GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
RAJYA SABHA
STARRED QUESTION NO. 172
ANSWERED ON 09/03/2026
COMPLETION STATUS OF HOUSING PROJECTS UNDER PMAY-U
*172 DR. ASHOK KUMAR MITTAL:
Will the Minister of Housing and Urban Affairs be pleased to state:
(a) the reason for several housing projects under PMAY-U remaining incomplete in major cities,
the details thereof;
(b) the major reasons causing the delays in central assistance, the details thereof;
(c) the number of houses still pending under the 2022-25 target and the steps Government is
undertaking to meet the target; and
(d) the steps taken to ensure accountability of implementing agencies, the details thereof?
ANSWER
THE MINISTER OF HOUSING AND URBAN AFFAIRS
(SHRI MANOHAR LAL)
(a) to (d): A statement is laid on the Table of the House.STATEMENT REFERRED IN REPLY TO RAJYA SABHA STARRED QUESTION NO. 172
FOR 09.03.2026 REGARDING COMPLETION STATUS OF HOUSING PROJECTS UNDER
PMAY-U
(a) to (d): Ministry of Housing and Urban Affairs (MoHUA) has been implementing Pradhan Mantri
Awas Yojana - Urban (PMAY-U) since 25.06.2015 with an aim to provide all weather pucca houses
with basic civic amenities to all eligible urban beneficiaries across the country. Based on the learnings
from the experiences of implementation of PMAY-U, MoHUA has revamped the scheme and launched
PMAY-U 2.0 ‘Housing for All’ Mission with effect from 01.09.2024 for implementation in urban areas
across the country to construct, purchase and rent a house by 1 crore additional eligible beneficiaries
at affordable cost in next five years. PMAY-U 2.0 is implemented through four verticals i.e.,
Beneficiary Led Construction (BLC), Affordable Housing in Partnership (AHP), Affordable Rental
Housing (ARH) and Interest Subsidy Scheme (ISS).
As per the Scheme Guidelines of PMAY-U, Central Assistance is released to States/Union Territories
(UTs) in three instalments of 40%, 40% and 20%. The release of Central Assistance is incumbent upon
fulfilment of mandatory compliances by the concerned States/UTs viz. submission of Utilisation
Certificates (UCs), Aadhaar seeding of beneficiaries, Action Taken Report (ATR) on the
recommendations of Third Party Quality Monitoring Agencies (TPQMA), Geo-tagging of progress of
construction stages of houses/projects, registration of Affordable Housing in Partnership (AHP)/In-
Situ Slum Redevelopment (ISSR) projects under Real Estate (Regulation and Development) Act, 2016
(RERA), etc. and other instructions issued by Ministry of Finance. Due installments are released to
States/UTs based on compliances as per PMAY-U Guidelines. The scheme period of PMAY-U has
been extended up to 30th September 2026 for completion of under-construction houses and release of
funds through SNA-SPARSH module. At present sufficient funds are available under SNA-SPARSH
module.
Based on the project proposals submitted by States/UTs, a total of 125.15 lakh houses, including 13.67
lakh under PMAY-U 2.0, have been sanctioned by the Ministry, so far. Out of which, 116.57 lakh
houses have been grounded and 97.30 lakh are completed/delivered to the beneficiaries across the
country as on 02.03.2026. Central Assistance of ₹1.77 lakh crore has been released to
States/UTs/implementing agencies against the total sanctioned Central Assistance of ₹2.09 lakh crore.
The timeline for completion of houses/projects varies from State to State and it generally takes 12-36
months in different verticals of the scheme and as per Detailed Project Reports (DPRs) of respective
projects. The completion timeline for houses depends on various factors like availability of
encumbrance free land, statutory compliances for start of construction, arrangement of funds by
beneficiaries, availability of State share etc.
To ensure transparency and accountability, the Mission uses various measures in implementation of
the scheme. A comprehensive and robust MIS system has been developed which helps all stakeholders
to seamlessly manage information pertaining to physical and financial progress. The MIS is equipped
with Geo-tagging features and integrated with BHUVAN Portal of National Remote Sensing Centre
(NRSC) and BHARAT MAP of National Informatics Centre (NIC) for monitoring the progress of
construction of houses. MIS has also been integrated with UMANG Mobile App, NITI Aayog
Dashboard and DBT Bharat Portal for dissemination of information. To ensure that benefits go only to
the genuine beneficiaries, various linkages have been placed such as UIDAI for Aadhaar validation of
beneficiaries and GIS based Central MIS etc.
The Ministry conducts regular review with the States/UTs on progress of the scheme including timely
submission of compliances by States/UTs for subsequent release of Central Assistance and its
utilization for completion of the sanctioned houses within the stipulated timeline. The progress of the
scheme can also be accessed on the PMAY-U dashboard (https://dashboard.pmay-urban.gov.in).
*****