GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6318
ANSWERED ON 02ND APRIL, 2026
BHARATMALA PARIYOJANA PHASE-I
6318. SHRI DILESHWAR KAMAIT:
SHRI ARUN GOVIL:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् ग मंत्री
be pleased to state:
(a) the progress of the Bharatmala Pariyojana Phase-I as it nears
completion in March 2026 and the total length of access-controlled
high-speed corridors operationalised since 2014 till date;
(b) the impact of the Delhi-Mumbai Expressway and the Ganga
Expressway on reducing travel time and logistics cost for industrial
clusters in western and northern india including Western Uttar
Pradesh particularly in the Meerut region;
(c) the status of the Parvatmala (National Ropeways Development
Programme) in providing last-mile connectivity to high-altitude
pilgrimage sites in Uttarakhand and Himachal Pradesh; and
(d) whether the Government has conducted any assessment to
strengthen additional road connectivity keeping in view the
requirements of the developing industrial and export hubs in and
around Meerut and if so, the details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)(a) Bharatmala Pariyojana Phase-I was approved by the
Government in 2017, covering a length of 34,800 km across the
country at an estimated outlay of ₹5,35,000 crore. Under the
programme, projects covering a total length of 26,425 km have been
awarded, out of which 22,223 km has been constructed upto
February 2026. The length of operational access-controlled National
High-Speed Corridors (HSCs) / expressways has increased from 93
km in 2014 to 3,644 km as of February 2026.
(b) The Delhi–Mumbai Expressway is an access-controlled, high-
speed corridor aimed at facilitating efficient movement of
passenger and freight traffic across Western and Northern India,
including Western Uttar Pradesh. The corridor is expected to reduce
travel time between Delhi and Mumbai by about 50% (to 12–13 hours
from approximately 25 hours) for passenger vehicles and by about
51% (to 15–16 hours from approximately 32 hours) for commercial
vehicles. It also provides a reduction in travel distance of about
16% (from 1,424 km to 1,242 km), thereby improving overall route
efficiency.
The improved connectivity and reduction in travel time are
expected to enhance freight movement efficiency and support
logistics operations along the corridor and its influence areas.
The Ganga Expressway project is being implemented by the
Uttar Pradesh Expressways Industrial Development Authority
(UPEIDA) under the Government of Uttar Pradesh.
(c) The status of the Ropeway projects taken up under National
Ropeways Development Programme in the State of Uttarakhand and
Himachal Pradesh is as under:
S. Ropeway project Length Status / stage
State / UT
No. / Stretch Name (in km)
2.32 Project is being
Himachal
1 Bijli Mahadev reconsidered due to
Pradesh
local opposition.
Sonprayag to 12.9 The work has been
2 Uttarakhand
Kedarnath Awarded
Govind Ghat to 12.4 The work has been
3 Uttarakhand Hemkund Sahib Awarded
JiKathgodam- 14.9 Under DPR stage
4 Uttarakhand
Hanuman Temple
(d) Development of National Highways is a continuous process. The
Government assesses the requirement of road infrastructure,
including connectivity needs of emerging industrial and export hubs
across the country and projects are taken up based on the outcome
of Detailed Project Reports (DPRs), traffic demand, connectivity
requirements and synergy with PM Gati Shakti National Master Plan
(NMP).
*****