**Executive Summary**
This document is a final order from the Pension Fund Regulatory and Development Authority (PFRDA) regarding Alankit Assignments Ltd. & Ors. The order is issued under Sections 30 of the PFRDA Act, 2013 and PFRDA Regulations, 2015 and is in pursuance of an order from the Securities Appellate Tribunal (SAT) dated 15.02.2021. The Authority directs a fresh inquiry into the issue of delay in SCF upload and remittance of contributions.
**Key Points / Main Content**
* **Background:**
* The Securities Appellate Tribunal (SAT) directed the Authority to reconsider the matter in light of observations made in its order dated 15.02.2021 concerning Appeal No. 3 of 2019.
* The PFRDA is a statutory authority established under the PFRDA Act, 2013 to promote and develop an organized pension system.
* Alankit Assignments Ltd. (Noticee No. 1) was registered as a Point of Presence (PoP) and an Aggregator, but its application for renewal was rejected.
* The Authority received complaints regarding NPS Lite customers being cheated and initiated adjudication proceedings against Noticees for violations of the PFRDA Act and Regulations.
* The Whole Time Member (Finance) and Member-in-charge of imposition of penalty passed an order on 02.01.2019 holding the Noticees liable, which was challenged by Noticees, and quashed by SAT.
* **Hearing and Submissions:**
* A hearing notice was issued to the Noticees on 02.09.2021, and a personal hearing took place on 23.09.2021.
* The Noticees were given the opportunity to file written submissions, which they did on 28.10.2021.
* **Issues Under Consideration:**
* The central issue is whether the NSDL Circular, 2012 and APY Circular, 2015, if applicable, would alter the findings of the Adjudicating Officer and the earlier order dated 02.01.2019.
* **Arguments of the Noticees:**
* The Noticees argued that the imposition of penalty was not maintainable given the NSDL Circular, 2012, and the APY Circular, 2015.
* They also argued that the PFRDA (Aggregator) Regulations, 2015, were not applicable to the alleged violations as the Regulations for Aggregators under NPS-Lite, 2010, were in effect during the relevant period.
* The Noticees claimed that delays were due to delays in the generation of Permanent Retirement Account Numbers (PRAN) by the Central Recordkeeping Agency (CRA).
* The Noticees argued that the penalties were based on notional loss and not actual loss.
* Finally, the Noticees submitted that all the guidelines were followed by the Noticees and thus, no penalty can be imposed by the Authority.
* **Order:**
* The Authority directs a fresh inquiry into the issue of delay in Subscriber Contribution Form (SCF) upload and remittance of contributions in light of relevant Regulations/Circulars, including those mentioned in the SAT order, and the arguments of the Noticees.
**Impact Analysis**
**Alankit Assignments Ltd. & Ors. (Noticees)**
* **Impact**: The Noticees are directly impacted by the order, as the Authority will re-examine transactions related to SCF upload and remittance delays.
* **Action Required**: The Noticees may be required to provide additional information and participate in the fresh inquiry.
**Pension Fund Regulatory and Development Authority (PFRDA)**
* **Impact**: The Authority is directed to conduct a fresh inquiry, requiring allocation of resources and review of past transactions.
* **Action Required**: The Authority must re-examine transactions in light of relevant regulations and circulars.
Key Entities Referenced
Pension Fund Regulatory and Development Authority (PFRDA): Statutory authority that regulates and develops the pension sector in India and the primary entity involved in the matter.
PFRDA Act, 2013: The primary act governing the PFRDA, under which the current order is issued.
PFRDA (Procedure for Inquiry by Adjudicating Officer) Regulations, 2015: Regulations under which the inquiry and adjudication process are conducted.
Securities Appellate Tribunal (SAT): The appellate body whose order led to a reconsideration of the matter by the PFRDA.
Alankit Assignments Ltd.: The entity against whom the proceedings were initiated for alleged violations related to NPS contributions.
FINAL ORDER
BEFORE WHOLE TIME MEMBER (LAW) AND MEMBER AUTHORIZED TO
IMPOSE PENALTY
Under Sections 30, of the PFRDA Act, 2013 and PFRDA (Procedure for Inquiry by
Adjudicating Officer) Regulations, 2015
IN THE MATTER OF ALANKIT ASSIGNMENTS LTD. & ORS.
(Case No. PFRDA/17/06/16/0010/2017-SUP-AGGR)
1. Alankit Assignments Ltd.
Alankit House, 4E/2,
Jhandewalan Extension,
New Delhi – 110055 …Noticee No. 1
2. Shri Alok Agarwal,
CEO & Director,
Alankit Assignments Ltd.,
Alankit House, 4E/2,
Jhandewalan Extension,
New Delhi – 110055 …Noticee No. 2
3. Shri Mukesh Chandra Agarwal,
Wholetime Director,
Alankit Assignments Ltd.,
Alankit House, 4E/2,
Jhandewalan Extension,
New Delhi – 110055 …Noticee No. 3
4. Shri Yashjeet Basrar,
Wholetime Director,
Alankit Assignments Ltd.,
Alankit House, 4E/2,
Page 1 of 10Jhandewalan Extension,
New Delhi – 110055 …Noticee No. 4
5. Shri Harish Chandra Agarwal,
Executive Director / Compliance Officer,
Alankit Assignments Ltd.,
Alankit House, 4E/2,
Jhandewalan Extension,
New Delhi – 110055 …Noticee No. 5
CORAM
Shri Pramod Kumar Singh
Whole Time Member (Law)
and Member authorized to
impose penalty
ORDER
1. INTRODUCTION
1.1. The present order is being passed in pursuance to the order of the Securities Appellate
Tribunal (SAT) dated 15.02.2021 in the matter of Alankit Assignments Ltd. & Ors. v. Pension
Fund Regulatory and Development Authority (PFRDA Appeal No. 3 of 2019).
1.2. SAT in its aforementioned order directed the Authority to reconsider the matter in the light
of the observations made by SAT in the order.
2. BACKGROUND
2.1. Pension Fund Regulatory and Development Authority (PFRDA/ the Authority) is a
statutory authority established under Section 3 of the Pension Fund Regulatory and
Development Authority Act, 2013 (PFRDA Act, 2013) notified w.e.f. 01.02.2014 to be a model
regulator for promotion and development of an organized pension system to serve the old age
Page 2 of 10income needs of people on a sustainable basis and to regulate the National Pension System
(NPS) and other pension schemes mentioned therein.
2.2. Alankit Assignments Limited (Noticee No. 1) was registered as a Point of Presence (PoP)
on 10.03.2010 for a period of five years. Further, Noticee No. 1 was registered as an Aggregator
on 24.11.2010 for a period of three years which was further extended on 04.02.2014 and
20.11.2014.
2.3. The Authority in exercise of its power under Section 52 of the Act notified PFRDA (Point
of Presence) Regulations, 2015 (PoP Regulations) and PFRDA (Aggregator) Regulations, 2015
(Aggregator Regulations). Post notification of the said Regulations, Noticee No. 1 applied for
renewal of certificate of registration for PoP and Aggregator on 20.05.2015 and 09.07.2015,
respectively. However, during pendency of the said applications, the Authority received
complaint on 16.10.2015 that NPS Lite customers were being cheated by one Mr. B. Vijay
Kumar Reddy. Further, during the fact-finding process of the Authority it was found out that
the Noticee No. 1 was having association with Mr. B. Vijay Kumar Reddy. He was using NPS
Lite Collection Center (NLCC)/ Point of Presence - Service Provider (POP-SP) Code which
was allocated to Noticee No. 1. Moreover, he had deposited contributions of subscribers to the
NPS-Lite collection account of Noticee No. 1.
2.4. The Authority issued a show cause notice on 16.03.2016 followed by another show cause
notice on 20.10.2017 seeking explanation from Noticee No. 1 with respect to the complaints
received against Mr. B. Vijay Kumar Reddy and his association with Noticee No. 1.
2.5. After the reply of Noticee No. 1, the Authority decided to initiate adjudication proceedings
against Noticees for violation of provisions of the PFRDA Act and Regulations. After
adjudication, the Adjudicating Officer recommended a penalty of Rs. 9,00,590/- (Rupees nine
lakhs five hundred and ninety only), where penalty of Rs. 4,00,590/- (Rupees four lakhs five
hundred and ninety only) was imposed on Noticee No. 1 on account of delay in upload of
Subscriber Contribution Form (“SCF”) and delay in remittance of funds to the Trustee Bank
and a penalty of Rs. 1,00,000/- (Rupees one lakh only) was imposed on each of the Noticees
on account of the repetitive nature of the defaults on the part of the Noticees.
2.6. The Whole Time Member (Finance) and Member-in-charge of imposition of penalty
passed an order on 02.01.2019 holding the Noticees liable under all the charges, thus,
Page 3 of 10confirming the recommendations of the Adjudicating Officer. Further, the review application
of the Noticees were rejected by the Chairman, PFRDA on 21.02.2019.
2.7. The application of Noticee No. 1 for renewal of certificate of registration for PoP and
Aggregator were rejected by the Authority on 21.02.2019.
2.8. The Noticees filed Appeal No. 3 of 2019 whereby the order of the Whole Time Member
imposing penalty on the Noticees for violation of the provisions of the Act and Regulations
was challenged.
2.9. SAT in its order dated 15.02.2021 allowed the said Appeal and quashed the impugned
order dated 02.01.2019 passed by the Whole Time Member and Member authorized to impose
penalty with the following observations, referring to the Circular no.
CRA/PO&RI/FC/2012/012 dated 04.12.2012 issued by the National Securities Depository
Limited (NSDL Circular, 2012) and Circular no. PFRDA/2015/20/APY/1 dated 27.07.2015
issued by PFRDA (APY Circular, 2015):
“46. We are of the opinion that non consideration of the aforesaid two Circulars which
goes to the root of the matter with regard to the time line for uploading of the SCF and
transfer of funds to the trustee bank vitiates the impugned order. If these two Circulars
are considered the finding relating to the alleged delay in the uploading of the SCF and
in the remittance may not happen or may get drastically reduced.
47. Consequently on this short ground, we are of the opinion that the impugned order
cannot be sustained and it not necessary to go into the other issues raised in the show
cause notice or the AO‟s report or in the impugned order. In view of the aforesaid, the
impugned order cannot be sustained and is quashed.
48. For the reasons stated aforesaid, the impugned order dated 21st February, 2019 in
appeal no.1 of 2019, impugned order dated 21st February, 2019 in appeal no.2 of 2019
and the impugned order dated 2nd January, 2019 in appeal no.3 of 2019 cannot be
sustained and are quashed. All the appeals are allowed. The matter is remitted to the
authority to decide the applications for grant of registration afresh and if it is unable
to grant the registration of certificate it will grant conditional registration which would
be subject to the outcome to the penalty proceedings. The Designated Member/WTM is
Page 4 of 10directed to reconsider the matter in the light of the observations made aforesaid. In the
circumstances of the case, parties shall bear their own costs.”
3. HEARING NOTICE, PERSONAL HEARING AND REPLY
3.1. A Hearing Notice dated 02.09.2021 was issued to the Noticees under Section 30 of the
Pension Fund Regulatory and Development Authority Act, 2013 read with Regulation 11 and
12 of the Pension Fund Regulatory and Development Authority (Procedure for Inquiry by
Adjudicating Officer) Regulations, 2015. In the interest of justice, an opportunity of personal
hearing was granted to the Noticees on 23.09.2021.
3.2. The personal hearing was attended by Shri Abhishek Kumar, Advocate and Shri Kamal
Garg, Deputy General Manager, Alankit Assignments Ltd. representing Noticee No. 1, Noticee
No. 3, Noticee No. 4 and Noticee No. 5. Shri Alok Agarwal, Noticee No. 2, represented himself
in personal capacity.
3.3. The Noticees were also provided an opportunity to file their written submissions by
08.10.2021 which was further extended to 28.10.2021 based on the request of the authorized
representatives of the Noticees dated 07.10.2021. The written submission was filed by the
Noticees on 28.10.2021.
4. ISSUE UNDER CONSIDERATION
4.1. The limited issue under consideration in the present matter is whether the NSDL Circular,
2012 and APY Circular, 2015, if found applicable in the facts and circumstances of the present
case, would alter the findings of the Adjudicating Officer and the order dated 02.01.2019 of
the Whole Time Member (Finance) and Member-in-charge of imposition of penalty.
5. ARGUMENTS OF THE NOTICEES
5.1. The Noticees submitted that the imposition of penalty on account of delay in upload of
SCF and delay in remittance of funds to the Trustee Bank under the Regulations for
Aggregators under NPS-Lite, 2010 is not maintainable and was made in complete
contravention of the applicable Regulations and in ignorance of the NSDL Circular, 2012
which revised the Turn Around Time (TAT) for processing regular NPS and NPS Lite forms
and the APY Circular, 2015.
Page 5 of 105.2. It was further argued that the alleged violations on which penalty had been recommended
were for the period of 30.12.2013 to 04.02.2015 during which Regulations for Aggregators
under NPS-Lite, 2010 were applicable. Therefore, PFRDA (Aggregator) Regulations, 2015
shall not be applicable for these alleged violations. Further, the Noticees did not violate any
guidelines of the Regulations for Aggregators under NPS-Lite, 2010.
5.3. The Noticees submitted that the contributions of the subscribers can be uploaded only after
Permanent Retirement Account Number (PRAN) is generated by the Central Recordkeeping
Agency (CRA) as it is the only identity of the subscribers. Therefore, only after PRAN is issued
an aggregator can upload SCF on the CRA system and make corresponding remittance.
5.4. It was also submitted that the NSDL Circular, 2012 modified TAT for generation of PRAN.
The Noticees relied on the said Circular to further argue that “T” meant the date of receipt of
generation of receipt provisional/temporary by the CRA-FC Acceptance Centre, namely
generation of PRAN, i.e. to say the time starts from the date of receipt generation of the
subscribers’ number (PRAN).
5.5. The Noticees in their written submissions submitted that the Company uploaded the SCF
within T+4, i.e. Date of Generation of PRAN + 4 days and remitted the funds to the Trustee
Bank with within T+5 (excluding Saturdays and Sundays), i.e. Date of Generation of PRAN +
5 days (excluding Saturdays and Sundays and bank holidays).
5.6. The Noticees further submitted that the Adjudicating Officer considered “T” as the date
on which the subscriber visited the center and the receipt was generated, however, the
Adjudicating Officer should have considered date of generation of PRAN as “T”. The Noticees
submitted that the Authority (PFRDA) in the APY Circular, 2015 had defined “T” as the date
of generation of PRAN. The Noticees in their oral submissions had argued that if the two
Circulars were considered then the number of instances where SCF upload was delayed would
decrease from 5,781 to 32. Likewise, the number of instances where remittance transfer was
delayed would decrease from 5,554, to 155. However, in their written submissions, the
Noticees turned around and argued that if the two Circulars are considered then no delay will
be stablished in the uploading of SCF and in the remittances.
5.7. The Noticees also submitted that the Adjudicating Officer levied penalty based on notional
loss and not the actual loss suffered by any subscriber. Further, no complaint or evidence on
Page 6 of 10record is available to establish that the subscribers suffered loss due to the alleged delay.
Moreover, they submitted that any delay in uploading of SCF and in the remittances was due
to delay in generation of PRAN by CRA.
5.8. The Noticees also challenged the basis of calculation of notional loss and argued that there
was no provision in the Regulations for Aggregators under NPS-Lite, 2010 or the Operational
Guidelines for Aggregators which provided any provision for rate of imposition of penalty.
Further, the Noticees submitted that Para 13 of the Regulations for Aggregators under NPS-
Lite, 2010 provided PFRDA with the power to lay down provisions for imposition of penalty
but no such provisions were made by the Authority.
5.9. The Noticees also submitted that the Authority cannot impose penalty on Noticee 2 to
Noticee 5 under Section 28(4) of the PFRDA Act as they are not registered intermediaries of
PFRDA. Further, the Noticees submitted that the Noticee 2 to Noticee 5 cannot be held liable
under Section 50 of the PFRDA Act as the said noticees are only responsible for taking broad
policy decisions and the day-to-day affairs of the Company is looked after by qualified
executives who are appointed by the Company from time to time for conducting its business.
5.10. The Noticees finally submitted that all the guidelines were followed by the Noticees and
thus, no penalty can be imposed by the Authority.
6. CONSIDERATION OF ISSUES AND FINDINGS
6.1. I have carefully examined material on record as well as submissions made by the Noticees
in their oral submissions on 23.09.2021 along with the written submissions filed on 28.10.2021.
6.2. The present proceedings were conducted in compliance with the order of SAT dated
15.02.2021 whereby SAT directed the Whole Time Member and Member authorized to impose
penalty to reconsider the matter in the light of the observations made therein, i.e. whether the
findings in respect of delay in the uploading of the SCF and in the remittance of the contribution
of subscribers would hold if the Adjudicating Officer and the Member Authorized to Impose
Penalty would have considered the NSDL Circular, 2012 and the APY Circular, 2015.
6.3. In the present matter, the primary argument of the Noticees is that the order of the Member
Authorized to Impose Penalty dated 21.02.2019 is not maintainable as the Adjudicating Officer
as well as the Member failed to take into consideration the NSDL Circular, 2012 which had
Page 7 of 10modified the time period within which Noticee No. 1 was expected to upload SCF and remit
contribution of the subscribers to the Trustee Bank.
6.4. Noticee No. 1 was first issued certificate of registration under Regulation for Aggregators
under NPS-Lite 2010. Annexure II of the Guidelines in supplement to “Regulation for
Aggregators under NPS Lite-2010” provided conditions for remittance of subscriber
contribution amount to NPS Account. According to the said clause, “Data in respect of
contributions collected during the week must be uploaded on the CRA system on Friday before
EOD. Corresponding remittances must be credited to the NPS account held with Trustee bank
by the next Monday.” The said clause, thus, prescribed timelines for uploading of SCF and
remittances of contribution of the subscribers to their NPS account. The Adjudicating Officer
has relied on the aforementioned clause to consider a Turn Around Time (TAT) for SCF upload
to be T+4 and for remittance of contributions of the subscribers to the NPS account as T+5
(excluding Saturday, Sunday and bank holiday) which was the maximum TAT prescribed by
the aforementioned clause. The Noticees have argued that the said timelines were effectively
modified by the NSDL Circular, 2012. The Noticees have argued that the NSDL Circular, 2012
had revised TAT prescribed to Central Recordkeeping Agency-Facilitation Centre (CRA-FC)
with respect to processing of PRAN Application Forms during Peak (months of March and
April) and Non-Peak (months other than March and April) period, thus, modifying the timeline
for uploading of SCF and remittance of contribution of the subscribers to the NPS account.
This argument was based on the rationale that an Aggregator cannot perform its function of
SCF upload and remittance of contribution of subscribers without processing of PRAN
Application Form and creation of NPS account.
6.5. In the present matter, it is pertinent to consider information and fund flow in the NPS
architecture before considering the arguments of the Noticees. According to the Regulations
for Aggregators under NPS-Lite 2010, an Aggregator shall collect cash or cheque, as the case
may be, from the subscriber and issue a physical receipt as a form of acknowledgement. At the
same time the Aggregator shall send verified NPS Application Form to CRA-FC for
digitization, processing and generation of PRAN. Further, the Aggregator would prepare and
upload SCF in CRA-Lite system and accordingly transfer funds to Trustee Bank. Even
assuming that NSDL Circular, 2012 had changed the timeline for the activities to be undertaken
by the Aggregator, the argument of the Noticees can at best be said to be valid only vis-à-vis
the new subscribers where PRAN is yet to be generated.
Page 8 of 106.6. In case of existing subscribers, i.e. subscribers with existing PRAN, the NSDL Circular,
2012 shall not modify the timeline for SCF upload and remittance of contributions of the
subscribers. Thus, in cases where the Aggregator collected contributions from an existing
subscriber, the same should have been processed in accordance with Annexure II of the
Guidelines in supplement to “Regulation for Aggregators under NPS Lite-2010”. Thus, in case
of existing subscribers Data in respect of contributions collected during the week must be
uploaded on the CRA system on Friday before EOD. Corresponding remittances must be
credited to the NPS account held with Trustee bank by the next Monday.”.
6.7. In the light of the above observations and two Circulars referred in the order of the SAT,
the Noticees were asked to submit, before the undersigned, all the transactions under
consideration for the period subject to the investigation along with the date of PRAN
generation, SCF upload and remittance of contribution of the subscribers. Despite acceding to
the said instruction no such submission has been made by the Noticees till date. The
undersigned is of the view that the facts and evidences available on record are not sufficient to
adequately examine the submissions of the Noticees in light of the Circulars referred in the
order of the SAT. Further, the failure of the Noticees themselves to submit the relevant
information as was sought by the undersigned has constrained the undersigned from examining
the issue in its totality. Therefore, the undersigned is of the view that a relook of all the
transactions under consideration in the light of relevant Circulars including the Circulars
referred in the order of the SAT, if found applicable, for the period subject to the investigation
needs to be re-examined by the Authority under the first proviso of Regulation 11(3) of the
PFRDA (Procedure for Inquiry by Adjudicating Officer) Regulations, 2015.
6.8. Thus, the Authority shall get the impugned transactions in the present matter examined in
the light of relevant Regulations/Circulars including the Circulars referred in the order of the
SAT and the arguments advanced by the Noticees that the timeline for SCF upload and
remittance of contributions of the subscriber has been modified which in turn will either reduce
number of delays significantly or no such delay will be established.
7. ORDER
7.1. Having considered all the facts and circumstances of the case, the material available on
record and the submissions made by the Noticees, I, in exercise of the powers conferred upon
me under Section 30 of the PFRDA Act read with Regulation 11(3) of the PFRDA (Procedure
Page 9 of 10for Inquiry by Adjudicating Officer) Regulations, 2015 hereby direct the Authority for a fresh
inquiry in the issue of delay in SCF upload and remittance of contributions of the subscriber in
light of relevant Regulations/Circulars including the Circulars referred in the order of the SAT
and the arguments advanced by the Noticees.
7.2. In terms of the provisions of Regulation 12 of the PFRDA (Procedure for Inquiry by
Adjudicating Officer) Regulations, 2015, a copy of this order is being sent to the Noticees and
also to PFRDA.
-sd-
Pramod Kumar Singh
Whole Time Member
(Law) and Member
authorized to impose
penalty
Date : 02.05.2022
Place : New Delhi
Page 10 of 10