Home India ROAD TRANSPORT AND HIGHWAYS Parliament Question: Condition of NH between Jaguli, Nadia a...
Date: 2025-12-18 Category: Not Applicable State: Union Government Country: India

Parliament Question: Condition of NH between Jaguli, Nadia and Beldanga, Murshidabad

Issued by ROAD TRANSPORT AND HIGHWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document presents the Minister of Road Transport and Highways’ response to Unstarred Question No. 3033 regarding the condition of National Highway (NH) 12 between Jaguli, Nadia, Beldanga, and Murshidabad. The response acknowledges localized issues but states the highway is maintained in traffic-worthy condition under existing contract agreements. Widening to 4-lane in 5.5 km in Murshidabad district including in Beldanga is under progress with scheduled completion by July, 2026. **Key Points / Main Content** * **Condition of NH-12:** * Localized issues such as surface distress, pothole formations, and drainage deficiencies have been observed, and corrective action is being taken. * Barasat to Krishnanagar (66.7 km) stretch is developed to 4-lane on Engineering Procurement Contract (EPC) mode and maintained by the EPC Contractor under the Defect Liability Period (DLP). * Krishnanagar to Baharampore (67 km) stretch is developed to 4-lane on Build-Operate-Transfer (BOT) mode and maintained in traffic-worthy condition. * Widening to 4-lane in 5.5 km in Murshidabad district including in Beldanga is under progress with scheduled completion by July, 2026. * Kapa More is on Kalyani Expressway, a State Expressway not maintained by the Central Government. * **Accident Data:** * No separate accident data due to the poor condition of the specified stretch is available. * 209 accidents have been reported during the current year on the 160 km stretch between Barasat to Baharampore. * **Maintenance:** * Pre-monsoon maintenance, including pothole filling, patch repairs, and drain cleaning, was executed by the EPC Contractor/Concessionaire. * Repair and maintenance fall under the scope of the existing Contractor/Concessionaire Agreement. **Impact Analysis** **EPC Contractor/Concessionaire** * **Impact:** Responsible for maintaining the NH-12 stretch in traffic-worthy condition as per existing agreements and addressing identified deficiencies. * **Action Required:** Continue maintaining the road as per the contract, including addressing surface distress, potholes, and drainage issues. **Commuters/Public** * **Impact:** The completion of the 4-lane widening project will improve traffic flow and reduce travel time; however, ongoing maintenance may cause temporary disruptions. * **Action Required:** Be aware of possible disruptions due to ongoing maintenance and planned widening projects. **Central Government** * **Impact:** Responsible for the oversight and management of the project through the Ministry of Road Transport and Highways. * **Action Required:** Ensure the Contractor/Concessionaire fulfill their obligations and deliver the widening project by July 2026.

Key Entities Referenced

Ministry of Road Transport and Highways: The primary ministry responsible for the National Highway in question. National Highway (NH) - 12: The specific highway that is the subject of the question, particularly the section between Jaguli and Murshidabad. Jaguli: A location central to the applicability of the policy, located on NH-12 Nadia: A location central to the applicability of the policy, located on NH-12 Murshidabad: A location central to the applicability of the policy, located on NH-12
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 3033 ANSWERED ON 18TH DECEMBER, 2025 CONDITION OF NH BETWEEN JAGULI, NADIA AND BELDANGA, MURSHIDABAD 3033. MS. MAHUA MOITRA: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार् ग मंत्री be pleased to state: (a) whether the Government is aware of the poor State of the National Highway (NH) between Jaguli, Nadia and Beldanga, Murshidabad, particularly under the Road over Bridge (RoB) in Krishnanagar Road Station as well as Kapa More Mohanpur and if so, the details thereof; (b) whether any accidents have been reported due to the poor condition of this stretch of the NH and if so, the details thereof; (c) whether any pre-monsoon repair or maintenance work has been carried out in these stretches and if so, the details thereof; (d) whether any funds have been allocated towards repair and maintenance of this stretch and if so, the details thereof; and (e) whether a timeline has been fixed for the repair of this stretch of the NH and if so, the details thereof? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI)(a) Localised instances of surface distress, pothole formations and deficiency in drainage performance has been observed and corrective action has been initiated to restore pavement integrity and proper drainage functionality. The status of National Highway (NH) – 12 between Jaguli to Murshidabad is as under: (1) The stretch between Barasat to Krishnanagar passing through Jaguli and Nadia having a length of 66.7 km has been developed to 4-lane on Engineering Procurement Contract (EPC) mode. The stretch is maintained by EPC Contractor in traffic worthy condition under the Defect Liability Period (DLP) as per the contract agreement. The Road under Bridge (RUB) at Krishnanagar gets submerged during rainy season. However arrangement has been made to drain out the water. (2) The stretch from Krishnanagar to Baharampore with a length of 67 km has been developed to 4-lane on Build- Operate-Transfer (BOT) mode and is being maintained in traffic worthy condition. The section between Beldanga to Murshidabad falls in the above stretch. In addition, widening to 4-lane in 5.5 km in Murshidabad district including in Beldanga is under progress with scheduled completion by July, 2026. Further, Kapa More is on Kalyani Expressway, which is a State Expressway and not maintained by Central Government. (b) No accident data, due to poor condition of the stretch, is separately available. However, in the stretch between Barasat to Baharampore having a length of about 160 km, 209 accidents have been reported during the current year. (c) Pre-monsoon maintenance works, including pothole filling, patch repairs and drain cleaning, were executed by the EPC Contractor/Concessionaire. (d) & (e) The repair and maintenance works fall within the scope of the existing Contractor/Concessionaire as per the Contract/Concessionaire Agreement and the stretch is being maintained in traffic worthy condition accordingly. *****

Continue your research