Ministry of Jal Shakti
STATUS OF STPs, EXPANSION OF RIVER
CLEANING, LiDAR MAPPING AND E-FLOW
COMPLIANCE
Posted On: 16 MAR 2026 6:18PM by PIB Delhi
Under the Namami Gange Programme, a total of 173 Sewage Treatment Plants (STPs) have been
commissioned and are currently operational as on January 2026, while in the meantime 8 more STPs
have been completed while 1 more STP is expected to be completed by 31st March. Ongoing projects
are closely monitored at multiple levels to ensure timely completion.
The mandate of the National Mission for Clean Ganga (NMCG) is to ensure effective abatement of
pollution and rejuvenation of the River Ganga by adopting a river basin approach. The primary focus is
to emphasize pollution abatement and conservation of the main stem of the Ganga River and its major
tributaries under the Namami Gange Program.
In order to expand the scope of river cleaning and adopt a basin-level and holistic approach, NMCG
facilitates & supports, the State Governments for rejuvenation of smaller rivers and tributaries within
the Ganga basin. In this regard, technical guidance and support are extended to the States, in
coordination with concerned departments, for planning and implementation of appropriate rejuvenation
measures.
Under the Namami Gange Programme, a total of 8 sewerage infrastructure projects has been taken up
with a treatment capacity of 280 Million Litres per Day (MLD) for the rejuvenation of Kali West and
Hindon rivers.
Under Namami Gange program advanced survey technologies like LiDAR, UAV and Drone based
Surveys etc. have been used for improved river basin management. A Drain Dashboard has been
developed to provide authentic videographic visualization and mapping of outfalls on Ganga mainstem.
The dashboard provides geo-tagged information and enables state and district-level authorities to
monitor pollution sources, prioritze interventions and respond effectively.
The Government of India vide Gazette Notification dated 9th October, 2018 notified the minimum
environmental flows for River Ganga that needs to be maintained at various locations on the river. As
per the notification, monitoring of e-flow is being carried out by Central Water Commission (CWC)
since 1st January, 2019. CWC is monitoring 11 projects and submits quarterly progress reports. As per
these reports, e-flow compliances have been noticed at most of the projects. In cases of non-
compliances necessary actions are taken.
The information was provided by THE MINISTER OF STATE FOR JAL SHAKTI SHRI RAJ
BHUSHAN CHOUDHARY in a written reply to a question in Rajya Sabha today.
***
ND(Rajya Sabha USQ 2634)
(Release ID: 2240872) Visitor Counter : 120