**Executive Summary**
This document is a notification from the Tamil Nadu Government Gazette, dated November 15, 2017, regarding the Tamil Nadu Transmission Corporation Limited's (TANTRANSCO) sanction for erecting transmission lines in the General Construction Circle, Coimbatore, to transmit and distribute power. The erection of a 110 KV DC line is detailed, and interested parties have one month from the publication date to submit representations regarding the scheme.
**Key Points / Main Content**
* **Transmission Line Erection:**
* TANTRANSCO has sanctioned the erection of transmission lines to meet additional power demands.
* The work will be taken up shortly.
* **Specific Project Details:**
* Erection of a 110 KV DC line on DC towers with Panther conductor.
* Purpose: Making LILO (Line In Line Out) of the existing Ponnapuram-Ingur 110 KV feeder-II.
* Location: At the proposed Thaneerpandal 110/33-11 KV SS (Substation).
* **Route Information:**
* Route Length: 3.375 Km.
* The line passes through the following Revenue Villages:
* Myladi
* Thaneerpandal
* Murungatholuvu
* Thenmugam Vellode
* District: Erode District, Perundurai Taluk
* **Representation Period:**
* Interested parties have one month from the publication date to submit representations on the scheme.
**Impact Analysis**
**Stakeholder: Tamil Nadu Transmission Corporation Limited (TANTRANSCO)**
* **Impact:** TANTRANSCO is responsible for carrying out the erection of the transmission lines.
* **Action Required:** To undertake the project.
**Stakeholder: General Public/Interested Parties**
* **Impact:** Potentially impacted by the construction of the new transmission lines.
* **Action Required:** Review the proposed scheme and submit representations within one month of the publication date if they have concerns, as per the Electricity Act 2003.
**Stakeholder: Residents of Myladi, Thaneerpandal, Murungatholuvu, and Thenmugam Vellode**
* **Impact:** Potentially affected by the transmission line passing through their revenue villages.
* **Action Required:** Review the proposed scheme and submit representations within one month of the publication date if they have concerns, as per the Electricity Act 2003.
Key Entities Referenced
Electricity Act 2003: Law referenced for addressing representations regarding the transmission line project.
Tamil Nadu Transmission Corporation Limited (TANTRANSCO): Entity responsible for erecting transmission lines to transmit and distribute power, as stated in the gazette notification.
Coimbatore: Location of the General Construction Circle of TANTRANSCO, overseeing the erection of transmission lines.
Tamil Nadu Government Gazette: Official publication containing notifications related to government activities, including infrastructure projects.