GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6249
ANSWERED ON 2ND APRIL, 2026
IMPLEMENTATION OF PARVATMALA PARIYOJANA IN TELANGANA
6249. SHRI ARVIND DHARMAPURI:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the objectives, scope and implementation framework of the
Parvatmala Pariyojana for development of ropeway infrastructure in
the country;
(b) the details of ropeway projects identified, approved and under
implementation across the country, State-wise along with their
present status and timelines;
(c) whether the locations in Telangana have been identified or
proposed under the Parvatmala Pariyojana and if so, the details
thereof including the present status; and
(d) the process and criteria followed for selection, approval and
execution of ropeway projects under the scheme and the expected
timeline for inclusion and completion of future projects?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)(a) The National Ropeways Development Programme, namely
Parvatmala Pariyojana, was announced by the Government in Union
Budget 2022-23 with an aim to develop alternative mobility systems
across the country to improve connectivity and convenience for
commuters in hilly regions and to decongest urban areas where
conventional transport is not feasible, while promoting safe,
sustainable and efficient last-mile connectivity and boosting tourism.
(b) The details are enclosed at Annexure.
(c) & (d) Government of Telangana has requested for the sanction of
three ropeway projects at the pilgrim/tourist locations in Telangana.
Execution of the ropeway projects is carried out by National Highways
Logistics Management Limited (NHLML) in partnership with the
concerned State/UT Government through the signing of a Ropeways
Development Agreement (RDA). Timelines for inclusion and completion
of projects are project-specific and depend upon the readiness of
proposals, statutory clearances and other associated factors. The
NHLML has initiated the process for the appointment of consultant for
the preparation of Detailed Project Report for three projects.
The investment decision and implementation of the ropeways projects
are prioritised based on technical feasibility, socio-economic benefits,
fulfilment of the criteria, the requirement for connectivity, and
financial viability.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (b) OF THE LOK SABHA
UNSTARRED QUESTION NO. 6249 ANSWERED ON 2ND APRIL, 2026
ASKED BY SHRI ARVIND DHARMAPURI REGARDING
IMPLEMENTATION OF PARVATMALA PARIYOJANA IN TELANGANA.
The details of projects identified, approved and under implementation across the country under
National Ropeways Development Programme:
S. Name of Ropeway project/ Length (in Status Tentative Completion
No. State/UT Stretch Name km) Date
Uttar Varanasi Cantt to 3.85 Under June -2026
1
Pradesh Gowdolia Chowk implementation
Uttar 2.2 Under April-2027
2 Sangam Prayagraj
Pradesh implementation
Himachal 2.32 Under **
3 Bijli Mahadev
Pradesh implementation
Madhya Mahakaleshwar 1.76 Under **
4
Pradesh Temple, Ujjain implementation
Madhya Tikitoriya Mata 0.15 Under July-2027
5
Pradesh Temple implementation
0.88 Under March-2027
6 Haryana Dhosi Hill
implementation
1.05 Under bidding 2 years from the
Jammu and Shankaracharya
7 Appointed Date of the
Kashmir Temple
Concessionaire
Sonprayag to 12.9 Awarded May-2032
8 Uttarakhand
Kedarnath
Govind Ghat to 12.4 Awarded May-2032
9 Uttarakhand
Hemkund Sahib Ji
Ramtek Gad 0.64 Under bidding 1.5 years from the
10 Maharashtra
Temple Appointed Date
Kamakhya Devi 1.43 Under bidding 1.5 years from the
11 Assam
Temple Appointed Date
Pegalwadi to 3.93 Under DPR stage -
12 Maharashtra
Brahmagiri
Tawang Monastery 5.15 Under DPR stage -
Arunachal
13 to P.T. Tso Lake at
Pradesh
Tawang
Kathgodam- 14.9 Under DPR stage -
14 Uttarakhand
Hanuman Temple
15 Gujarat GIFT City 2.4 Under DPR stage -
** Project is being reconsidered due to local opposition.
*****