GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 272
TO BE ANSWERED ON 11.03.2026
UTILISATION OF BUDGETARY GRANTS FOR RAILWAYS
*272. SMT. SHAMBHAVI:
SHRI MUKESHKUMAR CHANDRAKAANT DALAL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the utilisation of budgetary grants and appropriations by
the Ministry for the Financial Year 2025-26;
(b) whether spending of nearly eighty percent of the allocated Rs. 2.5 lakh
crore for the said Financial Year has been reported and if so, the details
thereof;
(c) the major sectors/projects on which these funds were expended
particularly in Khagaria, Samastipur, Surat, Ghaziabad, Sagar and Jamui
Lok Sabha Constituencies;
(d) whether any mechanism has been put in place for monitoring expenditure,
ensuring financial discipline and preventing cost overruns and if so, the
details thereof and if not, the reasons therefor;
(e) whether any reallocations/supplementary provisions were made during
the year to meet priority requirements and if so, the details thereof and
if not, the reasons therefor; and
(f) the manner in which actual expenditure during the Financial Year, 2026
compares with targets and utilisation in previous years to enable future
planning?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): A Statement is laid on the Table of the House.
*****
§STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (f) OF STARRED
QUESTION NO.272 TO BE ANSWERED ON 11.03.2026 IN LOK SABHA
(a) to (f): The utilization of Gross Budgetary Allocations by Indian Railways
is as follows:
(₹ in crore)
Financial Year Gross Budgetary Allocation % Utilisation
2024-25 2,52,200 100%
2025-26 2,52,200 ~ 97%
(as on 09.03.2026)
Indian Railways has significantly ramped up its project execution capability
in recent years. Gross Budgetary Allocation for Railway has increased
approximately 8 times from ₹ 32,300 crore in FY 2014–15 to ₹ 2,52,200 crore
in FY 2025–26 for expanding the network capacity.
The Railway projects are surveyed/sanctioned/executed Zonal Railway-wise
and not State-wise/Constituency-wise as the Railway projects may span
across State boundaries. The major sectors on which funds were expended
include new lines, doubling, multitracking, gauge conversion, ROB/RUB
construction, station redevelopment and passenger amenities etc. The
State-wise detail are as follows:
Bihar
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the State of Bihar is as under:
Period Outlay
2009-14 ₹1,132 Cr./year
2025-26 ₹10,066 Cr. (Nearly 9 times)
The details of commissioning/laying of new track falling fully/partly in the
State of Bihar during 2009-14 and 2014-25 is as under:-
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 318 Km 63.6 Km/yr
2014-25 1,899 Km 172.6 Km/yr(More than 2.5 times)
2As on 01.04.2025, 52 projects (31 New Lines, 01 Gauge Conversions and 20
Doubling), of a total length of 4,663 km, costing ₹86,107 crore, falling
fully/partly in Bihar, are sanctioned. The summary is as under:-
Total Length Total Exp
No of
Length Commissioned upto
Category sanctioned
NL/GC/DL till Mar'25 Mar'25
Projects
(in Km) (in Km) (₹ in Cr)
New Lines 31 2,691 516 16,814
Gauge
1 69 52 544
Conversion
Doubling/Multi-
20 1,904 446 11,995
tracking
Total 52 4,663 1,014 29,353
Status of major projects falling in Khagaria, Jamui and Samastipur Lok
Sabha constituencies of Bihar is as under:
Name of Total Length Commissioned (in Status of balance
Project Length Km) length
(in Km) (in Km)
Sakri- 84 54 Km commissioned. 30 Km balance.
Hasanpur Sections Commissioned: Works taken up in
new line • Sakri-Harnagar (44 Km) balance section
• Bithan - Hasanpur Road Harnagar - Bithan (30
(10 Km) Km)
Doubling of 38 26 Km commissioned. 12 Km balance.
Samastipur Sections Commissioned: Works taken up in
Darbhanga • Samastipur – balance section
Rambhadrapur (16 Km) Rambhadrapur –
• Thalwara – Darbhanga Thalwara (12 Km)
(10 Km)
Khagaria- 41 19 Km commissioned. 22 Km balance.
Kushweshw Section Commissioned: • Works taken up in
arsthan new • Khagaria – Alauli (19 balance section
line Km) Alauli –
Kushweshwarstha
n (22 Km)
Jhajha – 20 - • Works taken up
Batia new
line
3Details of some of the recently completed projects falling fully/partly in the
State of Bihar are as under:
S.No. Project Cost
(₹ in Crore)
1 Munger Bridge (19 km) 2,774
2 Kosi Bridge (22 Km) 516
3 Patna Bridge (40 Km) 3,555
4 Hajipur-Bachwara Doubling (72 km) 930
5 Kiul-Gaya Doubling (123 km) 1,200
6 KarotaPatner-Mankatha - Surface triangle (8 km) 129
7 Rampurhat-Mandarhill New Line and Rampurhat- 1,500
Murarai- 3rd line (160 km)
8 Jaynagar-Darbhanga-Narkatiaganj and Narkatiaganj- 1,193
Bhikhna Tori Gauge Conversion (295 Km)
9 Sakri-Laukaha Bazar-Nirmali & Saharsa-Forbesganj 2,113
Gauge Conversion (206 Km)
10 Bakhtiyarpur Flyover (4 Km) 402
11 Katareah-Kursela Patch Doubling incl. bridge on river 222
Kosi (7 km)
12 Araria-Galgalia New Line (111 Km) 4, 415
Some of the projects falling fully/partly in the State of Bihar which have been
taken up are as under:
S.No. Project Cost
(₹ in Cr.)
1 Sitamarhi-Sheohar New Line (28 Km) 567
2 Sakri-Hasanpur New Line (76 Km) 735
3 Khagaria-Kusheshwarsthan New Line (42 Km) 1,511
4 Neora-Daniawan–Biharsharif-Barbigha-Shekhpura 2,200
New Line (166 Km)
5 Koderma-Tilaiya New Line (65 Km) 1,626
6 Hajipur-Sagauli New Line (151 Km) 2,087
7 Araria-Supaul New Line (96 Km) 1,605
8 Vikramshila-Katareah New Line with Bridge over 2,090
RiverGanga(26 Km)
9 Pirpainti-Jasidih New Line (97 Km) excluding 2,140
Hansdiha-Godda New Line (30 Km)
10 Sonnagar – Patratu multitracking (291 Km) 5,148
11 Samastipur – Darbhanga Doubling (38 Km) 624
4S.No. Project Cost
(₹ in Cr.)
12 Rampur Dumra - Tal-Rajendra Pul-Additional 1,677
bridge and doubling (14 Km)
13 Sagauli-Valmiknagar Doubling (110 Km) 1,280
14 Muzaffarpur-Sagauli Doubling (101 Km) 1,465
15 Barauni- Bachwara 3rd & 4th line (32 Km) 124
16 Son Nagar – Andal Multi tracking (749 Km) 12,334
17 Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km) 2,192
18 Bakthiyarpur-Fatuha 3rd and 4th line (24 Km) 931
Madhya Pradesh
Budget allocation in the recent years has increased significantly. Budget
allocation for Infrastructure projects and safety works, falling fully/partly in
the State of Madhya Pradesh is as under:
Period Outlay
2009-14 ₹632 crore/year
2025-26 ₹14,745 crore (More than 23 times)
The details of commissioning/laying of new track falling fully/partly in the
State of Madhya Pradesh during 2009-14 and 2014-25 is as under:
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 145 Km 29 Km/year
2014-25 2651 Km 241 Km/year (More than 8 times)
As on 01.04.2025, 24 Railway projects (08 New Lines, 02 Gauge Conversion
and 14 Doubling), of total length of 4,740 Km costing ₹89,542 crore falling
fully/partly in the State of Madhya Pradesh are sanctioned. The summary is
as under:
Category No. of Total Length Total Exp upto
projects Length Commissioned Mar'25
(in Km) (in Km) (₹ in Cr)
New Lines 8 1914 544 15,069
Gauge
2 809 430 6,766
Conversion
Doubling /
14 2017 1118 19,566
Multitracking
Total 24 4,740 2,093 41,401
5Status of major projects falling in Sagar Lok Sabha constituencies of Madhya
Pradesh is as under:
Name of Project Total Length Commissioned Status of balance
Length (in Km) length
(in Km) (in Km)
Katni-Bina 3rd 263 • Project -
line commissioned.
Jhansi-Bina 3rd 153 133 Km 20 Km balance.
line commissioned. Works taken up in
Sections balance sections
commissioned: Jakhlaun – Dhaura
• Jhansi – Jakhlaun (12 Km) and Agasod –
(107 km) Bina (8 Km)
Dhaura – Agasod (26
Km)
Itarsi-Bina 4th 237 - Recently sanctioned.
line (237 Km)
Details of some of the recently completed projects falling fully/partly in the
State of Madhya Pradesh are as under:
S.No. Name of Project Latest Cost
(₹ in Crores)
1. Anuppur-Katni 3rd line (165 Km) 2,311
2. Pendra Road-Anuppur 3rd line (50 Km) 394
3. Khodri-Anuppur Doubling with flyover at Bilaspur (72 792
Km)
4. Bhopal-Bina 3rd line (145 km) 1,075
5. Bina-Kota Doubling (283 km) 2,477
6. Jabalpur-Gondia Gauge Conversion including 2,005
Balaghat-Katangi (300 Km)
7. Chhindwara-Nagpur Gauge Conversion (150 Km) 1,512
8. Chhindwara-Mandla Fort Gauge Conversion (182 Km) 1,268
9. Ghat Pindari-Balkheda Doubling (6 Km) 29
10. Guna-Ruthiyai Doubling (20 Km) 175
11. Jukhei Chord line, Bye Passing the Katni Yard (2 Km) 12
12. Sontalai-Bagratawa Doubling (7 Km) 110
13. Itarsi-Budhni 3rd line (25 Km) 286
14. Teegaon-Chichonda Ghat Section 3rd line (17 Km) 176
15. Barkhera-Bhopal 3rd line (41 km) 473
6S.No. Name of Project Latest Cost
(₹ in Crores)
16. Nagda-Ujjain Doubling of Gambhir Bridge (2 Km) 28
17. Nimach-Chittaurgarh Doubling (56 Km) 560
18. Budhni-Barkhera 3rd line (27 Km) 1,703
19. Indore-Dewas-Ujjain Doubling (79 Km) 757
20. Powerkheda-Jujharpur Rail flyover (16 Km) 443
21. Guna- Etawah New Line (348 Km) 683
22. Ramna-Singrauli doubling (160 Km) 2,436
23. Karaila Road- ShaktinagarDoubling(32 Km) 763
24. Malkhedi-Mahadeokhedi Doubling (12 Km) 59
Some of the projects falling fully/partly in the State of Madhya Pradesh which
have been taken up are as under:
S. No Project Cost
(₹ in Crores)
1. Shahdol-Singhpur 4th Line (6 Km) (passing through
54
Shahdol constituency)
2. Katni- Grade separator / Bypass (35 Km) 2300
3. Katni- Singrauli Doubling (257 Km) 4377
4. Lalitpur-Satna, Rewa-Singrauli&Mahoba-
8914
Khajuraho New Line (541 Km)
5. Ramganjmandi-Bhopal New Line (277 Km) 5073
6. Indore-Budni New Line (198 Km) 7474
7. Nimach-Badi Sadri New Line (48 Km) 495
8. Gwalior-Sheopurkalan Gauge Conversion with
2913
extension to Kota (284 Km)
9. Itarsi- Nagpur 3rd line (280 Km) 2450
10. Jhansi-Bina 3rd line (153 Km) 2002
11. Mathura-Jhansi 3rd line (274 Km) 5924
12. Jhansi-Kairar-Manikpur&Khirar-Bhimsen Doubling 4330
(431 Km)
13. Satna-Rewa Doubling (50 Km) 590
14. Ruthiyai Bye Pass line (3 Km) 54
15. Guna Bye Pass line (2 Km) 179
16. Ujjain Fly Over (2 Km) 100
17. Manmad - Indore New Line (360 Km) 18529
18. Bhusawal-Khandwa 3rd & 4th Line (131 Km) 3285
19. Dahod-Indore New Line (205 Km) 9746
20. Nimach-Ratlam Doubling (133 Km) 1096
21. Chhota Udepur-Dhar New Line (147 Km) 1794
7S. No Project Cost
(₹ in Crores)
22. Ratlam-Nagda 3rd and 4th line (41 Km) 964
23. Vadodara-Ratlam 3rd and 4th line (259 Km) 8387
24. Ratlam-Khandwa Gauge Conversion (299 Km) 7265
25. Bina-Itarsi 4th Line (237 km) 4329
26. Itarsi-Nagpur 4th Line (297 Km) 5010
Gujarat
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Gujarat is as under:
Period Outlay
2009-14 ₹ 589 crore/year
2025-26 ₹. 17,155 crore (More than 29 times)
The details of commissioning/laying of new track falling fully/partly in the
State of Gujarat during 2009-14 and 2014-25 is as under:
Period New Track Average Commissioning of new
Commissioned tracks
2009-14 660 Km 132 Km/year
2014-25 2,764 Km 251 Km/yr (nearly 2 times)
As on 01.04.2025, 36 Railway projects (6 New Lines, 17 Gauge Conversion
and 13 Doubling), of a total length of 2,564 Km, costing ₹30,275 crore, falling
fully/partly in the State of Gujarat have been sanctioned. The summary is as
under:-
Category No. of Total Length Total Expenditure upto
sanctioned length commissioned Mar'25
projects (Km) upto Mar'25 (₹ in Cr.)
(Km)
New Lines 6 532 105 5,494
Gauge
17 1,379 718 6,213
Conversion
Doubling /
13 653 40 1,158
Multitracking
Total 36 2,564 863 12,865
8Details of some of the completed projects falling fully/partly in the State of
Gujarat are as under:
S.No. Name of Project Cost
(₹in Cr.)
1 Mahesana-Taranga Hill Gauge Conversion (210 891
Km)
2 Himmatnagar-Khedbrahma Gauge Conversion 482
(55 Km)
3 Ahmedabad-Botad Gauge Conversion (170 Km) 1,810
4 Dhasa-Jetalsar Gauge Conversion (104 Km) 1,024
5 Ahmedabad-Mahesana Gauge Conversion (69 874
Km)
6 Katosan-Chanasma Gauge Conversion (38 Km) 484
7 Kalol-Kadi-Katosan Gauge Conversion (37 Km) 347
8 Vijapur-Ambliyasan Gauge Conversion (42 Km) 415
9 Dabhoi-Chandod with extension up to Kevadiya 1,018
Gauge Conversion (50 Km)
10 Viramgam-Samakhiali Doubling (182 Km) 1,492
11 Palanpur-Samakhayali Doubling (247 Km) 2,538
12 Mahesana-PalanpurDoubling (65 Km) 537
13 Surendranagar-Rajkot Doubling (116 Km) 1,425
14 Anand-GodharaDoubling (79 Km) 692
15 Vatva-Ahmedabad 3rd Line (8 Km) 61
16 Viramgram-Surendranagar Doubling (65 Km) 382
17 Udhna-Jalgaon Doubling (307 Km) 2,448
Details of some of the projects falling fully/partly in the State of Gujarat
which have been taken up are as under:
S. No. Project Cost
(₹ in Cr.)
1 Naliya-Jakhau Port New Line (25 Km) 410
2 Miyagam Karjan-Choranda-Malsar Gauge Conversion 450
(37 Km)
3 Jambusar-Kavi Gauge Conversion (26 Km) 318
4 Kosamba-Umarpada Gauge Conversion (70 Km) 468
5 Khijadiya-Amreli Gauge Conversion (17 Km) 178
6 Barejadi-Nandej (Geratpur)- Sanand 4th Line (38 Km) 962
7 Samakhiali-Gandhidham Quadrupling (53 Km) 1430
8 Vishvamitri-Dabhoi Doubling (33 Km) 394
9 Taranga Hill- Ambaji-Abu Road New Line (116 Km) 2798
910 Sabarmati D Cabin- Sarkhej Doubling (21 Km) 323
11 Deshalpar-Hajipir-Luna and Vayor-Lakhpat New Line 2526
(145 Km)
12 Vadodara-Ratlam 3rd & 4th Line (259 Km) 8387
13 Rajkot-Kanalus Doubling (111 Km) 1081
To improve connectivity in Surat Constituency, following projects/survey has
been taken up:
1) Construction works on the flagship High speed bullet train project have
gathered momentum in Maharashtra. Now 100% land acquisition has
been completed. Works of bridges, aqueducts etc. have been taken up.
2) Western DFC also passes through Maharashtra. About 178 route Km of
western DFC is situated in Maharashtra which is about 12% of overall
route length of western DFC. 76 Km of this project from New Gholvad
to New Vaitarna in Maharashtra has already been commissioned.
Balance works have been taken up. Connectivity of WDFC to JNPT will
boost the capacity to handle cargo and container traffic from port to
Delhi NCR.
3) Some of the important surveys falling fully/partly in the Surat have been
taken up are as under:
S.No. Project Length (in
KMs)
1 Udhna-Jalgaon 3rd and 4th line 304
2 Dahanu-Surat-Vadodara-Anand 3rd and 4th 311
line
Uttar Pradesh
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Uttar Pradesh is as under:
Period Outlay
2009-14 ₹1,109 crore/year
2025-26 ₹19,858 crore (Nearly 18 times)
The details of commissioning/laying of new track falling fully/partly in the
State of Uttar Pradesh during 2009-14 and 2014-25 is as under:
10New Track
Period Average Commissioning of new tracks
Commissioned
2009-14 996 Km 199 Km/year
2014-25 5272 Km 479 Km per year (More than 2 times)
As on 01.04.2025, 49 projects (10 New Line, 02 Gauge Conversion and 37
Doubling) of 3,807 Km length, costing ₹62,360 crore falling fully/partly in the
State of Uttar Pradesh are sanctioned. The summary is as under:-
Category No of Total Length Exp
Projects Length Commissioned upto
(km) (km) Mar'25
(₹ in Cr.)
New Line 10 1,227 340 10,517
Gauge Conversion 02 67 0 281
Doubling/Multitracking 37 2,513 983 19,813
Total 49 3,807 1,323 30,611
Status of major project falling in Ghaziabad Lok Sabha constituencies of
Uttar Pradesh is as under:
Name of Project Total Length Length Status of
(in Km) Commissioned balance length
(in Km) (in Km)
Chipyana-Buzurg- 3 - Works taken up
Ghaziabad – 4th line
Details of some of the recently completed projects falling fully/partly in the
State of Uttar Pradesh are as under:
Cost
S. N. Project
(₹ in Cr.)
Domingarh-Gorakhpur-Kusumhi - 3rd Line and
1 508
Gorakhpur-Nakaha Jungle Doubling (21 Km)
Bahraich-Nanpara-Nepal Ganj Gauge Conversion (56
2 342
Km)
3 Ballia-Ghazipur city Doubling (65 Km) 650
4 Ghazipur city-Tarighat New Line (17 Km) 1,766
5 Gonda-Gorakhpur Loop Gauge Conversion (260 Km) 863
6 Gonda-Bahraich Gauge Conversion (60 Km) 318
7 Barabanki-Akbarpur Doubling (161 Km) 1,700
Kaptanganj-Thawe-Chhapra Gauge Conversion (234
8 819
Km)
11Cost
S. N. Project
(₹ in Cr.)
9 Pilibhit-Shahjahanpur Gauge Conversion (83 Km) 589
10 Indara-Dohrighat Gauge Conversion (34 Km) 213
11 Lucknow-Pilibhit Gauge Conversion (263 Km) 1,634
12 Bhadoi-Janghai Doubling (31 Km) 168
13 Lahota-Bhadoi Doubling (39 Km) 184
14 Meerut-Muzaffarnagar Doubling (55 Km) 430
15 Phaphamau-Prayagraj Doubling (14 Km) 212
16 Muzaffarnagar–Tapri Doubling (52 Km) 525
17 Utretia-Raibareilly Doubling (66 Km) 662
18 Raibareilly-Amethi Doubling (60 Km) 668
19 Alamnagar-Utretia Doubling (20 Km) 358
20 Bhimsen—Jhansi Doubling (206 Km) 2,620
21 Etawah-Mainpuri New Line (58 Km) 313
22 Malhaur-Daliganj Doubling (13 Km) 183
23 Ruma Chakeri- Chandari 3rdLine (13 Km) 177
Bareilly-Pilibhit-Tanakpur Gauge Conversion (102
24 313
Km)
25 Rosa-Sitapur Cantt-Burhwal Doubling (181 Km) 2,094
26 Jaunpur- Akbarpur (Tanda) Doubling (77 Km) 676
27 Ramna- Renukut-Singrauli Doubling (160 Km) 2,436
28 Janghai- PhaphamauDoubling (47 Km) 414
29 Varanasi-Madhosingh-Prayagraj Doubling (120 Km) 2,018
30 Karaila Road- ShaktinagarDoubling (32 Km) 763
31 Deoband (Muzzafarnagar)-Roorkee (27 Km) 1,289
32 Agra-Etawah New Line(110 Km) 427
33 Phephna-Indara, Mau-Shahganj Doubling (150 Km) 1,778
Some of the projects falling fully/partly in the State of Uttar Pradesh which
have been taken up are as under:
S.No. Project Cost(₹ in Cr.)
1 Barabanki-Burhwal 3rd Line (27 Km) 426
2 Burhwal- Gonda Kacheri 4th line (56 Km) 796
3 Burhwal-Gonda 3rd Line (62 Km) 1118
4 Bahraich- Khalilabad New Line (240 Km) 4940
5 Katra-Ayodhya Dham Doubling (10 Km) 466
6 Pt. Deen Dayal Upadhyaya- Prayagraj 3rd Line 2649
(150 Km)
7 Billi-Chunar Doubling (102 Km) 1424
8 Chhapra-Ballia Doubling (65 km) 1046
9 Unchhar-Amethi New Line (66 Km) 1229
1210 Etah-Kasganj New Line (29 Km) 389
11 Gorakhpur- Valmikinagar Doubling (96 Km) 1121
12 Varanasi-Pt. Deen Dayal Upadhyaya 3rd and 4th 2464
Line (15 Km)
13 Jhansi-Khairar-Manikpur&Khairar-Bhimsen 4330
Doubling (431 Km)
14 Sahjanwa-Dohrighat New Line (81 Km) 1320
Station Redevelopment
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their implementation
in phases to improve the stations. The master planning includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
• Amenities for Divyangjans
• Better passenger information systems
• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
13The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1337 stations have been identified for development under Amrit
Bharat Station Scheme. Out of these, 98 stations are located in Bihar, 87
stations are located in Gujarat, 80 stations are located in Madhya Pradesh
and 157 stations are located in Uttar Pradesh including:
• 4 stations (Khagaria Junction, Maheshkhunt, Mansi Junction and Simri
Bakhtiyarpur) of Khagaria Lok Sabha Constituency,
• Samastipur station of Samastipur Lok Sabha Constituency,
• 5 stations ( Bhestan, Kim, Sayan, Surat and Utran) of Surat Lok Sabha
Constituency,
• Ghaziabad station of Ghaziabad Lok Sabha Constituency,
• 2 stations (Bina and Saugor) of Sagar Lok Sabha Constituency.
The names of stations identified for development under Amrit Bharat Station
Scheme in Bihar, Gujarat, Madhya Pradesh and Uttar Pradesh are as
following:
No. of
State Names of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi,
BapudhamMotihari, Barahiya, Barauni, Barh,
Barsoi Jn, Begusarai, Bettiah, Bhabua Road,
Bhagalpur, Bhagwanpur, Bihar Sharif, Bihiya,
Bikramganj, Buxar, Chakia, Chausa,
Chhapra, Dalsingh Sarai, Darbhanga,
DauramMadhepura, Dehri On Sone, Dholi,
Dighwara, Dumraon, Durgauti, Ekma, Fatuha,
Gaya, Ghorasahan, Guraru, Hajipur Jn,
Jamalpur Jn, Jamui, Janakpur Road,
Jaynagar, Jehanabad, Jhanjharpur,
Kahalgaon, Karhagola Road, Katihar Jn,
Khagaria Jn, Kishanganj, Kudra, Labha,
Laheria Sarai, Lakhminia, Luckeesarai Jn,
Madhubani, Maheshkhunt, Mairwa, Mansi Jn,
14No. of
State Names of Stations
Stations
Masrakh, Mokama, Motipur, Munger
(Monghyr), Muzaffarpur Jn, NabinagarRoad,
Narkatiaganj Jn, Naugachia, Nawadah,
Paharpur, Patliputra, Patna Jn, Piro,
Pirpainti, Rafiganj, Raghunathpur., Rajendra
Nagar Terminal (Patna), Rajgir, Ram Dayalu
Nagar, Raxaul, Sabaur, Sagauli, Saharsa,
Sahibpur Kamal, Sakri, Salauna, Salmari,
Samastipur, Sasaram, Shahpur Patoree,
Shivanarayanpur, Simri Bakhtiyarpur,
Simultala, Sitamarhi, Siwan, Sonpur Jn.,
Sultanganj, Supaul, Taregna, Thakurganj,
Thawe
Gujarat 87 Ahmedabad, Anand, Ankleshwar, Asarva,
Bardoli, Bhachau, Bhaktinagar, Bhanvad,
Bharuch, Bhatiya, Bhavnagar, Bhestan,
Bhildi, Bilimora Jn, Botad Jn., Chandlodia,
Chorvad Road, Dabhoi Jn, Dahod, Dakor,
Derol, Dhrangadhra, Dwarka, Gandhidham,
Godhra Jn, Gondal, Hapa, Himmatnagar, Jam
Jodhpur, Jam Wanthali, Jamnagar, Junagadh
Jn, Kalol Jn, Kanalus Jn, Karamsad, Keshod,
Khambhaliya, Kim, Kosamba Jn, Lakhtar,
Limbdi, Limkheda, Mahemadabad Kheda
Road, Mahesana Jn, Mahuva, Maninagar,
Mithapur, Miyagam Karjan Jn, Morbi, Nadiad
Jn, Navsari, New Bhuj, Okha, Paddhari,
Palanpur Jn, Palitana, Patan, Porbandar,
Pratapnagar, Rajkot Jn, Rajula Jn, Sabarmati
BG, Sabarmati MG, Sachin, Samakhiyali,
Sanjan, Savarkundla, Sayan, Siddhpur, Sihor
Jn., Somnath, Songadh, Surat,
Surendranagar, Than, Udhna, Udvada,
Umargaon Road, Unjha, Utran, Vadodara,
Vapi, Vatva, Veraval, Viramgam, Vishvamitri
Jn., Wankaner
Madhya 80 Akodia, Amla, Anuppur, Ashoknagar,
Pradesh Balaghat, Banapura, Bargawan, Beohari,
Berchha, Betul, Bhind, Bhopal, Bijuri, Bina,
BiyavraRajgarh, Chhindwara, Dabra, Damoh,
15No. of
State Names of Stations
Stations
Datia, Dewas, Gadarwara, Ganjbasoda,
Ghoradongri, Guna, Gwalior, Harda,
Harpalpur, Indore Jn, Itarsi Jn, Jabalpur,
Junnor Deo, Kareli, Katni Jn, KatniMurwara,
Katni South, Khachrod, Khajuraho Jn,
Khandwa, Khirkiya, Laxmi Bai Nagar, Maihar,
Maksi Jn, Mandla Fort, Mandsor, MCS
Chhatarpur, Meghnagar, Morena, Multai,
Nagda Jn, Nainpur Jn, Narmadapuram
(Hoshangabad), Narsinghpur, Nepanagar,
Nimuch, Orchha, Pandhurna, Pipariya,
Ratlam, Rewa, Ruthiyai, Sanchi, Sant
Hirdaram Nagar, Satna, Saugor, Sehore,
Seoni, Shahdol, Shajapur, Shamgarh,
Sheopur Kalan, Shivpuri, Shridham,
Shujalpur, Sihora Road, Singrauli,
Tikamgarh, Ujjain, Umaria, Vidisha,
Vikramgarh Alot
Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh
Pradesh Jn, Akbarpur Jn, Aligarh, Amethi, Amroha,
Anand Nagar Jn., Aonla, Ayodhya Dham
Junction, Azamgarh, Babatpur, Bachhrawan,
Badaun, Badshahnagar, Badshahpur, Baheri,
Bahraich, Balamau Jn., Ballia, Balrampur,
Banaras, Banda, Barabanki Jn, Bareilly,
Bareilly City, Barhni, Basti, Belthara Road,
Bhadohi, Bharatkund, Bhatni, Bhuteshwar,
Bijnor, Bulandsahar, ChandauliMajhwar,
Chandausi, Chilbila, Chitrakutdhamkarwi,
Chopan, Chunar Jn., Daliganj, Darshannagar,
Deoria Sadar, Dhampur, Dildarnagar, Etawah
Jn., Farrukhabad, Fatehabad, Fatehpur,
Fatehpur Sikri, Firozabad, Gajraula,
Garhmuktesar, Gauriganj, Ghatampur,
Ghaziabad, Ghazipur City, Gola Gokarnath,
Gomtinagar, Gonda, Gorakhpur, Govardhan,
Govindpuri, Gursahaiganj, Haidergarh,
Hapur, Hardoi, Hathras City, Idgah Agra Jn,
Izzatnagar, Janghai Jn, Jaunpur City,
Jaunpur Jn, Kannauj, Kanpur Anwarganj,
Kanpur Bridge Left Bank, Kanpur Central,
16No. of
State Names of Stations
Stations
Kaptanganj Jn, Kasganj Jn, Kashi,
Khalilabad, Khorason road, Khurja Jn., Kosi
Kalan, Kunda Harnamganj, Lakhimpur,
Lalganj, Lalitpur Jn, Lambhua, Lohta,
Lucknow (Charbagh) NR, Lucknow city,
Lucknow Jn. (NER), Maa Belha Devi
Pratapgarh Junction, Maghar, Maharaja Bijli
Pasi, Mahoba Jn, Mailani Jn, Mainpuri Jn,
Malhaur, Manak Nagar, Manikpur Jn,
Mariahu, Mathura Jn, Mau Jn, Meerut City Jn,
Mirzapur, Modinagar, Mohanlalganj,
Moradabad Jn, Muzaffarnagar, Nagina,
Najibabad Jn, Orai, Panki Dham, Phaphamau
Jn, Phulpur, Pilibhit Jn, Pokhrayan, Prayag
Jn, Prayagraj Jn, Pt. Deen Dayal Upadhyay Jn
, Rae Bareli Jn, Raja Ki Mandi, Ramghat Halt,
Rampur Jn, Renukoot, Saharanpur Jn.,
Salempur, Seohara, Shahganj Jn,
Shahjahanpur, Shamli, Shikohabad Jn.,
Shivpur, Siddharth nagar, Sitapur Jn.,
Sonbhadra, Sri Krishna Nagar, Sultanpur Jn,
Suraimanpur, Swaminarayan Chappia, Takia,
Tulsipur, Tundla Jn., Ujhani, Unchahar,
Unnao Jn, Utraitia Jn, Varanasi Cantt.,
Varanasi City, Vindhyachal, Virangana
Lakshmibai Jhansi, Vyasnagar, Zafarabad
Development works at railway stations under Amrit Bharat Station Scheme
in Bihar, Gujarat, Madhya Pradesh and Uttar Pradesh have been taken up at
a good pace and the works have been completed at following stations in
Bihar, Gujarat, Madhya Pradesh and Uttar Pradesh:
Ayodhya Dham Junction, Balrampur, Bareilly City, Beohari, Bhind, Bijnor,
Chhindwara, Dakor, Derol, Fatehabad, Fatehpur, Godhra Jn, Gola Gokarnath,
Gomtinagar, Govardhan, Govindpuri, Hapa, Harpalpur, Hathras City, Idgah
Agra Jn, Izzatnagar, Jam Jodhpur, Jam Wanthali, Junnor Deo, Kanalus Jn,
Karamsad, Katni South, Khalilabad, Khambhaliya, Kosamba Jn, Limbdi,
17Mahuva, Mailani Jn, MCS Chhatarpur, Mithapur, Morbi, Nainpur Jn,
Narmadapuram, Okha, Orchha, Palitana, Panki Dham, Pirpainti, Pokhrayan,
Porbandar, Rajula Jn, Ramghat Halt, Saharanpur Jn., Samakhiyali, Sanchi,
Seoni, Shajapur, Shridham, Siddharth Nagar, Sihor Jn., Suraimanpur,
Swaminarayan Chappia, Thawe, Ujhani, Utran and Vidisha
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Khagaria Lok Sabha Constituency:
• Khagaria Junction station: The structural work of new station building
till second floor, raising and extension of platform no. 2/3 have been
completed. The works of new entrance porch, new platform shelter,
circulating area and 12 m Foot Over Bridge have been taken up.
• Maheshkhunt station: The works of erection of canopy structure in
front of station building and widening of approach road have been
completed. The works of improvement of station building, platform
shelter, circulating area, parking and boundary wall have been taken
up.
• Mansi Junction station: The structural work of new station building till
second floor has been completed. The works of new platform shelter,
circulating area and 12 m Foot Over Bridge have been taken up.
• Simri Bakhtiyarpur station: The works of new station building, platform
shelter, circulating area and parking have been completed. The work
of 12 m Foot Over Bridge has been taken up.
Samastipur Lok Sabha Constituency:
• Samastipur station: The works of new station building at second entry,
improvement of existing waiting hall, toilet and circulating area have
been taken up.
Surat Lok Sabha Constituency:
18• Bhestan station: The works of station building, platform shelter,
platform raising, extension and surfacing, circulating area and 12 m
Foot Over Bridge have been taken up.
• Kim station: The works of entrance porch, platform shelter, platform
surfacing, improvement of waiting hall, toilet and entry/exit gate have
been completed. The works of improvement of station building,
signage and Divyangjan facilities have been taken up.
• Sayan station: The works of improvement of station building,
concourse, platform raising and surfacing, platform shelter,
improvement of toilet, circulating area, parking and entry gate have
been completed. The works of 12 m Foot Over Bridge have been taken
up.
• Surat station: The works of Electronic Interlocking (EI) building,
running room, Railway Protection Force barrack, hospital and
structural work of Gujarat State Road Transport Corporation (GSRTC)
building have been completed. The works of East side station building,
concourse, platform shelter, platform surfacing and finishing works of
Gujarat State Road Transport Corporation (GSRTC) building have been
taken up.
Ghaziabad Lok Sabha Constituency:
• Ghaziabad station: The structural works of station building at main
entry side and second entry side, foundation work of new Foot Over
Bridge-B at Tundla end, roof plaza, extension work of existing Foot Over
Bridge-A, finishing work of electrical substation at main entry side and
second entry side, Magistrate building, Government Railway Police and
Railway Protection Force buildings have been taken up.
Sagar Lok Sabha Constituency:
• Saugor station: The works of improvement of station building, new
entry and exit porches, platform raising and surfacing of platform no.
191, improvement of waiting hall, new toilet block and Divyangjans
facilities have been completed. The works of circulating area, parking
and 12 m Foot Over Bridge have been taken up.
At Bina station, high level platform, platform shelter, enquiry counter, retiring
room, cloak room, waiting hall, lift, Foot Over Bridge etc. amenities are
available. The works of platform shelter, lift at platform no. 4/5, seating
arrangement and Divyangjan water booths have been completed in recent
years.
Further, Bina station has been identified for development under Amrit Bharat
Station Scheme which includes works of new station building, porch, air
concourse, improvement of existing platforms, parking, lift, escalator and
Foot Over Bridge.
Development / upgradation / modernisation of stations including under Amrit
Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation and expenditure under Plan Head-53 are
maintained Zonal Railway-wise and work-wise, not station-wise or state-
wise.
Road Over Bridges (ROBs)/Road Under Bridges (RUBs)
Sanctioning of works of Road over Bridges (ROBs)/Road under Bridges
(RUBs) in lieu of Level crossings (LCs) is a continuous and dynamic process
of Indian Railway. Such works are prioritised and taken up on the basis of its
impact on safety in train operations, mobility of trains & impact for road
users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto Jan’26) 14,024 Nos.
20As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at cost of ₹
1,14,196 Cr on Indian Railways which are at various stages of planning and
execution. The ongoing works for mentioned Lok Sabha Constituency are as
under:
S.No. Constituency Total ongoing works (ROBs/ Total cost
RUBs) (₹ in crore)
1. Khagaria 8 447
2. Samastipur 6 464
3. Surat 39 267
4. Ghaziabad 21 367
5. Sagar 16 641
6. Jamui 3 87
Further, the details of allocation and expenditure for ROBs/RUBs work are
maintained Zonal Railway-wise.
Bihar is covered under the jurisdiction of four railway zones, namely Eastern
Railway, Northeast Frontier Railway, North Eastern Railway and East Central
Railway. For these zones, an allocation of ₹ 1,828 crore has been made for
the financial year 2025–26, out of which an expenditure (up to January, 2026)
of ₹ 1,584 crore has been incurred so far.
Gujarat is covered under the jurisdiction of two railway zones, namely North
Western Railway and Western Railway. For these zones, an allocation of ₹
2,081 crore has been made for the financial year 2025–26, out of which an
expenditure (up to January2026) of ₹ 1,820 crore has been incurred so far.
Madhya Pradesh is covered under the jurisdiction of seven railway zones,
namely Central Railway, East Central Railway, North Central Railway, South
Central Railway, South East Central Railway, West Central Railway and
Western Railway. For these zones, an allocation of ₹ 5,801 crore has been
made for the financial year 2025–26, out of which an expenditure (up to
January, 2026) of ₹ 5,105 crore has been incurred so far.
Uttar Pradesh is covered under the jurisdiction of five railway zones, namely
East Central Railway, North Central Railway, Northern Railway, North
21Eastern Railway and West Central Railway. For these zones, an allocation of
₹ 3,794 crore has been made for the financial year 2025–26, out of which an
expenditure (up to January, 2026) of ₹ 3,343 crore has been incurred so far.
Various Steps taken to monitor progress of works including expenditure are
as under :
• Regular reviews at various levels including Railway Board and Zonal
Railway levels;
• Online project monitoring systems and dashboards;
• Adherence to codal provisions and General Financial Rules;
• Internal audit and inspection;
• Milestone-based fund release and outcome monitoring; and
• Contract management systems to prevent cost overruns.
Re-appropriation of funds within Plan Heads is undertaken during the year
based on progress and priority of works, in accordance with delegated
financial powers. Supplementary provisions, where required, are obtained
with dueapprovals to meet committed liabilities and priority requirements.
The actual expenditure during Financial Year 2025-26 is broadly in line with
the targets set in the Budget and continues the trend of enhanced capital
investment witnessed in recent years. This sustained increase in capital
outlay has facilitated faster project execution, improved safety and
enhanced network capacity, and provides inputs for future planning and
realistic target setting.
*****
22