This document is the Indian government's response to Unstarred Question No. 173 in the Lok Sabha, answered on January 29th, 2026, regarding the development of NH-744 in Kollam Lok Sabha Constituency. The government states that it has taken up the Detailed Project Report (DPR) for the road's development and outlines the progress on three separate stretches. The final decision on project implementation will depend on DPR finalization, wildlife clearance, traffic density, and PM-Gatishakti principles.
**Key Points / Main Content**
* **DPR Progress for NH-744 in Kollam Lok Sabha Constituency:**
* The DPR is being prepared with a corridor-based approach in three packages.
* **Edamon-Kadambattukonam (39 km):** DPR has been completed.
* **Edamon-Aryankavu (21 km):** DPR is at the final feasibility stage.
* **Aryankavu-Puliyurai (2.3 km):** DPR is at the feasibility stage; statutory clearances (Forest, Wildlife, Environmental) are being processed. This stretch falls partly in Tamil Nadu.
* **Project Implementation Decision:**
* After finalization of the DPR and receipt of wildlife clearance, the decision on project implementation will be based on traffic density and synergy of the project with the principles of PM-Gatishakti.
**Impact Analysis**
**Stakeholder: Landowners whose land was notified for the development of NH-744**
* **Impact:** Landowners are facing hardship due to notification and delay in compensation disbursement.
* **Action Required:** No action mentioned in the document.
**Stakeholder: Residents/Commuters of Kollam Lok Sabha Constituency and Tamil Nadu (Aryankavu-Puliyurai stretch)**
* **Impact:** Improved road infrastructure and connectivity upon project completion.
* **Action Required:** No action required unless mentioned later.
**Stakeholder: Government agencies involved in statutory clearances (Forest, Wildlife, Environmental)**
* **Impact:** Required to process statutory clearances for the Aryankavu-Puliyurai stretch.
* **Action Required:** Need to process the statutory clearances promptly.
**Stakeholder: Ministry of Road Transport and Highways**
* **Impact:** Responsible for overseeing and implementing the NH-744 development project.
* **Action Required:** Need to finalize DPRs, secure wildlife clearances, and evaluate project based on traffic density and PM-Gatishakti principles to decide on project implementation.
Key Entities Referenced
NH-744: The national highway that is the subject of the development proposal.
Detailed Project Report (DPR): The report being created to plan the development of NH-744.
Ministry of Road Transport and Highways: The ministry responsible for the development of NH-744.
Kollam Lok Sabha Constituency: The specific area in which the development of NH-744 is focused.
PM-Gatishakti: A national master plan for multi-modal connectivity, used as a principle for project implementation.
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 173
ANSWERED ON 29TH JANUARY, 2026
DEVELOPMENT OF NH-744
173. SHRI N K PREMACHANDRAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् ग मंत्री
be pleased to state:
(a) whether the Government proposes to initiate action for the
development of NH-744 in a time-bound manner in Kollam Lok Sabha
Constituency, if so, the details thereof;
(b) whether the Government has fixed any time target for granting
approval for the development of NH-744 in Kollam Lok Sabha
Constituency, if so, the details thereof;
(c) whether the Government has initiated any action for
disbursing compensation to landowners whose land was notified for
the development of NH-744, if so, the details thereof;
(d) whether it has come to the notice of the Government that
landowners are facing hardship due to the said notification and
delay in disbursement of compensation, if so, the details of action
taken thereon; and
(e) whether the Government has initiated action for completion of
the Detailed Project Report (DPR) of NH-744 in Kollam Lok Sabha
Constituency in a time-bound manner and if so, the details of action
taken thereon?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (e) Government has taken up Detailed Project Report (DPR)
for NH-744 in the Kollam Lok Sabha Constituency. The DPR is beingprepared with corridor-based approach in three packages, and
progress is as follows:
i. For Edamon-Kadambattukonam (39 km) stretch, DPR has been
completed.
ii. For Edamon-Aryankavu (21 km) stretch, DPR is at the final
feasibility stage
iii. For Aryankavu-Puliyurai (2.3 km) stretch, which falls partly in
Tamil Nadu, DPR is at the feasibility stage, and statutory
clearances including Forest, Wildlife and Environmental
Clearances are being processed.
After finalization of DPR and receipt of wildlife clearance, the
decision on project implementation would be taken based on traffic
density and synergy of the project with the principles of PM-
Gatishakti.
*****