See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5333
TO BE ANSWERED ON 25.03.2026
UPGRADATION OF MANGALURU CENTRAL RAILWAY STATION AS WORLD
CLASS RAILWAY STATION
5333. SHRI CAPTAIN BRIJESH CHOWTA:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Mangaluru Central railway station was identified for
development as a “World Class Railway Station” and if so, the details of
the proposal and estimated investment made;
(b) the steps taken since the announcement to implement the said project
including preparation of feasibility reports, redevelopment plans and
consultations;
(c) the reasons for non-implementation/delay in upgrading the station under
the World Class Station programme;
(d) whether the Government proposes for redevelopment/modernisation of
said railway station under the Amrit Bharat Station Scheme/other
programmes and if so, the details of works sanctioned, funds allocated
and timelines for their completion; and
(e) the details of the total capital expenditure incurred during the last five
years on passenger amenities and infrastructure at Mangaluru Central
and Mangaluru Junction railway stations?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach. So far, 1338
stations have been identified for redevelopment under Amrit Bharat Station
Scheme, out of which 61 stations including Mangalore Central and
Mangalore Junction are located in Karnataka.
§ Page 1 of 6At Mangalore Central station, the works of development of second entry,
construction of booking office, development of circulating area and parking
at second entry and improvement of water supply arrangements have been
completed in recent years. Further, the works for provision of platform
shelters, coach indicator and extension of foot over bridge have been taken
up.
Master planning for development of Mangalore Central railway station
under Amrit Bharat Station Scheme has been taken up. This is an iterative
process requiring optimization and the time frame for such optimization
cannot be indicated at this stage.
Amrit Bharat Station scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning,
keeping in view the necessity at each station includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
• Amenities for Divyangjans
• Better passenger information systems
Page 2 of 6• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
The stations identified for redevelopment under Amrit Bharat Station
Scheme in Karnataka are as following:
No. of
State Names of Stations
Stations
Almatti, Alnavar, Arsikere Junction, Badami,
Bagalkot, Ballary, Bangalore Cantt., Bangarpet,
Bantawala, Belagavi, Bidar, Chamaraja Nagar,
Channapatna, Channasandra, Chikkamagaluru,
Chikodi Road, Chitradurga, Davangere, Dharwad,
Dodballapur, Gadag, Gangapur Road, Gangavathi,
Ghataprabha, Gokak Road, Gubbi, Harihar,
Hassan, Hosapete, Kalaburagi Jn., Kengeri,
Koppal, Krantivira Sangolli Rayanna (Bengaluru
Karnataka 61
Station), Krishnarajapuram, Malleswaram, Malur,
Mandya, Mangalore Central, Mangalore Jn,
Munirabad, Mysuru Jn (Mysore), Raichur Jn,
Ramanagaram, Ranibennur, Raybag, Sagar
Jambagaru, Sakleshpur, Shahabad, Shivamogga
Town, Shravanabelgola, Shree Siddharoodha
Swamiji Hubballi Jn, Subramanya Road, Talguppa,
Tiptur, Tumakuru, Udupi, Vijayapura, Wadi,
Whitefield, Yadgir, Yesvantpur
Page 3 of 6Development works at railway stations under Amrit Bharat Station Scheme
in Karnataka have been taken up at a good pace. Till now, works of 09
stations (Alnavar, Badami, Bagalkot, Dharwad, Gadag, Gokak Road, Koppal,
Munirabad, Bantawala) in Karnataka have been completed under this
scheme. The activities for development at other stations have also been
taken up at good pace and progress of some of the stations located in
Karnataka is as given below:-
Mangalore Junction station: The works of widening of the station
approach road, works of circulating area including parking,
improvement of station building including porch, booking office,
provision of additional platform shelter, provision of new waiting hall
with toilet, improvement to platform surfacing at platform 1, provision
of lighting, coach guidance boards and parcel office have been
completed. The works for construction of 6 m wide foot over bridge
has been taken up.
Bangalore Cantonment station: The works of diversion road on south
side, training centre, hostel on north side and electric substation
building have been completed. The works of south side station
building, north side station building, circulating area and foot over
bridge have been taken up.
Chamaraja Nagar station: The works of improvement of station
building, entrance porch, platform shelter, platform surfacing, waiting
hall, booking counter, circulating area and parking have been
completed. The works of lift, escalator and 12 m foot over bridge have
been taken up.
Page 4 of 6 Hosapete station: The works of improvement of station building,
platform shelter, improvement of waiting hall and coach indication
board at platform no. 1 have been completed. The works of platform
surfacing, coach indication board at platform no. 2/3, lift, escalator
and 12 m foot over bridge have been taken up.
Ranibennur station: The works of improvement of station building,
entrance porch, platform shelter, platform surfacing, waiting hall,
toilet, circulating area, parking and entry arch have been completed.
The works of lift, escalator and 12 m foot over bridge have been taken
up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station are carried out based on category
of station/condition/traffic handled etc.
Further, development/redevelopment/upgradation of Railway Stations is
complex in nature involving safety of passengers & trains and requires
various statutory clearances such as fire clearance, heritage, tree cutting,
airport clearance etc. The progress also gets affected due to brown field
related challenges such as shifting of utilities, (involving water/sewage
lines, optical fiber cables, gas pipe lines, power/signal cables etc.)
infringements, operation of trains without hindering passenger movement,
speed restrictions due to works carried out in close proximity of high
voltage power lines etc. and these factors affect the completion time.
Therefore, no time frame can be indicated at this stage.
Page 5 of 6Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme are generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation and expenditure under Plan Head-53
are maintained Zonal Railway-wise and not station-wise or state-wise.
Mangalore Central and Mangalore junction Railway stations fall under the
jurisdiction of Southern Railway for which an allocation (RE) of ₹ 1125
crores has been made for the financial year 2025-26. For Southern Railway,
total expenditure of ₹3210 crores has been incurred during the last four
and current year (till January, 2026).
*****
Page 6 of 6