GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3351
ANSWERED ON 12TH MARCH, 2026
LANDSLIDES AND ACCIDENTS ON NATIONAL HIGHWAY
CONSTRUCTION SITES
3351. ADV K. FRANCIS GEORGE:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् ग मंत्री
be pleased to state:
(a) whether the Government is aware of incidents of landslides, hill
collapses and accidents at National Highway construction sites;
(b) the details of such incidents reported during the last five years,
corridor-wise and Statewise;
(c) whether any geological or environmental assessment has been
conducted regarding safety lapses such as improper hill cutting,
weak retaining structures and poor drainage and if so, the findings
thereof;
(d) the steps taken to mandate geotechnical audits, safety
monitoring and compliance with disaster management guidelines;
and
(e) the measures proposed to establish real-time landslide
monitoring systems and strengthen contractor accountability
mechanisms?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS(SHRI NITIN JAIRAM GADKARI)
(a) and (b) Damages sustained and accidents on NHs, including
structures thereon, are also caused due to various other reasons
like design flaws, non-compliance to Standards / Specifications,
improper construction practices / techniques etc. apart from Force
Majeure events like heavy rains, landslides, floods etc. Generally,
incidents of extreme rainfall and landslides are witnessed in the
Himalayan Region and Western Ghat sections are causing large
scale damages to infrastructure including National Highways (NHs)
sections.
State / Union Territory (UT) – wise details of Incidents of
collapses / major deficiencies in NHs stretches (including in
structures like Bridges, culverts etc.) reported during the last five
years are at Annexure.
(c) to (e) Based upon the learning of failures of hill slopes during
construction, Environmental Impact Assessment reports etc., the
Government has taken various initiatives for developing disaster
resilient NHs infrastructure, including structures thereon, which
includes: -
i. Consultants to include slope studies and stabilization as part
of Detailed Project Report preparation. Geological and
geotechnical investigation are to be carried out covering both
within and beyond Right of Way (ROW) to prevent damages to
property and infrastructure. Also, due emphasis to be given for
construction of catch water drains, side drains with catch pits,
cut off drains, cross drainage, etc.
ii. Implementation of standardized parameters for investigating
hill slope stability & selecting cost-effective long-term
stabilization measures for landslide-prone areas in hilly
regions.
iii. Hill construction methodology refined which mandates initial
construction only for hill cutting & slope protection and
subsequent highway construction only post stabilized cutting
formation and protection work.iv. Sensor instruments based monitoring of internal slope
disturbances has also been taken up in 2 NHs stretches on
pilot basis for real-time landslide monitoring systems.
v. Implementation of sustainable bio-engineering measures such
as coir/jute mat hydroseeding, interlinked chain mesh with
green strips, bamboo piling by stepped berms and erosion
control with Vetivar grass plantation on jute matting etc. for
stabilizing hilly and landslide prone areas, thereby enhancing
safety on NHs in such areas.
vi. Research scheme taken up through IIT Roorkee for
Development of Guidelines for the Assessment of Hillslope
Instability Instrumentation & Real Time Monitoring
vii. Standard Operating Procedure issued along with delegation of
powers to field officers in case of notified disasters.
viii. Operationalization of a centralized monitoring application
system for Monitoring and rectification of highway defects
which enables geo-tagging of defects along with photographs
for contractor’s accountability.
ix. Authority officers directed for thorough inspection of NHs
stretches within six months of expiry of the Defect Liability
Period (DLP) / Concession Period to check enforcement of
defect rectification and maintenance status of NHs stretches.
In the event of not fulfilling the Contractual obligations by
Contractor / Concessionaire, DLP / Concession Period is also
suitably extended.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) AND (b) OF LOK
SABHA UNSTARRED QUESTION NO. 3351 ANSWERED ON
12.03.2026 ASKED BY ADV K. FRANCIS GEORGE REGARDING
LANDSLIDES AND ACCIDENTS ON NATIONAL HIGHWAY
CONSTRUCTION SITES
State / UT – wise details of Incidents of collapses / major
deficiencies in NHs stretches (including in structures like Bridges,
culverts etc.) reported during the last five years: -
S. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
Permanent solution to Slip Zones
on Papu – Yupia – Hoj – Potin
section of NH-713A & NH-13 at Km
Rectification of defective work
31.000 (Hoj Market), Km 38.300
Arunachal initiated by the Contractor. Penalty
1 (Yabi Village), Km 39.000 2024 RE wall Collapsed
Pradesh of 5% of contract value imposed on
(Waterfall), Km 39.700 (Appa
Contractor.
Crusher) and Km 40.300 (Crusher
Point) in the state of Arunachal
Pradesh for the year 2021-22
Six-laning of Vijayawada bypass
from Chinna Autupalli (Design Concessionaire commenced the
Ch.0+000) to Gollapudi (Design Ch. rectification work based on
30+000) in Vijayawada – Defects in the construction of recommendation /suggestion of RE
2 2024
Gundugolanu Section of NH-16 in RE wall. wall Expert.
the State of Andhra Pradesh under Rs.10,99,235/- was recovered as
Andhra
Bharatmala Pariyojana on Hybrid damages from Concessionaire.
Pradesh
Annuity Mode
2 girders (G1&G2) on A1-A2
SIx laning of Anandapuram- abutment of flyover were Remedial measures were
3 Pendurthi-Anakapalli section of NH- 2021 collapsed due to usage of completed by the Concessionaire
16 in Andhra Pradesh multiple wooden blocks and at its own cost.
improper supports for girders.
Four Laning of Simaria-Khagaria
Section of NH-31 from Km. 206.050 Issues reported by CRRI in
Repair works taken up by
to Km. 266.282 (Design Chainage) quality of Concrete of
4 2023 Contractor as recommended in
and (Existing Chainage Km. superstructure in bridge at Km
CRRI report
209.945 to Km. 270.000 of NH-31) 264.946
Bihar
in the State of Bihar on EPC Mode
Varanasi - Mohania (GTRIP/5;
Package - IV A): 4L of existing 2L Major deficiencies in structural Damages of INR 25 Cr imposed on
5 2023
section from km. 65 to km. 317 of elements Contractor
NH-2 in UP and Bihar on NH-2
4-Laning of Simga-Sargaon Section Action taken up for Panel
Cracks in Cement Concrete
Chhattisgarh 6 of NH-200 (New NH-130) from Km 2024 Rectifications at the risk & cost of
Panels
48+580 to Km 91+026 EPC Contractor.S. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
4-Laning of Sargaon-Bilaspur
Crack in Cement Concrete The EPC Contractor has
Section of NH-200 (New NH-130)
7 2022 Panels & RE Wall bulged at commenced the rectification work
from Km 91+026 to Km 126+525
Km. 91, 96, 101, 102 & 106. at site.
under EPC Mode
Rehabilitation & Upgradation 2-lane
with paved shoulders configuration
of Bilaspur Urdawal section in km The work is in Defect Liability
8 241.553 to 312.60 = 71.0476 km 2025 Damage in slab of Minor bridge Period and taken up by Contractor
(Masanialala to Rengapali) on NH at his own cost.
200 (New NH 49) (Package-
III)(Borai river MNB at km 217.358)
Collapse of road stretch
Four Laning of Parwanoo- Solan
between km. 3.130 to 3.170 on
Section NH-22 (New NH-05) from
Himachal the two-lane portion of the Restoration work has been
9 Km 67.000 to Km 106.139, under 2022
Pradesh project highway (approach road completed by EPC Contractor
NHDP phase-III on EPC basis in the
to Tunnel) of Parwanoo-Solan
State of Himachal Pradesh.
section of NH 05.
Some portion of deck slab fallen Arbitration notice issued to
Flyover and underpass at Hero down with settlement of the Contractor for recovery of
10 2024
Honda Chowk NH 48 bituminous surface (MCW-01) damages. Process of Rectification
on RHS at Ch. 36+350 and repair works initiated.
Penalty of Rs. 6.67 Cr on
Contractor and Rs. 20 lakhs on
Dwarka Expressway Pkg-III Authority’s Engineer imposed.
Crushing of concrete in some
11 (Delhi/HR Border to start of RoB 2021 Contractor and Authority’s
segments.
Gurugram) Engineer blacklisted for 3 months.
Restoration/ repair works
completed.
Authority has imposed damages
amounting to Rs.48,61,243/- on the
Haryana
contractor for delayed
maintenance. Rectification of
12 Delhi-Vadodara Expressway Pkg. 2 2024 Rutting
rutting has been taken up by
Contractor and majority of the
rutted portion has been rectified.
Authority has imposed damages
amounting to Rs. 42,95,049/- on
the contractor for delayed
13 Delhi-Vadodara Expressway Pkg. 3 2024 Rutting maintenance. Rectification of
rutting has been taken up by
Contractor and majority of the
rutted portion has been rectified.
Ruts, cracks and surface Penalty of ₹2.8 crore had been
Gujarat 14 Sanchore-Santalpur Package-4 2025 deformation/ Distress was imposed on the Contractor along
observed recently after rains in with a recommendation forS. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
June month 2025, severe debarment up to one year or until
rutting at some locations. successful rectification, whichever
is later. Contractor has taken up
repair/ restoration works. The
Project Director of NHAI was
suspended.
4 Laning of kutchery chowk to Performance Bank Guarantee of
Jharkhand 15 bijupara Secion of NH 75 from km 2022 Cracked PQC panels Rs 11.79 Crores encashed for non-
0.0 to km 34.00 rectification of defects
Concessionaire has taken up
Two/Four Laning of BRT Tiger Km 337+670 to
repair/ restoration works as per
16 Reserve Boundary to Bengalore 2025 Km337+680 RE Block of length
recommendation of report
Section of NH-948 10 mts collapsed
Karnataka submitted by IISC Bangalore.
Cracks on PQC Pavement and
Contractor has initiated actions for
17 4-laning of Hubli – Hospet section 2022 widening of longitudinal joints
rectification of damages.
on pavement
Four laning of Goa-Karnataka 2024
Border to Kundapur section of NH- Incident of collapse of three
66 (formerly NH-17) from Km. spans of Kaali Bridge.
Contractor debarred for 1 month on
18 93.700 to Km. 283.300 in the State Inadequate slope stability
Aug 2024
of Karnataka to be executed as works.
BOT Project on DBFOT Pattern
under NHDP-IV:
Distress in pile foundation was
NH Connectivity to ICTT at
observed at Bridge no. 07 & 08 Penalty of Rs. 30.74 Cr was
19 Vallarpdam from Kalamassery to 2025
Ch. 7+960 and Ch. 9+067 imposed on Contractor
Vallarpadam NH 966A
(BHS)
Damages in the pile foundation
Ch. 398+400 and 398+989 Concessionaire debarred for 1
20 Kodugallur to Edappally NH 66 2025
(RHS) year.
Collapse of VUP at Ch.
72+927 in 2022 during Authority has suspended the
construction Concessionaire and its promoter
Kerala 2022
Chengala-Neeleshwaram Section of from future bidding for 01-month
21 and
NH-66 Soil nailing collapsed incident period. Debarment also issued to
2025
occurred at Ch. 58+035 to Ch. Concessionaire. Senior Bridge
58+100 (RHS) on 16.06.2025 Engineer of AE removed from site.
with no casualties.
Unprotected soil slip in the cut Rectification work carried out and
Neeleshwaram-Thaliparambha
22 2025 section with debris deposition traffic restored with precautionary
Section of NH-66
on carriageways. barricading in median portion.
NHAI - Six laning from start of Debarment of Contractor and
Valanchery bypass to Kappirikkad Independent Engineering firm from
23 RE wall collapsed
section of NH – 66 (old NH-17) from 2025 participating in ongoing/future
Design Ch. 298+500 (Ex. km bidding for 01 month period orS. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
304.250) to Design Chainage completion of investigation by the
335+850 (Ex. km 349.260) in the expert Committee whichever is
state of Kerala on Hybrid Annuity later.
Mode under Bharatmala Pariyojana
NHAI, imposed penalty of Rs.
Collapse of 4 PSC Girders 15.35 Lakhs. Bridge Engineer &
24 Thuravoor-paravoor 2025
during construction Team Leader of AE were
Terminated.
Six Laning of Start of Kollam
Bypass to Kadambattukonam from Failure/Collapse of scaffolding
Km.486+000 to Km.517+800 of NH- of Minor Bridge (under Penalty of Rs. 9.55 lakhs imposed
25 2025
47 (New NH-66) in the State of construction) at Km.Ch. on Concessionaire
Kerala on Hybrid Annuity Mode 497+370(RHS)
under BharatmalaPariyojna
Toppling of two PSC girders at
span P-202-P-203
6L Elevated Corridor along with
development of existing 4 lane road Failure on part of AE to review Contractor and AE debarred from
26 2025
at ground level from Aroor to efficacy of material being used future bidding for 1 month.
Thuravoor Thekku section of NH 66 in launching and not ensuring
application of approved
launching scheme.
Debarment of the Project Manager
Construction of 4-laning Flyover of
of Contractor for 3 months and
NH-6 integrated with ROB's & River
Debarment of the Contractor for 9
Bridge including approach ramps Sliding of P7 end of the single
months.
service road footpath over RCC girder due to inadequate
utility duct for Octroi Naka to Itwari bracing after launching leading
27 2021 The damaged Girder was replaced
and Inner Ring Road from to collapse of 1 end of the
by Contractor at his own cost.
Manewada to Kalamna and Rani girder.
Prajapati Square to Vaishnav Devi
Project Director, NHAI, transferred
Square including ROB LC No. 71
immediately.
&72 in Nagpur of NH-6
Structure was Audited by VNIT
Maharashtra
Bal. Works of Fagne (Km. 510.000) Nagpur.
Damages observed in Slab of
28 to Maharashtra/Gujarat Border (Km. 2022 As per the recommendation of
Major Bridge at Ch.547.344
650.794) on NH-06 (New NH-53) VNIT, Nagpur, Contractor has
taken up reconstruction of slab.
Balance work for 4-laning of Panvel Panel cracking, poor riding
Contractor has taken up
29 to Indapur section from km.0.0 to 2024 quality, bumps, poor diversions
rectification works.
km.42.3 of NH-66 - EPC etc.
Section -II Kolde to Khetia Road Contractor has initiated actions for
30 2021 Cracked panels
km.50+200 to 98+800 rectification of damages.
The Performance BG of Contractor
31 Mehkar-Ajispur Road 2024 Cracked panels is forfeited. Process initiated for
rectification of damages.S. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
Contractor has initiated actions for
32 Bhokar-Sarsam 2024 Cracked panels
rectification of damages.
Contractor has initiated actions for
33 Sillod-Fardapur 2024 Cracked panels
rectification of damages.
Contractor has executed the panel
34 Parbhani to Gangakhed 2021 Cracked panels
replacement / rectification works.
Contractor has initiated actions for
35 Amdi - Saoner 2022 Cracked panels
rectification of damages.
Rehabilitation and upgradation &
NH-66 (Erstwhile NH-17) form km
241+300 to 281+300 (Arawali to
Contractor has initiated actions for
36 Kante Section) to four lane with Depression & cracks in PQC
2025 rectification of damages.
paved shoulder in the state of
Maharashtra under NHDP-IV on
Hybrid Annuity Mode.
Rehabilitation & Upgradation of NH-
66 (Old NH17) from Km 281+300 to
Km 332+200 (Kante to Waked Contractor has replaced cracked
37 2024 PQC cracks and settlement.
section) to four lanes in the state of panels.
Maharashtra under NHDP-IV on
Hybrid Annuity Mode.
Rehabilitation and up-gradation of
NH-66 (Old NH-17) form km
332/200 to km 367/200 (Watul to Contractor has initiated actions for
38 2024 Full depth Cracks in PQC
Talgaon Section) to four lanes in the rectification of damages.
State of Maharashtra under NHDP-
IV on EPC Mode.
Rehabilitatyion & up gradation for
Talere Gaganbawada Kolhapur
Road (NH-166G) stretches start
from Ch. 6/00 Km. to Ch. 11/00 Km.
and Ch. 19/300 Km. (Start of Karul
Contractor has initiated actions for
39 Ghat) to 35/300 Km. (End of 2025 Cracks in PQC
rectification of damages.
Gaganbawada) of NH-166G to 2
lane paved shoulder/2 lane
configuration lane, length 21.00 Km.
in the state of Mahrashtra on EPC
Mode.
Rehabilitation and Up-gradation to
Two lanes with paved shoulder from
Rectification of damages taken up
40 Karad to Tasgaon NH 266 from Km. 2024 Cracked panels
at risk and cost of Contractor.
0/00 to 58/830 in the State of
Maharashtra on EPC mode
Upgradation to two lane with paved Post construction defects are IIT Bombay has been appointed for
41 shoulder from Salaikhurd to Tiroda 2024 observed in the Rigid Pavement Technical Investigation of defects
Km 120/100 to 163/200 (Design i.e. formation of Longitudinal & and suggestion of remedialS. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
Km 44/00 to 87/00) of NH 753 on Lateral cracks, Opening of measures.
EPC Mode in the state of Central Joints, Settlement of
Maharashtra Panels etc.
Penalty imposed on each
contractor amounting to Rs. 50
Delhi Vadodara Expressway NE-4 Lakhs for non-rectification of
42 2024
Pkg.06 defects in the stipulated time frame
as per provision of contract
Rutting, Raincuts, potholes & agreement.
Delhi Vadodara Expressway NE-4 settlement
43 2024
Pkg.07
Delhi Vadodara Expressway NE-4
44 2024
Pkg.08
Delhi Vadodara Expressway NE-4
45 2024
Pkg.09
Construction of 6-lane access-
controlled Greenfield highway from
km 28+70 to Km. 53+0 of Sangariya
(i) Damage of Rs. 50.00 Lakhs
(near Chautala)-Rasisar (near
Deficiencies in riding quality and imposed upon the Contractor.
Bikaner) section of NH-754K as a
46 2024 settlement at some locations (ii) Two key personnel of Authority
part of Amritsar-Jamnagar
observed Engineer team were terminated
Economic Corridor in the State of
due to poor supervision.
Rajasthan under Bharatmala
Pariyojana -Phase-I (AJ/SR-
Rajasthan
Package-2)
Penalty of Rs. 1.00 Cr. imposed
and warning for debarment action
for any future instances upon the
Construction of 6-lane access
Contractor was issued.
controlled Greenfield highway from
Debarment of fabrication team and
km 53+000 to Km.
Designer team issued for the
88+000 of Sangariya (near
Failure of the nose structure period of 02 years in NHAI works.
Chautala)-Rasisar (near Bikaner)
47 2024 while launching of 83 mtr single Penalty of Rs. 20 Lakhs and
section of NH-754K as a part of
span truss bridge warning for debarment action for
Amritsar-Jamnagar Economic
any future instances upon the
Corridor in the State of Rajasthan
Authority Engineer.
under Bharatmala Pariyojana-
Debarment of Senior bridge
Phase-I (AJ/SR-Package-3)
Engineer deployed by the Authority
Engineer issued for a period of 2
years in NHAI works.
Damages amounting to Rs. 1.06
Cr. imposed for delayed
Rutting & settlement of maintenance. Also, IIT Kharagpur
48 Delhi-Vadodara Expressway Pkg. 4 2024
approach has been engaged for detailed
study for permanent rectification of
defects.S. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
Damages amounting to Rs. 88.32
lakhs imposed for delayed
maintenance. Bulging of RE wall
has been rectified as per
Rutting, settlement of approach suggestions of CRRI. Majority of
49 Delhi-Vadodara Expressway Pkg. 5 2024
& bulging of RE wall the rutting has been rectified.
Further, in addition to above, IIT
Kharagpur has been engaged for
detailed study for permanent
rectification of defects.
Delhi-Vadodara Greenfield
Stretch is operational w.e.f.
Alignment (NH-148N) (Pkg-16) (Ch.
30.11.2023 and at some
427.300 to Ch.452.420) [Major EPC Contractor has rectified
50 2024 locations the settlements
bridge over Takli river near damages. R
observed in approaches of
Nayagaon Jageer village to
structure
Rajasthan/MP Border]
Construction of proposed 2-lane
Post-completion, structural
ROB and its approaches in lieu of Contract has been
defects have been observed in
existing level crossing no. C-64 at terminated. Debarment of
51 2024 the deck slab of the ROB due to
km. 172.990 on Jodhpur–Ajmer contractor taken up. Bid for
honeycombing caused by poor
Road on NH-65 in District Nagaur rectification works invited.
workmanship.
Rajasthan
Four Laning of NH-161 from
Mangloor (Design Km 86.788
/existing Km 91.350 to At some locations Rutting and Penalty of of Rs.134.784
Telangana/Maharashtra Border Bleeding was observed in the Cr. imposed towards Breach of
Telangana 52 2022
(Design Km 135.751/ Existing Km Project Highway during O&M maintenance obligations.
140.873) in the state of Telangana Period
under Bharatmala Pariyojana on
Hybrid Annuity Mode (Package-III)
3 Girders (G1, G2 & G3)
between pier P4 & P5 at Km Contractor has replaced the girders
4-laning of Madurai - Chettikulam
53 2021 2+850 of down ramp collapsed at the said locations at his own
section from Km 0.000 to Km 7.300.
during fixing of the Bearing cost.
during construction.
In 2022: In 2022:
A Segmental Girder on P16-A penalty amounting to Rs. 7.305
P17 of RHS Carriageway fell crore (being 0.5% of the BPC) had
Tamil Nadu
down due to failure of hydraulic been imposed and recovered from
4-laning of Sethiyathope - 2022 jacks at Km 107+400 Anaikarai the Concessionaire.
54 Cholpauram section from Km and Major Bridge across Kollidam The collapsed span has been
65.960 to Km 116.440 2025 river. reconstructed by the
Concessionaire with their own cost.
In 2025:
The RE wall blocks portion of In 2025:
the A2 (Thanjavur) side The rectification work completed byS. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
approach (LHS side) have been the Concessionaire at their own
disconnected from the geo grid cost.
and fallen down.
The RE wall panel portion of the
4-laning of Thanjavur - Trichy A1 (Thanjavur) side approach Based on report of Expert
55 section from Km 80.000 to Km 2023 (LHS side) have been Committee, restoration work using
136.490 disconnected from the geo grid soil nailing completed by
and fallen down. Contractor.
Construction of 4 lane green field
highway from km 35.00 to 49.155 of
The project is under construction,
NH-731A with paved shoulder on Cracks observed over DBM due
the repair and rectification work
56 Hybrid Annuity Mode in the State of 2025 to percolation of rain water in
Uttar taken up by the concessionaire at
Uttar Pradesh. (Job No. CE-RO- some stretches.
Pradesh its own cost.
LKO/NH(O)/NH-731A/2021-
22/627 dt 05-01-2022)
Cracks in PQC Panel in length Contractor has initiated process for
57 Lucknow Ring Road Pkg-3A 2024
of 2.886 Km. rectification of damages.
Uttar
4L of Haridwar-Nagina section of Contractor has initiated process for
Pradesh & 58 2023 PQC panel cracks
NH-74 rectification of damages.
Uttarakhand
Construction, Operation and
Maintenance of 2-Lane Bi-
Rectification measures taken up by
Directional Silkyara Bend Barkot
the EPC contractors at its own
Tunnel with escape passage
Collapse at cavity in under cost.
Uttarakhand 59 including approaches on Dharasu– 2023
construction Silkyara Tunnel.
Yamunotri section between Ch.
Actions as per the Investigation
25.400 Km and Ch. 51.000 Km
Committee Report initiated.
falling along NH-134 (OLD NH-94)
in the state of Uttarakhand
i) Rectification works initiated by
Construction of 4-Laning of Puruliya
Contractor. Amount of Rs. 20.00
Bypass Section from Km. 84.030 to
Cracks have developed in the Lakh withheld from Contractor's bill.
60 Km. 94.345 of NH-32 (length 10.315 2025
newly constructed PQC.
Km) in the State of West Bengal on
ii) Key personal of AE has been
EPC Mode
debarred for a period of one year.
West Bengal
Four laning with paved shoulders of
NH-6 from Chichra to Kharagpur
Km 185.150 to Km 134.400 Repaired at the Risk and Cost of
61 2023 Cracks in PQC panels
including rehabilitation of existing EPC Contractor.
four lane from Km 134.400 to Km
129.600 in the state of West Bengal
1. Faulty Design in Bridge at 1. For Faulty Design at Km 96+326,
km. 96+326: penalty imposed of Rs.30 Lakhs on
Chandikhole-Bhadrak Section of
Odisha 62 2023 the Concessionaire and Rs.5 Lakhs
NH-16
2. Bridge at km. 79+614: on the Independent Engineer.
The span A1-P1 had dislodged Team Leader of IE and KeyS. Year of Details of Major damages /
State Name of the Project Action Taken
No. incident defects
from the pier P2 due to breaking Personnel of Concessionaire
of the cantilever suspended.
Portion of the pier cap and had
fallen on the ground. 2. For Bridge at km. 79+614:
Penalty of Rs.5 crore imposed on
Appearance of wide cracks (up the Contractor and Penalty of
to 3-4mm) in the pier cap on Rs.20 lakh imposed on the
grid “P2”. Supervision Consultant.
Damages of deck slab and Debarment of DPR Consultant for 1
girders of the dislodged span. year.
The cost of entire remedial
measures / reconstruction
recovered from the
Concessionaire.
Completion of Balance Work
Collapse of pier cap (P8) and
Panikoili – Rimuli section of NH-215
girders (P8 – P9 Span) Balance Restoration work executed by
(New NH-20) from Km.0.000 to
work of Belabahali Major Bridge Contractor at his own Cost based
63 Km.163.000 (Design Chainage 2022
LHS at Km.35.341 which was on the recommendation of Expert
Km0.000 to 166.173) in the state of
under construction collapsed Committee constituted.
Odisha in single percentage item
during launching of girders.
rate Contract
Construction of 6-lane Standalone
Flyovers at Bongaigaon, Chapaguri,
Pathsala, Simlaguri Chowk and Falling of one PSC Girder at
Baihata Junctions on stretches of Baihata Flyover (Span P1-P2), Penalty imposed on Contractor.
Assam 64 2024
NH-31 & NH-31C [new NH-27 resulting in the death of one Contractor debarred for 4 months.
(EW)] in the State of Assam under person.
Bharatmala Pariyojana on EPC
basis
Rehabilitation of km 181.00 to Km
206.00 section in Andaman Trunk
Road of NH-4 to Intermediate Lane
Distress, sinking of pavement at
65 with hard shoulder in the union 2024 Rectification works completed.
various locations.
Territory of Andaman & Nicobar
islands (Total length 25.00 km) on
Andaman &
EPC Mode” (Package-VII)
Nicobar
Construction of 4 Nos. of Minor
Islands The EPC contractor has carried out
Bridges at Km 21.717, Km 23.150, Punching in Deck Slab (LHS) of
the necessary rectifications at their
Km 88.300, Km 92.100 of NH- 223 the minor bridge across BD
own expense including
66 (New NH-4) connecting South 2024 Nallah at Km 88+300 and other
replacement of slab as
Andaman and Baratang Island in quality issues including bad
recommended by CRRI-CSIR
the Union Territory of Andaman & workmanship.
report.
Nicobar Islands on EPC mode.
*****