GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
R&B – Buildings – Construction of Seed Processing Plant / Godown at Nagavaram,
Wanaparthy Mandal (site location at Km 3/2-4 on Wanaparthy – Pebbair road Survey
No. 86 beside APTWR school for Girls at Wanaparthy in Mahaboobnagar District –
Extension of time for the Construction of Seed Plant / Godown – Complete the work with
in Five months - Accorded – Orders - Issued.
TRANSPORT, ROADS AND BUILDINGS (B.II) DEPARTMENT
G.O.Rt No. 100 Dated:01.02.2012
Read the following:-
1) From Sri Dr. Mallu Ravi, Ex-MLA, Jadcherla, Lr.Dt.18.11.2011 along
with letter of M/s Sri Sai Constructions addressed to the E-in-C(R&B),
Buildings.
2) From the E-in-C(R&B) Buildings, Hyd., Lr.No. TA9/AEE4/ 18969/2009,
Dt. 16.01.2012.
***
ORDER:
In the reference 1st read above, Sri Sai Constructions has requested for
extension of time till 31.03.2012 for the construction of Seed Plant/Godown at
Wanaparthy due to various reasons.
2) In the reference 2nd read above, the Engineer-in-Chief (R&B), Buildings,
Hyderabad has opined that revoking cancellation of work and extending time is not
desirable in the interest of the work.
3) Government after careful examination of the matter have observed that the
estimate contract value of the work is based on common SSR of 2008 – 09. If the
scheduled work is entrusted to another Contractor re tendering with revised SSR, there
will be financial loss to Government. Also, the Contractor has filed WP in Hon’ble High
Court recently. Further, the revised Estimates sent to Agriculture Department have not
yet been approved. If the scheduled work is entrusted another Contractor, it will be
completed by 31.08.2012 as per the time frame fixed by Agriculture & Co operation
Department and thereby a lot of time will be wasted and the purpose will not be served.
Therefore, Government have decided that the orders issued canceling the subject work
are revoked and the Contractor is given another opportunity which is final, with a
direction to complete the work within Five Months, so as to save time and money.
4) Accordingly, the Government hereby order for extension of time for the
Construction of Seed Plant / Godown and complete the work with in Five months to Sri
Sai Constructions.
5) The Engineer-in-Chief (R&B), Buildings, Hyderabad shall take necessary action
in the matter accordingly.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
S.P.SINGH
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Engineer-in-Chief (R&B), Buildings, Hyderabad.
The P.S. to Principal Secretary,
Agriculture & Cooperation Dept.
The Finance (Expr. PW) Dept.
Copy to:
The PS to Hon’ble Minister for Roads & Buildings,
A.P. Secretariat, Hyderabad.
SF/SC
//Forwarded: By Order//
SECTION OFFICER