Parliament Question: Greenfield Expressway Connecting Bengaluru and Chennai

Issued by ROAD TRANSPORT AND HIGHWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document is the response of the Minister of Road Transport and Highways to Unstarred Question No. 1142 in the Lok Sabha, answered on February 5, 2026. The question concerned the status of the Greenfield Expressway connecting Bengaluru and Chennai, particularly delays in the Arakkonam-Kanchipuram stretch. The response addresses the reasons for the delays and the proposed action plan. **Key Points / Main Content** * **Arakkonam-Kanchipuram Stretch Delays:** * Work on the Arakkonam-Kanchipuram stretch (25.5 km) has been stopped since May 2025. * Only 11 km of the 25.5 km stretch has been completed. * The primary cause for the delay is financial constraints faced by the Concessionaire. * **Expressway Commissioning:** * As it's a greenfield corridor project, the expressway can only be commissioned once all packages are completed. This includes the Arakkonam-Kancheepuram stretch. * **Action Plan:** * The National Highways Authority of India (NHAI) issued a notice of intention to terminate the Concessionaire on November 10, 2025, and a Speaking Order on January 8, 2026, as per Court direction. * Senior Lenders have proposed to substitute the Concessionaire (letter dated January 20, 2026). * Following the substitution of the Concessionaire by Senior Lenders, the remaining work will be completed. **Impact Analysis** **Stakeholder: Commuters / General Public** * **Impact:** Delays in the Arakkonam-Kanchipuram stretch impact the overall commissioning timeline of the expressway, causing traffic congestion and economic disruption in the Kanchipuram district. * **Action Required:** Expect delays until a new Concessionaire is in place and the remaining work is completed. **Stakeholder: National Highways Authority of India (NHAI)** * **Impact:** NHAI is responsible for overseeing the project and addressing the Concessionaire's failure to meet the project milestones. * **Action Required:** NHAI has issued notice of intention to terminate the Concessionaire and is working towards substituting the Concessionaire in accordance with Court direction and the Senior Lenders. **Stakeholder: Senior Lenders** * **Impact:** The Senior Lenders have a financial stake in the project and are taking action to ensure its completion. * **Action Required:** Substitute the Concessionaire so that the balance work can be completed. **Stakeholder: Concessionaire** * **Impact:** Responsible for construction, but experiencing financial constraint. * **Action Required:** The Concessionaire will be substituted.

Key Entities Referenced

Greenfield Expressway connecting Bengaluru and Chennai: The subject of the parliamentary question, concerning delays in its construction. Ministry of Road Transport and Highways: The ministry responsible for the project and answering the parliamentary question. National Highways Authority of India (NHAI): The authority involved in the concession and potentially terminating the contract. Arakkonam–Kanchipuram: The specific stretch of the expressway experiencing significant delays. Tamil Nadu: The state where the delayed Arakkonam-Kanchipuram stretch of the expressway is located.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 1142 ANSWERED ON 5TH FEBRUARY, 2026 GREENFIELD EXPRESSWAY CONNECTING BENGALURU AND CHENNAI 1142. SHRI SELVAM G: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) whether the Government is aware that while most sections of the four-lane access-controlled greenfield expressway connecting Bengaluru and Chennai are nearing completion, the Arakkonam– Kanchipuram stretch in Tamil Nadu has witnessed significant delays, with only about 11 km completed out of 25.5 km and if so, the details thereof; (b) whether the delay in this stretch is adversely affecting the overall commissioning timeline of the expressway and causing traffic congestion and economic disruption in Kanchipuram district and if so, the details thereof; (c) the reasons for the slow progress in the Arakkonam–Kanchipuram section including issues relating to railway overbridges, land acquisition or inter-agency clearances; and (d) the time-bound action plan proposed to be taken by the Union Government to complete the remaining works and ensure full operationalisation of the expressway at the earliest? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI) (a) In respect of Arakkonam – Kancheepuram stretch (25.5 Km), work has stopped since May 2025 due to financial constraints of theConcessionaire. Subsequent to intention to terminate notice to the Concessionaire by National Highways Authority of India (NHAI) dated 10.11.2025 and Speaking Order dated 08.01.2026 of NHAI as per Court direction, Senior Lenders have proposed to exercise their right to substitute the Concessionaire vide letter dated 20.01.2026. (b) Being a Greenfield Corridor Project, the Expressway can be commissioned only on completion of all the Packages, including Arakkonam – Kancheepuram stretch. (c) Main reason for slow progress of Arakkonam – Kancheepuram section is financial constraints faced by the Concessionaire. As on date, no other issue is affecting the project. (d) Subsequent to substitution of the Concessionaire by Senior Lenders, the balance work shall be taken up and completed. *****