**Executive Summary**
The Ministry of Statistics and Programme Implementation (MoSPI) conducted a review meeting on Central Sector infrastructure projects in the North Eastern States on January 20, 2026, in Guwahati, Assam. Led by Hon'ble Minister of State Rao Inderjit Singh, the meeting aimed to assess project progress, address challenges, and reinforce the government's commitment to infrastructure development in the region, aligning with the vision of Viksit Bharat @2047. Ministries/Departments/Implementing agencies acknowledged and appreciated the support provided by the State Governments in facilitating project execution.
**Key Points / Main Content**
* **Meeting Overview:**
* High-level review of Central Sector infrastructure projects in North Eastern States.
* Organized by MoSPI in association with the Transformation & Development Department, Government of Assam.
* Attended by over 100 officers from 11 Central Ministries and 8 State Governments.
* **Strategic Importance:**
* Infrastructure development is vital for a developed nation and Viksit Bharat @2047.
* Focus on integrated, future-ready, and inclusive infrastructure to enhance productivity and competitiveness.
* Emphasis on strengthening connectivity, logistics, and access to essential services.
* **Project Status:**
* 221 central sector infrastructure projects, totaling Rs. 2.33 lakh crore, are under implementation in the North Eastern Region.
* Projects reviewed spanned 11 Central Ministries/Departments.
* **Ministry-Specific Reviews:**
* **MoRTH:** Reviewed 177 projects covering 3,634 km.
* **Ministry of Railways:** Reviewed nine ongoing projects implemented by NorthEast Frontier Railway (NFR). NFR expedited works including the inauguration of the Bhairabi–Sairang new line in Mizoram on 13.09.2025 and completion of 1,072 route km of electrification. NFR requested State support for addressing issues related to encroachments, land acquisition, law and order, and forest clearances to accelerate project execution.
* **Ministry of Power:** Reviewed nine projects, addressing issues such as contractor availability and compensation for Reserve Forest areas.
* **Ministry of Petroleum and Natural Gas:** Reviewed 21 projects, highlighting implementation challenges and the recent inauguration of the 2G Ethanol (Bio Refinery) at Numaligarh, Assam.
* **Ministry of Civil Aviation:** Reviewed three projects totaling ₹2,534.26 crore, focusing on issues at Imphal and Pakyong Airports.
* **Department of Telecommunications:** Reviewed two projects totaling ₹ 2227.45 crore, emphasizing coordinated development of power distribution and last-mile infrastructure.
* **Department of Higher Education:** Reviewed seven projects amounting to ₹ 2,915.52 crore
* **Government Commitment:**
* Reaffirmation of commitment to accelerating infrastructure development through effective coordination, monitoring, and issue resolution.
* Emphasis on timely project completion and a proactive approach to resolve bottlenecks.
**Impact Analysis**
**Central Ministries/Departments/Implementing Agencies**
* **Impact:** Responsible for implementing infrastructure projects in the North Eastern States.
* **Action Required:** Expedite project execution, address challenges proactively, and collaborate with State Governments for support.
**State Governments (of the North Eastern Region)**
* **Impact:** Play a crucial role in facilitating project execution.
* **Action Required:** Provide support to Central Ministries/Departments in areas such as land acquisition, forest clearances, and law and order to ensure timely project completion.
**Citizens of the North Eastern Region**
* **Impact:** Will benefit from improved connectivity, infrastructure, and socio-economic development.
* **Action Required:** N/A.
Key Entities Referenced
Viksit Bharat @2047: A national vision for a globally competitive and self-reliant India by 2047, emphasized in the review of infrastructure projects.
Ministry of Statistics and Programme Implementation (MoSPI): The central ministry responsible for the review of infrastructure projects and promoting data-driven monitoring.
North Eastern States: The region in India where the infrastructure projects under review are located.
Transformation & Development Department, Government of Assam: The Assam government department that partnered with MoSPI for the infrastructure project review meeting.
Infrastructure and Project Monitoring Division (IPMD): The IPMD division of the Ministry of Statistics and Programme Implementation (MoSPI), which oversees and monitors the infrastructure and project progress.
Ministry of Statistics & Programme Implementation
Press Brief on “Review of Central Sector
Infrastructure projects in North Eastern States”
at Guwahati, Assam
प्रव तथ: 20 JAN 2026 5:30PM by PIB Delhi
Rao Inderjit Singh, Hon’ble Minister of State (Independent Charge), Ministry of Statistics and
Programme Implementation (MoSPI), chaired a high-level review meeting of Central Sector infrastructure
projects under implementation in the North Eastern States at Guwahati. The meeting was organised in
association with Transformation & Development Department, Government of Assam in the presence of
Dr. J.B. Ekka, Additional Chief Secretary, Government of Assam and Shri Dilip Kumar Borah, Senior
Most Secretary to the Government of Assam, Transformation and Development Department. The meeting
was conducted in the presence of 100 plus officers/officials from 11 Central Ministries & their project
implementing agencies and 8 State Governments of the North Eastern Region.
During the review meeting, it was discussed that Infrastructure is the backbone of a developed nation and
a central pillar of the Hon’ble Prime Minister’s vision of Viksit Bharat @2047. Guided by his emphasis
on integrated, future-ready, and inclusive infrastructure, world-class physical and digital networks are
being created to enhance productivity, competitiveness, and ease of living. By strengthening connectivity,
logistics efficiency, and access to essential services, infrastructure is driving balanced regional
development and unlocking the growth potential of every region. This sustained infrastructure push will
be instrumental in transforming India into a globally competitive and self-reliant economy by 2047.
Joint Secretary, MoSPI, Shri Supreet Singh Gulati, in his welcome note, setting the agenda for the meet,
mentioned that a total of 221 central sector infrastructure projects, spanning 11 Central
Ministries/Departments with an original cost of Rs. 2.33 lakh crore were currently under implementation
in the North Eastern Region.In his opening remarks, Secretary, MoSPI, Dr. Saurabh Garg, reiterated the Government’s commitment to
strengthening institutional mechanisms for infrastructure monitoring and highlighted the role of MoSPI’s
Infrastructure and Project Monitoring Division (IPMD) and the PAIMANA – Project Assessment,
Infrastructure Monitoring and Analytics for Nation-Building portal in enabling data-driven
monitoring of Central Sector infrastructure projects costing ₹150 crore and above. He also mentioned
about the capacity building programmes conducted by MoSPI on Project Planning and Management and
encouraged State Governments to nominate officers associated with infrastructure development to
participate in these programmes.
During the meeting, reviews were undertaken for projects of the 11 Ministries/Departments. During the
review of MoRTH projects in the North Eastern States, 177 projects covering 3,634 km were
examined/reviewed. For the Ministry of Railways, nine ongoing projects were reviewed. NorthEast
Frontier Railway (NFR) is implementing rail connectivity projects in the North Eastern Region, where
difficult terrain, monsoon-dominated climate, limited working seasons, landslides, and remoteness pose
major execution challenges. Despite these constraints, NFR has expedited works, including the
inauguration of the Bhairabi–Sairang new line in Mizoram on 13.09.2025 and completion of 1,072 route
km of electrification. NFR requested State support for addressing issues related to encroachments, land
acquisition, law and order, and forest clearances to accelerate project execution.
For the Ministry of Power, nine projects were reviewed. While discussing the CSST and Distribution
System projects of Power Grid Corporation of India Limited (PGCIL) in Arunachal Pradesh and Sikkim,
issues included non-availability of contractors, local hindrances, and issues in assessment and
disbursement of compensation in Reserve Forest areas were highlighted. For the Tato-I Hydroelectric
Project (186 MW) of North Eastern Electric Power Corporation Limited (NEEPCO) issues including
transmission line completion and road connectivity constraints due to ongoing road upgradation works
were discussed.
For the Ministry of Petroleum and Natural Gas, 21 ongoing projects were reviewed. The Ministry
highlighted that certain projects in the North Eastern Region have faced implementation challenges due to
external supply disruptions and land-related issues, particularly for projects initiated during the COVID-19
period. Issues regarding the North East Gas Grid Project included pending land acquisition approvals and
administrative clearance for 33 km of pipeline were discussed. The recently inaugurated 2G Ethanol (Bio
Refinery) at Numaligarh, Assam, the world’s first 2G Bio-ethanol Plant using bamboo, was also
highlighted. It was emphasized that this project was a step towards energy “atmanirbharta” and also
aligned with the “annadata se urjadata” vision of the Hon’ble Prime Minister.
For the Ministry of Civil Aviation, three projects costing ₹ 2,534.26 crore were reviewed. Issues discussed
for the “Redevelopment of Imphal Airport” included highway closures and monsoon impacts, while issues
for the “Runway Widening at Pakyong Airport” related to land availability and construction of an alternate
access route. The Ministry requested continued State support for dumping excavated material.
For the Department of Telecommunications, two Projects costing ₹ 2227.45 crore were reviewed. It was
emphasized that while optical ground wire (OPGW) along power transmission lines is already enabling
bandwidth provision, coordinated development of power distribution and associated last-mile
infrastructure is essential to effectively strengthen telecommunications.
For the Department of Higher Education, seven projects amounting to ₹ 2,915.52 crore are under
implementation in the North Eastern Region. The Department submitted that the objective of establishing
one National Institute of Technology (NIT) in each State is to serve as a regional hub for technological
education and innovation.Also, the projects of the Department of Sports, Ministry of Coal, and the Ministry of Labour and
Employment were reviewed, and critical issues were discussed. Ministries/Departments/Implementing
agencies acknowledged and appreciated the support provided by the State Governments in facilitating
project execution.
Concluding the review meeting, Hon’ble Minister of State (Independent Charge), Rao Inderjit Singh
emphasized the importance of timely completion of infrastructure projects in the North Eastern Region for
strengthening connectivity, promoting inclusive growth, and supporting socio-economic development. He
urged all stakeholders to adopt a proactive and solution-oriented approach to resolve bottlenecks and
ensure faster project execution. He expressed confidence that, through sustained collective effort, the
Hon’ble Prime Minister’s vision of a prosperous, connected, and empowered North Eastern Region will be
realized, thereby making a meaningful contribution to the realisation of the national vision of Viksit
Bharat @2047.
The meeting concluded with a reaffirmation of the Government’s commitment to accelerating
infrastructure development in the North Eastern States through effective coordination, continuous
monitoring, and timely resolution of issues.
****
Samrat/