Parliament Question: Delay in Construction of National Highway in Maharashtra

Issued by ROAD TRANSPORT AND HIGHWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document contains the answer to Unstarred Question No. 1081 in Lok Sabha, answered on February 5th, 2026, regarding delays in National Highway construction in Maharashtra. The Minister of Road Transport and Highways provides data on construction progress over the past five years, reasons for project delays, and steps taken to expedite stalled projects. The target for 2025-26 is 990 km of NH construction. **Key Points / Main Content** * **Construction Progress:** * Provides year-wise details of NH construction length in Maharashtra from 2020-21 to 2025-26 (up to Dec 2025), with 2870 km constructed in 2020-21 and 552 km constructed till Dec 2025. * Sets a target of 990 km for NH construction in Maharashtra for the year 2025-26. * **Reasons for Delays:** * Delays are attributed to Right of Way (ROW) disputes, land acquisition issues, forest and wildlife clearances, utility shifting, pre-construction activities, and contractor cash flow problems. * Pending issues have been substantially resolved, and delayed projects are targeted for completion within revised timelines. * **Government Initiatives for Timely Completion:** * Streamlining and expediting land acquisition through "Bhoomirashi" portal and GIS-based Land Acquisition Plan. * Revamping "Parivesh" Portal for faster forest and environmental clearances. * Enabling online approval of General Arrangement Drawings (GAD) for Road Over Bridge/Road Under Bridge (ROB/RUB) from the Railways. * Leveraging the review and resolution of bottlenecks mechanism in collaboration with State Governments. * Railways has launched a web portal for Railway related clearances with defined timelines. * **Monitoring and Resolution Mechanisms:** * Strong framework using multiple mechanisms for monitoring project progress and contractor efficiencies. * Regular review meetings at various levels with stakeholders. * Liquidated damages imposed against contractors for delays, including contract termination. * State Governments conduct coordination meetings led by the Chief Secretary. * Unresolved issues are escalated through the Project Monitoring Group and "PRAGATI". **Impact Analysis** **Stakeholder: Ministry of Road Transport and Highways** * **Impact:** Required to monitor project progress, resolve bottlenecks, and ensure timely completion of NH projects in Maharashtra. * **Action Required:** Continue implementing the initiatives outlined in the response, monitor progress, and address unresolved issues through the established mechanisms. **Stakeholder: Contractors** * **Impact:** Subject to stricter monitoring, potential penalties for delays, and possible contract termination if performance is unsatisfactory. * **Action Required:** Improve efficiency, address cash flow issues, and comply with revised project timelines. **Stakeholder: State Government of Maharashtra** * **Impact:** Needs to collaborate with the Union Government to resolve land acquisition and clearance issues. * **Action Required:** Actively participate in coordination meetings, facilitate land acquisition, and expedite clearances. **Stakeholder: Railways** * **Impact:** Responsible for timely approval of ROB/RUB General Arrangement Drawings (GAD) and Railway related clearances. * **Action Required:** Utilize the new web portal for Railway related clearances and adhere to defined timelines for approvals.

Key Entities Referenced

Maharashtra: The state where National Highway construction delays are being addressed. Bhoomirashi: Portal used for streamlining land acquisition for NH projects. Parivesh: Portal used for facilitating faster forest and environmental clearances. Ministry of Road Transport and Highways: The primary ministry responsible for national highway construction. National Highways: Subject of the construction and delays, impacts scope.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 1081 ANSWERED ON 5TH FEBRUARY, 2026 DELAY IN CONSTRUCTION OF NATIONAL HIGHWAY IN MAHARASHTRA 1081. SMT. SUPRIYA SULE: SHRI MOHITE PATIL DHAIRYASHEEL RAJSINH: Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) whether the Union Government has taken note of the reported slowdown in National Highway construction in Maharashtra, including the total length constructed during the last five years, year-wise and the progress achieved in 2024-25 vis-à-vis the targets fixed for 2025-26; (b) whether major highway, expressway or corridor projects in the State have been delayed or stalled and if so, the project-wise reasons, cost overruns and revised timelines; (c) whether the impact of land acquisition delays, financing constraints, contractor capacity issues and pending clearances has been assessed; and (d) the steps taken to expedite stalled projects, improve coordination with the State Government, ensure timely fund release and mitigate adverse effects on employment, rural connectivity and industrial logistics in Maharashtra? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI) (a) The details of the target set and achievement for construction of National Highways (NHs) in Maharashtra during the last five years is as under:Financial Year Length of NHs constructed in Maharashtra 2020-21 2870 2021-22 1534 2022-23 1087 2023-24 1463 2024-25 1203 2025-26 (upto Dec 2025) 552 The target for 2025-26 for length of NH constructed in Maharashtra is 990 km. (b) to (c) There have been delays in completion of some NH projects due to existing Right of Way (ROW) disputes, delays in land acquisition, forest as well as wildlife clearances, delays in utility shifting and other pre- construction activities as well as cash flow issues with some of the Contractors. All the pending issues have been substantially resolved and these delayed projects are targeted for completion within the revised timelines in a phased manner. (d) In order to ensure timely completion of NH projects, the Government has undertaken various initiatives. These include streamlining and expediting land acquisition using “Bhoomirashi” portal and GIS-based Land Acquisition Plan, revamping “Parivesh” Portal to facilitate faster forest and environmental clearances, enabling online approval of General Arrangement Drawings (GAD) of Road Over Bridge/Road Under Bridge (ROB/RUB) from the Railways, and leveraging the mechanism of review and resolution of bottlenecks / hindrances in ongoing projects, in active collaboration with the State Governments and other stakeholders. Railways has also launched a web portal for Railway related clearances with defined timelines for various approvals. The Government has put in place a strong framework using multiple mechanisms for monitoring project progress and contractor inefficiencies. Regular review meetings are conducted at various levels with stakeholdersto assess project progress, and critical projects, such as those delayed by more than three years or pending for award / appointment. In addition to this, liquidated damages have been imposed against the Contractors for delays attributed to the Contractors including termination of the Contract and awarding the balance works at risk and cost of the previous Contractors. Further, many State Governments conduct coordination meetings led by the Chief Secretary to resolve issues affecting project execution. Projects where issues remain unresolved are escalated for further review through the Project Monitoring Group and “PRAGATI”. *****