GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
APSIDC – Nalgonda District - Construction & Commissioning of L-16 LIS on NSLBC near
Pacharigadda H/O Dondavarigudem Village, Miryalaguda Mandal, Nalgonda District”–
Administrative Approval for Rs.406.50 lakhs – Accorded – Orders – Issued.
= = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = =
IRRIGATION & CAD (MI T) DEPARTMENT
G.O.Rt.No. 198 Date:18.2.2012
Read the following:-
1) From the Vice Chairman & Managing Director, APSIDC Ltd Letter
No.IDC/MD/SE/Tech/L-16 LI Scheme/11-12/2304, dated 6.9.2011
2) From the Vice Chairman & Managing Director, APSIDC Ltd Letter
No.IDC/MD/SE/Tech/L-16 LI Scheme/11-12/3465, dated 26.11.2011
@@@
ORDER:
In the letter 1st read above, The Vice Chairman & Managing Director, APSIDC Ltd
has submitted an estimate for the work “Construction & Commissioning of L-16 Lift Irrigation
Scheme on NSLBC near Pacharigadda H/O Dondavarigudem Village, Miryalaguda Mandal,
Nalgonda District” stating that the scheme is proposed for irrigating 1152 Acres as a
separate LI Scheme from the existing L-15 & L-16 Scheme which was commissioned during
1975, as the water is not reaching to tail end ayacut since last (10) years. The estimate is
prepared with current SSR 2011-12 with latest cement and steel rates to accord
administrative approval for Rs.420.00 lakhs under Normal State Plan funds of APSIDC for
the year 2011-12 under Head of Account “4702-101-11-15-530, 531”. Hence the VC & MD
has requested to accord administrative approval for Rs.420.00 lakhs for the above work
under Normal State Plan.
2. In the letter 2nd read above, the Vice Chairman & Managing Director, APSIDC Ltd
has stated that the work of site clearance and the works in approach road for a value of
Rs.80,780/- could be taken up under MGNREGP duly following the procedure. For the
balance components, the labour component involved is 1.38% of total cost of LI Scheme
works. The quantities for formation of intake leading channels / pipelines, head works,
pressure mains are usually more than 1000 cum having depth of excavation ranging from
2m to 5m. Hence such works could not be taken up manually. The working season for
execution of LI Scheme works will be 3 to 5 months only in a year as there is no provision
for land acquisition / compensation of crops etc in the estimates. All the LI Schemes are to
be completed within 2 years period. Hence, the VC & MD has requested to accord
administrative approval for Rs.419.19 lakhs for the above work under State Plans funds duly
proposing an amount for Rs.80,780/- for the component of site clearance & approach road
to be taken up the work under MGNREGP.
3. Government, after careful examination of the matter, revise estimate of the following:-
a) The financial provision for the following components has been restricted for
the above LI Scheme as per G.O. No.205, I & CAD (MI IV) Department, dated 3.12.2008 as
per details shown below:
Scheme Component Provision in Sanctioned
Estimate amount
L-16 LIS Survey & Rs.8,00,000/- Rs.4,03,200/-
Investigation
charges
(PTO)2
The following provisions in the estimates have been deleted.
Scheme Component Provision in Sanctioned
Estimate amount
L-16 LIS Audit charges Rs.3,28,000/- -
Operation & Maintenance Rs.1,80,000/- -
charges
Evaluation & Monitoring Rs.4,12,000/- -
charges
4. Accordingly, Government, after careful examination of the matter, hereby accord
administrative approval for Rs.406.50 lakhs (Rupees four hundred six lakhs and fifty
thousand only) for the work -“Construction & Commissioning of L-16 Lift Irrigation Scheme
on NSLBC near Pacharigadda H/O Dondavarigudem Village, Miryalaguda Mandal,
Nalgonda District”, Out of which an amount of Rs.405.69 lakhs shall be debitable to the
Head of Account “4702 COL on M.I. – MH 101 - GH 11 Normal State Plan – SH (15) – L.I.
works – 530 Major Works / 531 Other Expenditure”
5. The Rural Development Department have agreed to include the component of site
clearance and approach road under shelf of project for taking up it under MGNREGP.
Hence, the remaining amount of Rs.0.81 lakhs for the component of site clearance and
approach road shall be proposed under MGNREGP funds in consultation with Rural
Development Department
6. The Vice Chairman & Managing Director, APSIDC Ltd shall take further action
accordingly.
7. This order issues with the concurrence of Finance (Expr.PW) Department vide their
U.O.No.35158/1068/Expr.PW/A1/12, dated 9.1.2012 and PR & RD (RD) Department vide
their U.O.No.3513/RD.II/A1/2012, Dated 14.2.2012
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
Dr.Prasanta Mahapatra
Principal Secretary to Government
To,
The Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad
The District Collector, Nalgonda District.
Copy to:
The Commissioner, Rural Development Department.
The Accountant General, AP Hyderabad.
The Director of Works & Accounts, MJ Road, Hyderabad.
The OSD to M ( MI, APSIDC, LI, WALAMTARI & GWD)
The Finance (Expr.PW) Department
The PS to Principal Secretary to Government (Irrigation)
The PS to Principal Secretary to Government ,PR &RD(RD) Dept.
The PS to Special Secretary to Government
SF/SC
// FORWARDED: BY ORDER //
SECTION OFFICER