GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
I&CAD Department – Minor Irrigation – West Godavari District – Construction
and Commissioning of Kopparru L.I. Scheme on Left Bank of Gonteru Drain in
Narasapuram (M), West Godavari District – administrative approval for
Rs.563.315 Lakhs - Orders – Issued.
IRRIGATION & CAD (MI.A) DEPARTMENT
G.O.Rt.No. 194 Dated:18-02-2012.
Read the following:-
1) From the VC & MD, APSIDC Letter No.IDC/MD/SE/Tech/
Matyapuri LI Scheme/11-12,/659, dated: 23.05.2011.
2) Govt. Letter No.12805/Minor-I/A1/2011-1, dated: 28.6.2011.
3) From the VC & MD, APSIDC, Hyderabad Lr.No.IDC/MD
SE/Tech/Matyapuri LIS /11-12/2136, dated:22.08.2011.
4) Govt.Letter No.12805/MI.A1/2011-2, dated: 02.11.2011.
5) From the VC & MD, APSIDC, Lr.No.IDC/MD/SE/Tech/
Matyapuri LIS/11-12/3276, dated:16.11.2011.
6) From the VC & MD, APSIDC, Lr.No.IDC/MD/SE/Tech/
Matyapuri LIS/11-12/4159, dated:10.01.2012.
7) From the VC & MD, APSIDC, Lr.No. IDC/MD/ Tech/Elr/
Matsyuapuri LIS-/2011-12/4483, dated: 30.01.2012.
<<<>>>
O R D E R:-
In the reference 1st read above, the Vice Chairman & Managing Director,
A.P. State Irrigation Development Corporation Limited, Hyderabad while
enclosing the estimates for Construction and Commissioning of Kopparru L.I.
Scheme on left bank of Gonteru Drain at Matsyapuri (V) in Narasapuram (M)
of West Godavari District for Rs.547.62 lakhs, to irrigate an ayacut of 3675
acres, he has stated that the Hydrological clearance was accorded by the ENC
(A.W), I&CAD, Hyderabad for utilization of 1.65 Cumecs on left bank of
Gonteru drain at KM 38.60 at Matsyapuri (V) in Narasapuram (M) of West
Godavari District and he has requested the Government for according
administrative approval for 547.62 lakhs under the State Plan funds of APSIDC
2010-2011 under Head of Account 4702-COL on Minor Irrigation –MH 101-
GH(11)-SH(15) L.I. Schemes -530-531 OE”.
2) In the reference 5th read above, the Vice Chairman and Managing
Director, A.P. State Irrigation Development Corporation Limited, Hyderabad
has stated that the labour component for the entire scheme is worked to 2.64%
(PTO)
::2::
in respect of L.I. Scheme under MGNREGP. The work of jungle clearance for a
value of Rs.5,500/- for the above L.I. Scheme could be taken up under
MGNREGP duly following the procedure. For the balance components the
labour component involved is 2.62% of total cost of L.I. Scheme works. The
quantities for formation of intake leading channels/pipelines, head works,
Pressure mains are usually more than 1000 cum having depth of excavation
ranging from 2m to 7m, hence such works can not be taken up manually.
Therefore he has requested the Government to accord administrative approval
for an amount of Rs.579.95 lakhs for Construction and Commissioning ofKopparru L.I. Scheme, on left bank of Gonteru Drain at Matyapuri (V) in
Narasapuram Mandal of West Godavari District under state plan funds duly
deleting Rs. 5,500/- for jungle clearance from the proposal.
3) Government after careful examination of the matter delete the
following provisions in this estimates.
Tank/Scheme component provision in sanctioned
estimates amount
Kopparru Audit charges Rs.4,56,000/- -
L.I. Scheme Operation & Maintenance
Charges ------------------- Rs. 60,000/- -
Evaluation & Monitoring
Charges ------------------ Rs.5,78,000/- -
Vetting of structural
designs ------------------ Rs. 1,00,000/- -
Non-Refundable fee
payable to SE/IC Eluru -- Rs.3,72,000/- -
Laying of foundation
stone and for inauguration Rs. 1,00,000/- -
4) Accordingly, Government hereby accord administrative approval for
Rs.563.315 lakhs (Rupees Five hundred sixty three lakhs thirty one thousand
and five hundred only) out of which Rs.563.26 lakhs shall be met out of
Normal State Funds available with A.P. State Irrigation Development
Corporation Limited, for Construction and Commissioning of Kopparru L.I.
Scheme, on left bank of Gonteru drain at Matsyapuri (V) in Narasapuram
Mandal of West Godavari District.
(Conted..Page...3)
::3::
5) The amount sanctioned in para ( 4 ) shall be debited under the Head
of Account “4702-MH-101-GH-11 NSP-SH(15) L.I. works – 530/531 OE”.
6) The Rural Development Department have agreed to include the
Jungle clearance work components under the shelf of project for taking up it
under MGNREGP. Hence expenditure for the remaining amount of Rs. 5,500/-
for the component of Jungle clearance shall be met from out of the MGNREGP
funds.
7) The Vice Chairman & Managing Director, A.P. State Irrigation
Development Corporation Limited, Hyderabad shall take further action
accordingly.
8) This orders issues with the concurrence of Finance (Expr.PW)
Department vide U.O. Note No.31589/981/A1/Exp.PW/2011, dated 7.12.2011
and PR & R D (RD) Department vide their U.O. No. 3516/RD-II/ A1/ 12,
dated:16.02.2012.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH.)Dr. PRASANTA MAHAPATRA
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Vice Chairman & Managing Director, APSIDC Ltd., Hyderabad.
The District Collector, West Godavari District.
Copy to :-
The Commissioner, Rural Development Department, A.P., Hyderabad.
The PS to Principal Secretary to Government, PR&RD Department,
The Accountant General A.P., Hyderabad.
The Director of works Accounts, MJ Road, Hyderabad.
The OSD to M (MI, APSIDC, L.I, WALAMTARI &GWD).
The Finance (Expr.PW1) Department.
The PS to Principal Secretary to Government (Irrigation).
The PS to Special Secretary to Government .
SF/SC.
//FORWARDED :: BY ORDER//
SECTION OFFICER