bengal.
*****