GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6339
ANSWERED ON 02ND APRIL, 2026
COMPENSATION FOR LAND ACQUISITION UNDER BHARATMALA
PARIYOJANA
6339. SHRI KARTI P CHIDAMBARAM:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् ग मंत्री
be pleased to state:
(a) the total land required and land acquired for projects under
Bharatmala Pariyojana since 2017 as on date, State-wise and
project-wise;
(b) the total compensation assessed and disbursed for such land
acquisition, State-wise and year-wise;
(c) the number of cases where compensation or rehabilitation and
resettlement payments remain pending beyond statutory timelines
under the Right to Fair Compensation and Transparency in Land
Acquisition Rehabilitation and Resettlement Act, 2013; and
(d) whether any review has been conducted on cost escalation in
bharatmala projects due to delays in land acquisition and the
project-wise extent of such escalation thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) The process for land acquisition for National Highway
(NH) projects are governed as per NH Act, 1956 and compensation
is determined as per provisions of Right to Fair Compensation andTransparency in Land Acquisition, Rehabilitation and Resettlement
(RFCTLARR) Act, 2013, as made applicable by Government. The
acquisition of land for National Highway projects is a continuous
process and the Competent Authority for Land Acquisition (CALA),
notified under Section 3(a) of NH Act, 1956, is responsible for the
payment of compensation. Further, there remains a time lag
between award and disbursement, due to various reasons including
disputes in ownership of the land, discrepancy in revenue records,
unwillingness of the beneficiary to receive the
disbursement/payment due to disputes on compensation etc. The
State wise details of land acquired under Bharatmala Pariyojana
during last 05 years by National Highways Authority of India (NHAI)
are annexed.
(d) Currently, as per the available data, 85 under construction
National Highways (NHs) projects including projects under
Bharatmala Pariyojana are delayed by more than three years,
attributable to various issues such as, bottlenecks relating to land
acquisition, statutory clearances / permissions, utility shifting,
encroachment removal, law & order issues, financial crunch
affecting implementation capacity of concessionaire / contractor,
poor performance of contractor / concessionaire, and Force Majeure
events such as Covid-19 pandemic, Change of Law, etc.
The Government has undertaken various initiatives to prevent
recurrence of delays and cost escalations. These include
streamlining and expediting land acquisition and compensation
using “BhoomiRashi” portal integrated with Public Finance
Management System (PFMS) and GIS-based Land Acquisition Plan,
revamping “Parivesh” Portal, to facilitate faster forest and
environmental clearances, enabling online approval of General
Arrangement of Drawings (GAD) of Road Over Bridge/ Road Under
Bridge (ROB/ RUB), and leveraging the mechanism of review and
resolution of bottlenecks / hindrances in ongoing projects, in active
collaboration with the State Governments and other stakeholders.
Government has also launched a web portal for Railway related
clearances with defined timelines for various approvals.The Government has put in place a strong framework using
multiple mechanisms for monitoring project progress and contractor
inefficiencies. Regular review meetings are conducted at various
levels with stakeholders to assess project progress, and critical
projects, such as those delayed by more than three years or pending
for award/ appointment. Cost escalation is not incurred in all
delayed projects. If delay is not attributable to the Contractor,
escalation is paid as per contract conditions, which may or may not
result in additional cost, depending upon final value of price
escalation determined on actual completion of project. If delay is
attributable to the Contractor, damages are imposed and there is no
additional cost due to delay.
Many State Governments conduct coordination meetings led by the
Chief Secretary to resolve issues affecting project execution.
Projects where issues remain unresolved are escalated for further
review through the Project Monitoring Group. As a result of the
above, no. of projects delayed by more than 3 years has come down
to 85 in February 2026.
The optimal alignment for a new project is approved by an
Empowered Committee keeping in view the viability of the project
after taking into consideration various factors such as the cost of
the land, the time period for acquisition etc.ANNEXURE REFERRED TO IN REPLY TO PART (a) TO (c) OF LOK
SABHA UNSTARRED QUESTION NO. 6339 ANSWERED ON 02ND
APRIL, 2026 ASKED BY SHRI KARTI P CHIDAMBARAM REGARDING
„COMPENSATION FOR LAND ACQUISITION UNDER BHARATMALA
PARIYOJANA‟.
State Wise Details of Land Acquisition for Project including under
Bharatmala Pariyojana by National Highways Authority of India
(NHAI) during last 5 years (2021-2026)
Acquired land during Last 05 Years
S. No. State
(Hectare)
1 ANDHRA PRADESH 5033.20
2 ASSAM 674.66
3 BIHAR 5274.88
4 CHHATTISGARH 976.45
5 DADRA & NAGAR HAVELI 2.36
6 DELHI 16.05
7 GUJARAT 2442.12
8 HARYANA 1832.60
9 HIMACHAL PRADESH 510.39
10 JAMMU & KASHMIR 632.37
11 JHARKHAND 4482.28
12 KARNATAKA 6292.26
13 KERALA 781.95
14 MADHYA PRADESH 6634.87
15 MAHARASHTRA 4779.82
16 MEGHALAYA 2.85
17 ODISHA 2602.28
18 PONDICHERRY 8.82
19 PUNJAB 5483.34
20 RAJASTHAN 1799.60
21 TAMIL NADU 1058.58
22 TELANGANA 4796.16
23 UTTAR PRADESH 7098.43
24 UTTARAKHAND 606.86
25 WEST BENGAL 2274.86
TOTAL 66098.03
*****