**Executive Summary**
The document is a response to Lok Sabha Unstarred Question No. 2240, answered on February 12, 2026, addressing damage to roads, bridges, and expressways due to rainfall. It details the Government's efforts to maintain National Highways (NHs), reporting that 51 projects/stretches have experienced major damages due to rainfall during the financial year 2025-26. The document outlines quality control measures and actions taken against contractors for failures.
**Key Points / Main Content**
* **Responsibility for NH Development:** The Ministry of Road Transport and Highways (MoRTH) is primarily responsible for the development and maintenance of National Highways (NHs).
* **Damage Reporting:**
* 51 projects/stretches reported major damages due to rainfall during FY 2025-26, with state/UT-wise details and actions taken provided in the Annexure.
* **Quality Standards and Supervision:**
* NHs are constructed as per stipulated quality standards specified in Indian Roads Congress (IRC) specifications and codes.
* Consultants (Authority's Engineer/Independent Engineer) are appointed for day-to-day supervision.
* Executing agencies ensure adherence to quality requirements by contractors/concessionaires.
* **Defect Rectification and Monitoring:**
* Deficiencies are brought to the notice of concessionaires/contractors for corrective action.
* Government initiated monitoring of quality, including defect rectification, through a mobile-based application.
* **Additional Quality Control Initiatives:**
* Mandatory road condition assessments using Network Survey Vehicle (NSV).
* Analysis of high-resolution imagery from drone surveys integrated with AI/Machine Learning.
* Deployment of Mobile Quality Control Vans (MQCVs) in selected states.
* Deployment of Third-Party Quality Auditors for independent quality audits.
* Adoption of Automated & Intelligent/Machine-aided Construction (AI-MC) in NH projects.
* **Consideration of Environmental Factors:** Rainfall, flood levels, climate, and soil are considered during the Detailed Project Report (DPR) preparation.
**Impact Analysis**
**Ministry of Road Transport and Highways (MoRTH)**
* **Impact:** Responsible for development and maintenance of NHs, including implementing quality control measures and monitoring project progress.
* **Action Required:** Ensure adherence to quality standards, monitor projects closely, and take corrective actions when deficiencies are identified.
**Contractors / Concessionaires**
* **Impact:** Responsible for adhering to quality standards, rectifying deficiencies, and facing potential penalties for failures.
* **Action Required:** Implement quality control measures, respond to deficiencies promptly, and comply with contractual obligations.
**Field Officers / Engineers**
* **Impact:** Directly involved in efficient highway project management and monitoring of projects.
* **Action Required:** Utilize mobile-based applications for defect monitoring and rectification to ensure quality control.
**Authority Engineers / Independent Engineers**
* **Impact:** Responsible for day-to-day supervision of works at site.
* **Action Required:** Supervise the construction work to adhere to quality standards and specifications of the project.
Key Entities Referenced
Ministry of Road Transport and Highways (MoRTH): The primary government body responsible for the development and maintenance of National Highways in India.
National Highways (NHs): The core subject of the policy, referring to the nationally important roads and expressways under the Ministry's purview.
Indian Roads Congress (IRC): Organization that sets the specifications and codes for road construction in India, which are referenced in the policy.
Dadra and Nagar Haveli and Daman and Diu: Union Territory specifically mentioned due to construction projects and concerns regarding road quality and drainage.
Network Survey Vehicle (NSV): A mandatory assessment tool for road conditions on National Highways.
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2240
ANSWERED ON 12TH FEBRUARY, 2026
DAMAGE TO ROADS, BRIDGES AND EXPRESSWAYS DUE TO
RAINFALL
†2240. SHRI BHUMARE SANDIPANRAO ASARAM:
SHRI NILESH DNYANDEV LANKE:
DR. SHIVAJI BANDAPPA KALGE:
SMT. DELKAR KALABEN MOHANBHAI:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् ग मंत्री
be pleased to state:
(a) whether the Government maintains any data of the recent
incidents of damage caused to newly constructed roads, bridges
and expressways due to rainfall in various parts of the country and
if so, the details thereof;
(b) the number of such failures in infrastructure constructions
reported in the country, particularly in Maharashtra, UT of Dadra
and Nagar Haveli and Daman and Diu and other States/UTs during
the current financial year 2025-26, project and State/UT-wise along
with the reasons identified for these failures;
(c) whether any action including blacklisting or imposition of
penalties has been taken against the contractors or agencies found
responsible for the said failures and if so, the details thereof; and
(d) the steps being taken by the Government to ensure better
construction quality, drainage design and climate resilience in
future highway projects in the country particularly in the UT of
Dadra and Nagar Haveli and Daman and Diu?ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) The Government in Ministry of Road Transport and
Highways (MoRTH) is primarily responsible for development and
maintenance of National Highways (NHs).
Major damages in newly constructed NHs / National
Expressways, including structures (like bridges etc.) thereon, due to
rainfall, have been reported for 51 projects / stretches during the
current Financial Year (FY) 2025-26, State / Union Territory (UT) –
wise details of which along with action taken are at Annexure.
(d) All efforts are made to ensure that the National Highways
(NHs), including for the UT of Dadra and Nagar Haveli and Daman
and Diu, are constructed as per stipulated quality standards
specified in the Indian Roads Congress (IRC) specifications and
codes. To ensure that highway construction adheres to stipulated
quality standards, Consultants [Authority’s Engineer (AE) /
Independent Engineer (IE)] are appointed by the executing agencies
for day-to-day supervision of works at site. Officials of executing
agencies undertake inspections from time to time and ensure
adherence of conformity of quality of the work done by the
Concessionaire / Contractor with stipulated requirements.
Deficiencies observed, if any, are brought to the notice of the
Concessionaires/ Contractors for taking up necessary corrective /
remedial actions as stipulated in technical schedules of the
Contract/ Concession Agreement or within a reasonable period as
decided by the executing agency / AE / IE.
The Government in Ministry of Road Transport and Highways
has initiated monitoring of the quality including defect rectification
in NHs projects through mobile based application. This facilitates
efficient highway project management by the internal stakeholders
(Field officers / Engineers / Contractors / Concessionaires) directlyfrom onsite, through digital reporting of daily and monthly defects,
submission of geo-tagged and time-stamped photos for inspections
and digital uploading of test results.
The Government has taken the following additional initiatives
for improvement of quality control systems in implementation of
NHs works, some of which are as stated below: -
i. Mandatory assessments of road conditions through Network
Survey Vehicle (NSV) before start of work, before issue of
completion certificate and thereafter at regular intervals of six
months after completion of the work, thereby enabling quality
assessment of NHs at regular intervals for (a) ensuring the
maintenance during Concession period / DLP and (b)
prioritizing maintenance requirements to maintain NHs in
traffic worthy condition. NSV system for road condition
assessment has further been revamped using analytics for
enforcement of contractual provisions during Operation and
Maintenance (O&M);
ii. Analysis of High-Resolution Imagery collected from Drone
Surveys in Drone Analytics Monitoring System (DAMS)
integrated with Artificial Intelligence / Machine Learning
algorithms for periodic evaluation of progress and quality of
ongoing NHs works from time to time;
iii. Deployment of Mobile Quality Control Vans (MQCVs) equipped
with Non-Destructive Testing Equipment on pilot basis in four
States, namely in Gujarat, Rajasthan, Odisha and Karnataka,
for diagnostic assessments of overall health and quality of
works from time to time during project implementation
phases. Decision has been taken to diversify this initiative in
some more States;
iv. Deployment of Third Party Quality Auditors for independent
quality audits of NH works on a case-to-case basis;v. Adoption of Automated & Intelligent / Machine-aided
Construction (AI-MC) in NH projects.
Aspects of rainfall, high flood level, climate, type of terrain,
soil category etc. are invariably taken into consideration during
preparation of Detailed Project Report (DPR) for all NH development
/ upgradation projects. Accordingly, construction of roadside lined /
unlined drains, Cross Drainage structures viz., Culverts, Minor &
Major bridges across natural streams / drainage etc., are carried out
as per scope of contract for the project by the Contractor /
Concessionaire as per standard specifications and Indian Roads
Congress (IRC) codes.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (c) OF LOK SABHA UNSTARRED QUESTION NO. 2240
ANSWERED ON 12.02.2026 ASKED BY SHRI BHUMARE SANDIPANRAO ASARAM, SHRI NILESH DNYANDEV
LANKE, DR. SHIVAJI BANDAPPA KALGE AND SMT. DELKAR KALABEN MOHANBHAI REGARDING DAMAGE
TO ROADS, BRIDGES AND EXPRESSWAYS DUE TO RAINFALL
State / UT – wise details of major deficiencies / damages reported in newly constructed NHs / National
Expressways, including structures (like bridges etc.) thereon, due to rainfall, during the current FY 2025-26
along with action taken: -
S.
State Project / Stretch Name Details of Major damages / defects Action Taken
No.
Ruts, cracks and surface deformation / Distress was Show Cause Notice issued to Contractor. Based on Expert
Gujarat 1 Sanchore-Santalpur Package-4 (NH-754A) observed after rains in June 2025; severe rutting at team report, Contractor directed for rectification of damaged
some locations. location. Rectification work under progress.
Kullu Manali connected by temporary restoration; traffic plying
in 2 lane; Manali Bypass connectivity restored. Bids for
2 Kiratpur-Manali section (NH Nos. 205, 154, 03) 15.165 km damaged
permanent restoration of 9 Nos. locations received and for
other locations bids invited.
3 Parwano-Solan-Shimla section (NH-5) 0.68 km damaged Landslide removed from all locations and traffic is through.
Shimla- Mataur section (NH Nos. 205, 103, 03, Temporary restoration completed. Permanent restoration
4 2.595 km damaged
Himachal 503) completed except at 2 locations.
Pradesh Temporary restoration works completed. Permanent restoration
5 Pathankot-Mandi section (NH-154) 2.165 km damaged
works taken up.
6 Banikhet - Chamba – Bharmour (NH-154A) 13.5 km damaged Traffic through. Permanent restoration works taken up.
7 Sainj – Luhri – Aut (NH-305) 21.38 km damaged Traffic through. Permanent restoration works taken up.
8 Theog – Hatkoti (NH-705) 9.35 km damaged Traffic through.
9 Shimla – Rampur -Wangtoo-Kaurik (NH-5) 38.75 km damaged Traffic through. Permanent restoration works taken up.
10 Snail – Hatkoti (NH-707) 3.16 km damaged Traffic through. Permanent restoration works taken up.
11 Mcleodganj – Dharamshala (NH-503) 1.56 km damaged Traffic through. Permanent restoration works taken up.S.
State Project / Stretch Name Details of Major damages / defects Action Taken
No.
12 Bankhandi – Bhota (NH-503A) 0.23 km damaged Traffic through. Permanent restoration works taken up.
13 Hamirpur-Karnohal-Kalwahn-Mandi (NH-3) 11.08 km damaged Traffic through. Permanent restoration works taken up.
Land slides, settlement & sinking of roads, culverts Temporary restoration works completed; Traffic movement
14 Domail-Katra-Reasi-Bhamla road (NH-144)
damage, damage to protection walls restored.
Sinking of road, damage to protection walls, culverts Temporary restoration works completed; Traffic movement
15 Akhnoor-Poonch road (NH-144A)
and lined drains restored.
100m road washed away, affecting 220 m diversion
Temporary restoration works completed; Traffic movement
16 Chenani- Sudhmahadev road (NH-244) road constructed by cutting hill side. Breast wall,
restored. Permanent restoration works in progress.
drains, retaining walls damaged in 2.066 km.
Due to extensive landslide, Retaining Wall & Carriage Temporary restoration works completed; Traffic movement
17 Batote to Thathri section (NH-244)
way damaged. restored. Permanent restoration works in progress.
Due to extensive landslide, Retaining Wall & Carriage Temporary restoration works completed; Traffic movement
18 Thathri-Drabshalla- Chatroo section (NH-244)
way, box culvert damaged. restored. Permanent restoration works in progress.
Due to extensive landslide, Protection work / Road
19 Chatroo-Sinthantop- Vailoo section (NH-244) Permanent restoration works completed.
surface damaged.
Due to extensive landslide, Retaining Wall & Carriage Temporary restoration works completed; Traffic movement
20 Goha-Khellani road (NH-244)
way damaged. restored. Permanent restoration works in progress.
Jammu &
(i) Damage to three spans of the RHS 2 lane Devak
Kashmir
bridge due to settlement of two piers.
(ii) Damage to abutment and RHS span bridge on
Ravi river Temporary restoration works completed; Permanent restoration
21 Pathankot – Jammu section (NH-44)
(iii) Damage to three spans of LHS 2 lane bridge at works in progress.
Khaderu.
(iv) Scouring and Damage to apron/ floor protection
of bridges.
Massive land slides at Batra Hospital, Sidhra, Temporary restoration works completed; Permanent restoration
22 Jammu - Udhampur section (NH-44)
Nagrota, Bann, Jhajjar Kotli and Sangoor. works in progress.
Abutment and bridge span damaged at Tharad.
Udhampur - Chenani section (NH-44) Temporary restoration works completed; Permanent restoration
23 RCC Retaining wall and road carriageway fully
works in progress.
damaged at Balia Nala.
Approach of tunnel is damaged and chocked with Temporary restoration works completed; Permanent restoration
24 Nasri- Ramban section (NH-44)
muck. works in progress.
25 Ramban- Banihal section (NH-44) The valley side retaining wall has been damaged. Permanent restoration works completed.S.
State Project / Stretch Name Details of Major damages / defects Action Taken
No.
Unprotected soil slip in the cut section with debris Rectification work carried out and traffic restored with
26 Neeleshwaram-Thaliparambha Section of NH-66
deposition on carriageways. precautionary barricading in median portion.
Six laning from start of Valanchery bypass to Debarment of Contractor and Independent Engineer firm from
Kerala
Kappirikkad section of NH – 66 (old NH-17) from participating in ongoing/future bidding for 01 month period or
27 RE wall collapsed
Design Ch. 298+500 (Ex. km 304.250) to Design completion of investigation by the expert Committee whichever
Chainage 335+850 (Ex. km 349.260) is later.
During construction period, due to ingress of water on
account of unprecedented rainfall, the shoulder and Show Cause notice issued to Contractor; also, Quality Audit of
28 Balaghat-Gondia section of NH 543
high embankment failed leading to visible defects in the section caried out through independent Auditor.
pavement layers.
During heavy rains, ingress of water resulted in
29 Jhansi-Khajuraho (Pkg-1) section of NH-39 failure/collapse of RE wall at Chainage 61+100 (LHS) Show Cause notice issued to Concessionaire.
of the ROB.
Madhya
During construction stage, sudden collapse of earth
Pradesh
mass at crown of under construction tunnel portal at
Km. 32+630 led to casualty of 02 workers; the
30 Tejajinagar - Balwara Section of NH-347BG Show Cause notice issued to Concessionaire.
preliminary study/examination has indicated that
design failures/incomplete works followed with heavy
rains have resulted in failure.
RE wall buldging led to collapse of 02-03 panel of A-1 Risk and Cost Notice issued to Contractor. Rectification works
31 Gwalior Shivpuri Section of NH-3
(LHS) of RE wall approaches of ROB at Km 109+900 under progress.
Approaches to certain minor bridges washed out;
32 Udgir -Ravi-Degloor section of NH-63 Temporary restoration work completed. Traffic is through.
Bridge return wall and wearing surface damaged.
Left & Right side road earthwork & subgrade side
Shoulder swept away due to flood. Existing Cross
33 Osmannagar to Kundral (NH-161A) Temporary restoration work completed. Traffic is through.
Drainage Work and road length heavily damaged due
Maharashtra to overtopping due to heavy flood.
Ghat portion on Fulsawangi to Mahur section on Landslide in ghat portion. Severe erosion noticed to
34 Temporary restoration work completed.
NH 752I the road carriageway. Damage to the existing HPC.
Existing Minor Bridge overtopped due to heavy flood.
Existing realignment section. Necessary repair work done.
35 Tiruka bridge on NH-50 Minor bridge towards Udgir side Approach Road
earthwork & subgrade, side Shoulder swept awayS.
State Project / Stretch Name Details of Major damages / defects Action Taken
No.
due to flood. Minor Bridge Railing & bridge wearing
Course swept away due to flood.
Landslide in Karanji ghat section; complete damage
Rehabilitation and Upgradation of NH-61 from end
to approach road embankments at various bridges
36 of Ahmendnagar Bypass to Kharawandi Kasar Temporary restoration work completed. Traffic is through.
and culverts, severe damage to side shoulders and
(Section of Km 232+000 to 284+000)
development of numerous potholes.
Km 137.000 to 147.000, 150.000 to 152.800,
37 156.000 to 160.000 & 211.600 to 217.700 of NH- Washed out BT stretch, water logging. Flood Damage Repair work approved.
160A
1 Pier of Minor Bridge damaged on upstream side of
38 Buldhana Khamgaon (NH-753E) Rectification work through maintenance contractor.
river; also bulging of existing piers.
Due to heavy rain, Land slide occurred & Potholes
39 Mahad to Raigad Fort Road of NH-166F Flood Damage Repair work approved.
were observed.
Ch. 191.980 Km to 192.060 Km (Near Phesama Subsidence zone triggered; sunk for about 22 m in a
Nagaland 40 Damaged road portion restored through maintenance contract.
Village) of NH-02 between Kohima and Mao length of 110-150 m.
Major bridge over river Ravi damaged due to
Jalandhar - Pathankot/ J&K Border section of NH-
Punjab 41 excessive discharge of flood water from Ranjit Sagar Traffic through. Permanent restoration works taken up.
44
Dam and Madhopur barrage.
Construction of 6-lane access-controlled
Greenfield highway from km 28+70 to Km. 53+0 (i) Damage of Rs. 50.00 Lakhs imposed upon the Contractor.
Deficiencies in riding quality and settlement at some
Rajasthan 42 of Sangariya (near Chautala)-Rasisar (near (ii) Two key personnel of Authority Engineer team were
locations observed
Bikaner) section of NH-754K as a part of terminated due to poor supervision.
Amritsar-Jamnagar Economic Corridor
43 Limchigad Bridge (NH-34) Bridge Collapse 100 Ft Bailey Bridge launched.
Kalgadi Bridge, km 238, Ramnagar-Pauri Section
44 Bridge Collapse 45 m Bailey Bridge Installed
of NH-309
Uttarakhand Tamak bridge, Km 41.050 on Suraithota-Malari
45 Bridge Collapse Temporary diversion constructed.
Road (NH-107B)
Pangti Bailey Bridge at Km 52.75 on the
46 Bridge Collapse New bridge is already under construction
Joshimath-Malari Road (NH-107B)S.
State Project / Stretch Name Details of Major damages / defects Action Taken
No.
Sinking of 500 m road at Km 1.5 and 500 m road at Temporary restoration completed. Landslide treatment work
47 Rudraprayag – Gaurikund (NH-107) Km 35.99 due to heavy rainfall & river erosion on executed at Km 35.99. DPR under preparation for Landslide
valley side treatment work at Km 1.5.
Dharali (Km 19.00 to Km 19.400), Harshil (Km
23.4 to Km 24.00), Sonagad (Km 46.850),
Balkandar (Km 46.200), Dabrani (Km 48.050), Temporary restoration completed. Permanent restoration works
48 Road sinking, wash out
Limchigad (Km 53.5), Papadgad ( Km 67.00), under progress.
Bhatwari (Km 69.100), Maneri (Km 87.00) of NH-
34
Temporary restoration completed through construction of
49 Jeevan Ashram (km 139) of Nh-707A 150 mtr road washed out diversion road. DPR under preparation for Landslide treatment
work.
Penalty of Rs. 14.693 Lakh imposed on Concessionaire for
50 Berhampore – Farakka Section of NH-12 Potholes, cracking, rutting, edge breaking etc.
breach of maintenance obligation of Berhampore Bypass
West Bengal After the occurrence of the landslide, Contractor was directed
51 Sevoke – Rangpo section of NH-10 Road sinking and landslide to immediately mobilize required machinery to the damaged
site and carry out necessary repair works.
*****