GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
RAJYA SABHA
UNSTARRED QUESTION NO. 3415
ANSWERED ON 23/03/2026
IMPLEMENTATION OF PM E-BUS SEWA IN PATNA
3415. SHRI AKHILESH PRASAD SINGH
Will the Minister of Housing and Urban Affairs be pleased to state:
(a) whether Patna has been included under the PM e-Bus Sewa scheme launched to promote electric
public transport in urban centres;
(b) the number of electric buses sanctioned, delivered and operational in Patna under the scheme since
2023;
(c) the financial assistance provided by the Centre for charging infrastructure, depot modernisation and
operational subsidies; and
(d) the steps taken to ensure long-term financial sustainability, reduction of urban air pollution and
improvement in last-mile connectivity in the State capital?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) to (c): Under the PM-eBus Sewa Scheme, which aims to augment city bus operation in urban areas,
150 e-buses have been sanctioned to Patna city along with financial support for associated
infrastructure. Delivery and operations of e-buses is dependent on completion of associated
infrastructure which consists Civil Depot infrastructure and Behind-the-Meter (BTM) Power
infrastructure which is the responsibility of the concerned State Government. At present, Civil Depot
and BTM infrastructure work has not been completed. Therefore, as of now no e-buses has been
deployed under the Scheme. The details of the buses and associated infrastructure project sanctioned
for Patna city under the Scheme are given at Annexure-I.
(d): Urban Transport is a part of Urban planning which is a State subject. Therefore, respective
State Governments are responsible for planning, execution and management of urban transport system
including financial planning of resources, steps for reduction in urban air pollution and mobility plan
of the city. However, Government of India has issued National Urban Transport Policy 2006, Metro
Rail Policy 2017, Transit Oriented Development (ToD) Policy 2017 and other policy guidelines for
planning of sustainable urban transport system. Central Government has sanctioned Patna Metro Rail
project with route length of 32.5 KM at the cost of ₹13,365.77 crore and at present about 3 Kms metro
rail stretch is operational. Apart from above, 100% Central Financial Assistance (CFA) for
undertaking the activities relating to preparation of Comprehensive Mobility Plan (CMP)/Detailed
Project Report (DPR)/Research studies etc. is provided to the cities under a sub-scheme head namely
“Transport Planning and Capacity Building in Urban Transport for metro and non-metro projects”
*****ANNEXURE-I
Details of the buses and associated infrastructure project sanctioned for Patna city under the
Scheme as on 16.03.2026
Buses Amount sanctioned (₹ in crores)
City Sanctioned Depot
BTM CDI
ISBT Bairiya
11.71 -
Patna 150
Parivahan Parisar
19.23 3.96
Total
30.94 3.96
BTM: Behind-the-Meter Power Infrastructure
CDI: Civil Depot Infrastructure