See Full Document Text
GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
R&B Department- Court Case- Contempt Case No. 159/2012, filed by
Sarva Smt. Namireddy Shakunthala & Others for non compliance of the
orders in WP.No.22860/2011, dated:03-11-2011 – Payment to deposit
of 50% decretal charges in respect of O.P.No.10/2005 on the file of
Senior Civil Judge, Miryalaguda – Revised Proposals submitted-
Sanction-Accorded - Orders – Issued.
TRANSPORT, ROADS AND BUILDINGS (R.IV) DEPARTMENT
G.O.Rt.No. 313 Dated: 26 .03.2012.
Read the following:
1. From the CCLA & Spl.CS to Govt. Lr.No.G1/403/2011,
dt:25-05-2011
2.From the CE(R&B) CRN & MD, APRDC, LrNo.823/
ENC(R&B)A&EAP/Phase-I/APSH2/06, dt:17.02.12
3.From the Collector, Nalgonda Dt, addressed to
CCLA, copy to Prl.Secy., R&B Dept. Fax MessageNo.G1
/8430/10, dt:18-2-2012
4.From the CCLA & Spl.CS to Govt. D.O.Lr.No.G1/403/2011,
dt:24-02-2012
5. From the GP for TR&B, HC of AP, Lr CCNo.159/2012 in
WPNo.22860/2011, TR&B, dt: 02-3-2012
6. From the Deputy Registrar, High Court of A.P. interim orders
dt.02-03-2012 in Contempt Case No.159/2012
7.From the CCLA & Spl.CS to Govt. Lr.No.G1/403/2011,
dt:09-03-2012
8.From the CE(R&B) CRN & MD, APRDC, LrNo.823/
ENC(R&B)A&EAP/Phase-I/APSH2/06, dt:16.03.12
***
ORDER:
In the letter 3rd read above, the District Collector, Nalgonda
District, has requested the Chief Commissioner of Land administration,
A.P. Hyderabad, to arrange to provide the funds for an amount of
Rs.13,77,13,665/- (Rupees Thirteen Crores seventy seven Lakhs
Thirteen Thousand six hundred and sixty five only) towards payment of
decretal charges in O.P.Nos.1/05, 2/05, 3/05, 4/05, 7/05, 8/05, 10/05,
15/05, 16/05, 17/05, 18/05, 44/05 as per interim orders dt:24.02.2010
of Hon’ble High Court to avoid personal appearance.
2. In the D.O. Lr. 4th read above, the Chief Commissioner of Land
administration and Spl. Chief Secretary to Govt., while enclosing a letter
dt.17-02-2012 of Government Pleader for Land Acquisition, wherein he
has informed that Smt. Namireddy Shakunthala & 4 others have filed
contempt case No. 159/2012 for non compliance of orders in WP
No.22860/2011 dt.03-11-2011 and that the Hon’ble Court has granted
two weeks time for reporting compliance of directions issued in the
orders of the High Court and he has also requested the Government to
comply with orders of the High Court on or before 01-03-2012 to avoid
personal appearance.
3. In the letter 7th read above, the Chief Commissioner of Land
administration & Spl. Chief Secretary to Govt., has stated that the
Collector, Nalgonda District in his letter dt: 22-2-2012, has submitted a
revised proposal, splitting the consolidated proposal submitted in the
letter dt: 07-2-2012, requested to sanction decretal charges for an
amount of Rs.29,49,685/- in respect of O.P.No.10/05 in which case
contempt case is filed.
PTO-2-
4. The Chief Commissioner of Land administration & Spl. Chief
Secretary to Govt., Hyderabad, while enclosing a copy of the letter of
Collector, Nalgonda has therefore requested the Government to
sanction to deposit of 50% decretal charges for an amount of
Rs.29,49,685/- in respect of O.P.No.10/05, as per the orders of Hon’ble
High Court Andhra Pradesh, dated: 02-3-2012 in Contempt Case
No.159/2012.
5. Government after careful examination of the matter, hereby accord
administrative sanction for release of an amount of Rs.29,49,685/-(
Rupees twenty nine lakhs forty nine thousand six hundred and eighty
five only) to deposit of 50% decretal charges in respect of
O.P.No.10/05 on the file of Senior Civil Judge, Miryalaguda, and as per
the orders of Hon’ble High Court Andhra Pradesh dated: 02-03-2012 in
Contempt Case No.159/2012.
6. The amount sanctioned in para ( 5 ) above, shall be met from the
Head of Account- 5054 - COL on Roads and Bridges – 04- District and
Other Roads - MH 800 Other Expenditure - GH 11- Normal State Plan -
SH(08) Other Roads – 530- Major Works - 532 Lands.
7. The Chief Engineer (R&B) CRN & Managing Director, A.P.Road
Development Corporation, Hyderabad, shall draw the amount
sanctioned at para (5) above and deposit the same in the Senior Civil
Judge, Miryalaguda, for realization of decretal amount in O.P.No.10/05
under intimation to the Government.
8. The Chief Engineer (R&B) CRN & Managing Director, A.P.Road
Development Corporation, Hyderabad, shall take further action
accordingly in the matter.
9. This order issues with the concurrence of Finance Department vide
their U.O.No.6881/276/A2/Expr.PWD/A2/2012, dated:19-03-2012.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
S.P.SINGH
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer (R&B) CRN & Managing Director,
A.P.Road Development Corporation, Hyderabad
Copy to:
The Government Pleader for TR&B, High Court of A.P., Hyderabad
The Chief Commissioner of Land administration &
Spl. Chief Secretary to Govt., A.P, Hyderabad
The District Collector, Nalgonda Distrct
The Accountant General, A.P, Hyderabad.
The Pay & Accounts Officer, Hyderabad.
The Finance (Expr.PW) Deptt.
PS to M(R&B)/ Prl.Secy., R&B
Sf/Sc.
//FORWARDED BY ORDER//
SECTION OFFICER