GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO-6229
ANSWERED ON 2nd APRIL, 2026
Development of Multi-Modal Logistics Parks under Bharatmala
Pariyojana
6229. Shri Alok Sharma:
Shri Krishna Prasad Tenneti:
Shri Lavu Sri Krishna Devarayalu:
Shri Captain Brijesh Chowta:
Shri Damodar Agrawal:
Shri Tejasvi Surya:
Shri Manoj Tiwari:
Shri Gopal Jee Thakur:
Shri Shankar Lalwani:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state :
(a) the number of Multi-Modal Logistics Parks planned under the
Bharatmala pariyojana and the number of projects currently under
development or operational, State/UT-wise including project-wise
for Karnataka;
(b) the locations identified for development of prioritised Multi-
Modal Logistics parks and the status of project implementation at
these sites including at Bengaluru;
(c) the framework adopted for selection of concessionaires and
execution of Multi-Modal Logistics Parks projects including the roleof model concessionaire agreements and standard bidding
documents;
(d) the extent of multimodal connectivity being integrated with the
logistics parks including linkages with rail, highways, ports and
inland waterways;
(e) the details of expected capacity of these parks in terms of cargo
handling and their role in improving logistics efficiency and reducing
transportation costs; and
(f) the investment and the expected outcomes of the multi-modal
logistics parks in Bengaluru?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) 4 nos. of Multi Modal Logistic Park (MMLP) Projects have been
taken up for development on Public Private Partnership (PPP) mode
at Chennai, Indore, Bengaluru and Nagpur under Bharatmala
Pariyojana. The Bharatmala Pariyojana has been discontinued since
November, 2023. The work of MMLP at Bengaluru, Chennai and
Indore are under implementation. The MMLP at Nagpur work was
terminated on account of concessionaire's default and the same has
been re-awarded on 18.03.2026.
(b) Government has so far prioritized 15 No. of locations (including
Bengaluru) for development of MMLPs, of which 6 Projects are under
implementation, Detailed Project Report (DPR) is in progress for 8
projects while DPR preparation is to be taken up for one project.
The location-wise details are annexed.
(c) MMLPs are being developed on Public Private Partnership (PPP)
mode following Design, Build Finance, Operate and Transfer
(DBFOT) model. The bidding is carried out through e-tendering using
the approved Request for Proposal (RFP) and approved Model
Concession Agreement (MCA).(d) Every Multi-Modal Logistics Parks (MMLPs) is being planned to
be developed as integrated logistics hubs with connectivity through
road and rail primarily but may also include waterways, wherever
feasible, to ensure seamless and efficient freight movement through
appropriate mode to other parts of the country.
(e) The capacity of a Multi Modal Logistics Park (MMLP) is
determined during the Detailed Project Report (DPR)/ project
implementation stage through market studies.
MMLP Development is planned to be developed in phases based on
land availability, ensuring scalability while balancing throughput
and storage requirements. The capacity expressed in Million Metric
Tons per Annum (MMTPA), is optimized with due consideration to
connectivity with key corridors such as access-controlled
highways/expressways and the Dedicated Freight Corridor, as well
as overall financial viability. The capacity of awarded MMLP
projects, in terms of total cargo volumes to be handled across all
modes in the horizon year, is annexed.
(f) The total investment for MMLP Bengaluru is Rs.1769.70 Crore
including Concessionaire cost of Rs.935.90 Crore and Authority
share of Rs. 833.80 Cr. At present MMLP Bengaluru is under
implementation and expected outcomes in terms of reducing
transportation, inventory and transaction costs, improving thereby
overall supply chain performance could be assessed once it is
completed and operationalized.ANNEXURE REFERRED IN REPLY TO PARA (b) & (e) OF THE LOK
SABHA UNSTARRED QUESTION NO. 6229 FOR ANSWER ON 2nd
APRIL 2026 REGARDING "DEVELOPMENT OF MULTI-MODAL
LOGISTICS PARKS UNDER BHARATMALA PARIYOJANA".
Sr.No. MMLP Cargo Status
location Capacity
estimated by
Authority in
MMTPA
1 Chennai 7.17 Under implementation
2 Indore 12.79 Under implementation
3 Bengaluru 29.46 Under implementation
4 Nagpur 9.47 Original work terminated; work
reawarded on 18.03.2026.
5 Jogighopa -- Area development work done on
Engineering Procurement
Mode(EPC) mode; Bid for partial
construction, Operation &
Maintenance to be invited
6 Jalna -- Rail terminal with rail
connectivity pre-existed on site
obtained from Jawaharlal Nehru
Port Authority (JNPA) for
development of Dry Port; other
facilities developed on EPC mode
by NHLML; Bid for Operation &
Maintenance awarded in March,
2025
7 Nashik -- DPR completed; project at
Appraisal stage
8 Patna -- DPR completed; project at
Appraisal stage
9 Anantapur -- DPR completed; project at
Appraisal stage
10 Hyderabad -- DPR completed; project at
Appraisal stage11 Varanasi -- DPR completed; project at
Appraisal stage
12 Pune -- DPR in progress
13 Coimbatore -- DPR in progress
14 Silchar -- DPR in progress
15 Vizag -- DPR is being initiated
* MMTPA-Million Metric Tons per Annum
*****