Parliament Question: Landslides and Accidents on National Highway Construction Sites

Issued by ROAD TRANSPORT AND HIGHWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 3351 ANSWERED ON 12TH MARCH, 2026 LANDSLIDES AND ACCIDENTS ON NATIONAL HIGHWAY CONSTRUCTION SITES 3351. ADV K. FRANCIS GEORGE: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार् ग मंत्री be pleased to state: (a) whether the Government is aware of incidents of landslides, hill collapses and accidents at National Highway construction sites; (b) the details of such incidents reported during the last five years, corridor-wise and Statewise; (c) whether any geological or environmental assessment has been conducted regarding safety lapses such as improper hill cutting, weak retaining structures and poor drainage and if so, the findings thereof; (d) the steps taken to mandate geotechnical audits, safety monitoring and compliance with disaster management guidelines; and (e) the measures proposed to establish real-time landslide monitoring systems and strengthen contractor accountability mechanisms? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS(SHRI NITIN JAIRAM GADKARI) (a) and (b) Damages sustained and accidents on NHs, including structures thereon, are also caused due to various other reasons like design flaws, non-compliance to Standards / Specifications, improper construction practices / techniques etc. apart from Force Majeure events like heavy rains, landslides, floods etc. Generally, incidents of extreme rainfall and landslides are witnessed in the Himalayan Region and Western Ghat sections are causing large scale damages to infrastructure including National Highways (NHs) sections. State / Union Territory (UT) – wise details of Incidents of collapses / major deficiencies in NHs stretches (including in structures like Bridges, culverts etc.) reported during the last five years are at Annexure. (c) to (e) Based upon the learning of failures of hill slopes during construction, Environmental Impact Assessment reports etc., the Government has taken various initiatives for developing disaster resilient NHs infrastructure, including structures thereon, which includes: - i. Consultants to include slope studies and stabilization as part of Detailed Project Report preparation. Geological and geotechnical investigation are to be carried out covering both within and beyond Right of Way (ROW) to prevent damages to property and infrastructure. Also, due emphasis to be given for construction of catch water drains, side drains with catch pits, cut off drains, cross drainage, etc. ii. Implementation of standardized parameters for investigating hill slope stability & selecting cost-effective long-term stabilization measures for landslide-prone areas in hilly regions. iii. Hill construction methodology refined which mandates initial construction only for hill cutting & slope protection and subsequent highway construction only post stabilized cutting formation and protection work.iv. Sensor instruments based monitoring of internal slope disturbances has also been taken up in 2 NHs stretches on pilot basis for real-time landslide monitoring systems. v. Implementation of sustainable bio-engineering measures such as coir/jute mat hydroseeding, interlinked chain mesh with green strips, bamboo piling by stepped berms and erosion control with Vetivar grass plantation on jute matting etc. for stabilizing hilly and landslide prone areas, thereby enhancing safety on NHs in such areas. vi. Research scheme taken up through IIT Roorkee for Development of Guidelines for the Assessment of Hillslope Instability Instrumentation & Real Time Monitoring vii. Standard Operating Procedure issued along with delegation of powers to field officers in case of notified disasters. viii. Operationalization of a centralized monitoring application system for Monitoring and rectification of highway defects which enables geo-tagging of defects along with photographs for contractor’s accountability. ix. Authority officers directed for thorough inspection of NHs stretches within six months of expiry of the Defect Liability Period (DLP) / Concession Period to check enforcement of defect rectification and maintenance status of NHs stretches. In the event of not fulfilling the Contractual obligations by Contractor / Concessionaire, DLP / Concession Period is also suitably extended.ANNEXURE ANNEXURE REFERRED TO IN REPLY TO PARTS (a) AND (b) OF LOK SABHA UNSTARRED QUESTION NO. 3351 ANSWERED ON 12.03.2026 ASKED BY ADV K. FRANCIS GEORGE REGARDING LANDSLIDES AND ACCIDENTS ON NATIONAL HIGHWAY CONSTRUCTION SITES State / UT – wise details of Incidents of collapses / major deficiencies in NHs stretches (including in structures like Bridges, culverts etc.) reported during the last five years: - S. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects Permanent solution to Slip Zones on Papu – Yupia – Hoj – Potin section of NH-713A & NH-13 at Km Rectification of defective work 31.000 (Hoj Market), Km 38.300 Arunachal initiated by the Contractor. Penalty 1 (Yabi Village), Km 39.000 2024 RE wall Collapsed Pradesh of 5% of contract value imposed on (Waterfall), Km 39.700 (Appa Contractor. Crusher) and Km 40.300 (Crusher Point) in the state of Arunachal Pradesh for the year 2021-22 Six-laning of Vijayawada bypass from Chinna Autupalli (Design Concessionaire commenced the Ch.0+000) to Gollapudi (Design Ch. rectification work based on 30+000) in Vijayawada – Defects in the construction of recommendation /suggestion of RE 2 2024 Gundugolanu Section of NH-16 in RE wall. wall Expert. the State of Andhra Pradesh under Rs.10,99,235/- was recovered as Andhra Bharatmala Pariyojana on Hybrid damages from Concessionaire. Pradesh Annuity Mode 2 girders (G1&G2) on A1-A2 SIx laning of Anandapuram- abutment of flyover were Remedial measures were 3 Pendurthi-Anakapalli section of NH- 2021 collapsed due to usage of completed by the Concessionaire 16 in Andhra Pradesh multiple wooden blocks and at its own cost. improper supports for girders. Four Laning of Simaria-Khagaria Section of NH-31 from Km. 206.050 Issues reported by CRRI in Repair works taken up by to Km. 266.282 (Design Chainage) quality of Concrete of 4 2023 Contractor as recommended in and (Existing Chainage Km. superstructure in bridge at Km CRRI report 209.945 to Km. 270.000 of NH-31) 264.946 Bihar in the State of Bihar on EPC Mode Varanasi - Mohania (GTRIP/5; Package - IV A): 4L of existing 2L Major deficiencies in structural Damages of INR 25 Cr imposed on 5 2023 section from km. 65 to km. 317 of elements Contractor NH-2 in UP and Bihar on NH-2 4-Laning of Simga-Sargaon Section Action taken up for Panel Cracks in Cement Concrete Chhattisgarh 6 of NH-200 (New NH-130) from Km 2024 Rectifications at the risk & cost of Panels 48+580 to Km 91+026 EPC Contractor.S. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects 4-Laning of Sargaon-Bilaspur Crack in Cement Concrete The EPC Contractor has Section of NH-200 (New NH-130) 7 2022 Panels & RE Wall bulged at commenced the rectification work from Km 91+026 to Km 126+525 Km. 91, 96, 101, 102 & 106. at site. under EPC Mode Rehabilitation & Upgradation 2-lane with paved shoulders configuration of Bilaspur Urdawal section in km The work is in Defect Liability 8 241.553 to 312.60 = 71.0476 km 2025 Damage in slab of Minor bridge Period and taken up by Contractor (Masanialala to Rengapali) on NH at his own cost. 200 (New NH 49) (Package- III)(Borai river MNB at km 217.358) Collapse of road stretch Four Laning of Parwanoo- Solan between km. 3.130 to 3.170 on Section NH-22 (New NH-05) from Himachal the two-lane portion of the Restoration work has been 9 Km 67.000 to Km 106.139, under 2022 Pradesh project highway (approach road completed by EPC Contractor NHDP phase-III on EPC basis in the to Tunnel) of Parwanoo-Solan State of Himachal Pradesh. section of NH 05. Some portion of deck slab fallen Arbitration notice issued to Flyover and underpass at Hero down with settlement of the Contractor for recovery of 10 2024 Honda Chowk NH 48 bituminous surface (MCW-01) damages. Process of Rectification on RHS at Ch. 36+350 and repair works initiated. Penalty of Rs. 6.67 Cr on Contractor and Rs. 20 lakhs on Dwarka Expressway Pkg-III Authority’s Engineer imposed. Crushing of concrete in some 11 (Delhi/HR Border to start of RoB 2021 Contractor and Authority’s segments. Gurugram) Engineer blacklisted for 3 months. Restoration/ repair works completed. Authority has imposed damages amounting to Rs.48,61,243/- on the Haryana contractor for delayed maintenance. Rectification of 12 Delhi-Vadodara Expressway Pkg. 2 2024 Rutting rutting has been taken up by Contractor and majority of the rutted portion has been rectified. Authority has imposed damages amounting to Rs. 42,95,049/- on the contractor for delayed 13 Delhi-Vadodara Expressway Pkg. 3 2024 Rutting maintenance. Rectification of rutting has been taken up by Contractor and majority of the rutted portion has been rectified. Ruts, cracks and surface Penalty of ₹2.8 crore had been Gujarat 14 Sanchore-Santalpur Package-4 2025 deformation/ Distress was imposed on the Contractor along observed recently after rains in with a recommendation forS. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects June month 2025, severe debarment up to one year or until rutting at some locations. successful rectification, whichever is later. Contractor has taken up repair/ restoration works. The Project Director of NHAI was suspended. 4 Laning of kutchery chowk to Performance Bank Guarantee of Jharkhand 15 bijupara Secion of NH 75 from km 2022 Cracked PQC panels Rs 11.79 Crores encashed for non- 0.0 to km 34.00 rectification of defects Concessionaire has taken up Two/Four Laning of BRT Tiger Km 337+670 to repair/ restoration works as per 16 Reserve Boundary to Bengalore 2025 Km337+680 RE Block of length recommendation of report Section of NH-948 10 mts collapsed Karnataka submitted by IISC Bangalore. Cracks on PQC Pavement and Contractor has initiated actions for 17 4-laning of Hubli – Hospet section 2022 widening of longitudinal joints rectification of damages. on pavement Four laning of Goa-Karnataka 2024 Border to Kundapur section of NH- Incident of collapse of three 66 (formerly NH-17) from Km. spans of Kaali Bridge. Contractor debarred for 1 month on 18 93.700 to Km. 283.300 in the State Inadequate slope stability Aug 2024 of Karnataka to be executed as works. BOT Project on DBFOT Pattern under NHDP-IV: Distress in pile foundation was NH Connectivity to ICTT at observed at Bridge no. 07 & 08 Penalty of Rs. 30.74 Cr was 19 Vallarpdam from Kalamassery to 2025 Ch. 7+960 and Ch. 9+067 imposed on Contractor Vallarpadam NH 966A (BHS) Damages in the pile foundation Ch. 398+400 and 398+989 Concessionaire debarred for 1 20 Kodugallur to Edappally NH 66 2025 (RHS) year. Collapse of VUP at Ch. 72+927 in 2022 during Authority has suspended the construction Concessionaire and its promoter Kerala 2022 Chengala-Neeleshwaram Section of from future bidding for 01-month 21 and NH-66 Soil nailing collapsed incident period. Debarment also issued to 2025 occurred at Ch. 58+035 to Ch. Concessionaire. Senior Bridge 58+100 (RHS) on 16.06.2025 Engineer of AE removed from site. with no casualties. Unprotected soil slip in the cut Rectification work carried out and Neeleshwaram-Thaliparambha 22 2025 section with debris deposition traffic restored with precautionary Section of NH-66 on carriageways. barricading in median portion. NHAI - Six laning from start of Debarment of Contractor and Valanchery bypass to Kappirikkad Independent Engineering firm from 23 RE wall collapsed section of NH – 66 (old NH-17) from 2025 participating in ongoing/future Design Ch. 298+500 (Ex. km bidding for 01 month period orS. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects 304.250) to Design Chainage completion of investigation by the 335+850 (Ex. km 349.260) in the expert Committee whichever is state of Kerala on Hybrid Annuity later. Mode under Bharatmala Pariyojana NHAI, imposed penalty of Rs. Collapse of 4 PSC Girders 15.35 Lakhs. Bridge Engineer & 24 Thuravoor-paravoor 2025 during construction Team Leader of AE were Terminated. Six Laning of Start of Kollam Bypass to Kadambattukonam from Failure/Collapse of scaffolding Km.486+000 to Km.517+800 of NH- of Minor Bridge (under Penalty of Rs. 9.55 lakhs imposed 25 2025 47 (New NH-66) in the State of construction) at Km.Ch. on Concessionaire Kerala on Hybrid Annuity Mode 497+370(RHS) under BharatmalaPariyojna Toppling of two PSC girders at span P-202-P-203 6L Elevated Corridor along with development of existing 4 lane road Failure on part of AE to review Contractor and AE debarred from 26 2025 at ground level from Aroor to efficacy of material being used future bidding for 1 month. Thuravoor Thekku section of NH 66 in launching and not ensuring application of approved launching scheme. Debarment of the Project Manager Construction of 4-laning Flyover of of Contractor for 3 months and NH-6 integrated with ROB's & River Debarment of the Contractor for 9 Bridge including approach ramps Sliding of P7 end of the single months. service road footpath over RCC girder due to inadequate utility duct for Octroi Naka to Itwari bracing after launching leading 27 2021 The damaged Girder was replaced and Inner Ring Road from to collapse of 1 end of the by Contractor at his own cost. Manewada to Kalamna and Rani girder. Prajapati Square to Vaishnav Devi Project Director, NHAI, transferred Square including ROB LC No. 71 immediately. &72 in Nagpur of NH-6 Structure was Audited by VNIT Maharashtra Bal. Works of Fagne (Km. 510.000) Nagpur. Damages observed in Slab of 28 to Maharashtra/Gujarat Border (Km. 2022 As per the recommendation of Major Bridge at Ch.547.344 650.794) on NH-06 (New NH-53) VNIT, Nagpur, Contractor has taken up reconstruction of slab. Balance work for 4-laning of Panvel Panel cracking, poor riding Contractor has taken up 29 to Indapur section from km.0.0 to 2024 quality, bumps, poor diversions rectification works. km.42.3 of NH-66 - EPC etc. Section -II Kolde to Khetia Road Contractor has initiated actions for 30 2021 Cracked panels km.50+200 to 98+800 rectification of damages. The Performance BG of Contractor 31 Mehkar-Ajispur Road 2024 Cracked panels is forfeited. Process initiated for rectification of damages.S. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects Contractor has initiated actions for 32 Bhokar-Sarsam 2024 Cracked panels rectification of damages. Contractor has initiated actions for 33 Sillod-Fardapur 2024 Cracked panels rectification of damages. Contractor has executed the panel 34 Parbhani to Gangakhed 2021 Cracked panels replacement / rectification works. Contractor has initiated actions for 35 Amdi - Saoner 2022 Cracked panels rectification of damages. Rehabilitation and upgradation & NH-66 (Erstwhile NH-17) form km 241+300 to 281+300 (Arawali to Contractor has initiated actions for 36 Kante Section) to four lane with Depression & cracks in PQC 2025 rectification of damages. paved shoulder in the state of Maharashtra under NHDP-IV on Hybrid Annuity Mode. Rehabilitation & Upgradation of NH- 66 (Old NH17) from Km 281+300 to Km 332+200 (Kante to Waked Contractor has replaced cracked 37 2024 PQC cracks and settlement. section) to four lanes in the state of panels. Maharashtra under NHDP-IV on Hybrid Annuity Mode. Rehabilitation and up-gradation of NH-66 (Old NH-17) form km 332/200 to km 367/200 (Watul to Contractor has initiated actions for 38 2024 Full depth Cracks in PQC Talgaon Section) to four lanes in the rectification of damages. State of Maharashtra under NHDP- IV on EPC Mode. Rehabilitatyion & up gradation for Talere Gaganbawada Kolhapur Road (NH-166G) stretches start from Ch. 6/00 Km. to Ch. 11/00 Km. and Ch. 19/300 Km. (Start of Karul Contractor has initiated actions for 39 Ghat) to 35/300 Km. (End of 2025 Cracks in PQC rectification of damages. Gaganbawada) of NH-166G to 2 lane paved shoulder/2 lane configuration lane, length 21.00 Km. in the state of Mahrashtra on EPC Mode. Rehabilitation and Up-gradation to Two lanes with paved shoulder from Rectification of damages taken up 40 Karad to Tasgaon NH 266 from Km. 2024 Cracked panels at risk and cost of Contractor. 0/00 to 58/830 in the State of Maharashtra on EPC mode Upgradation to two lane with paved Post construction defects are IIT Bombay has been appointed for 41 shoulder from Salaikhurd to Tiroda 2024 observed in the Rigid Pavement Technical Investigation of defects Km 120/100 to 163/200 (Design i.e. formation of Longitudinal & and suggestion of remedialS. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects Km 44/00 to 87/00) of NH 753 on Lateral cracks, Opening of measures. EPC Mode in the state of Central Joints, Settlement of Maharashtra Panels etc. Penalty imposed on each contractor amounting to Rs. 50 Delhi Vadodara Expressway NE-4 Lakhs for non-rectification of 42 2024 Pkg.06 defects in the stipulated time frame as per provision of contract Rutting, Raincuts, potholes & agreement. Delhi Vadodara Expressway NE-4 settlement 43 2024 Pkg.07 Delhi Vadodara Expressway NE-4 44 2024 Pkg.08 Delhi Vadodara Expressway NE-4 45 2024 Pkg.09 Construction of 6-lane access- controlled Greenfield highway from km 28+70 to Km. 53+0 of Sangariya (i) Damage of Rs. 50.00 Lakhs (near Chautala)-Rasisar (near Deficiencies in riding quality and imposed upon the Contractor. Bikaner) section of NH-754K as a 46 2024 settlement at some locations (ii) Two key personnel of Authority part of Amritsar-Jamnagar observed Engineer team were terminated Economic Corridor in the State of due to poor supervision. Rajasthan under Bharatmala Pariyojana -Phase-I (AJ/SR- Rajasthan Package-2) Penalty of Rs. 1.00 Cr. imposed and warning for debarment action for any future instances upon the Construction of 6-lane access Contractor was issued. controlled Greenfield highway from Debarment of fabrication team and km 53+000 to Km. Designer team issued for the 88+000 of Sangariya (near Failure of the nose structure period of 02 years in NHAI works. Chautala)-Rasisar (near Bikaner) 47 2024 while launching of 83 mtr single Penalty of Rs. 20 Lakhs and section of NH-754K as a part of span truss bridge warning for debarment action for Amritsar-Jamnagar Economic any future instances upon the Corridor in the State of Rajasthan Authority Engineer. under Bharatmala Pariyojana- Debarment of Senior bridge Phase-I (AJ/SR-Package-3) Engineer deployed by the Authority Engineer issued for a period of 2 years in NHAI works. Damages amounting to Rs. 1.06 Cr. imposed for delayed Rutting & settlement of maintenance. Also, IIT Kharagpur 48 Delhi-Vadodara Expressway Pkg. 4 2024 approach has been engaged for detailed study for permanent rectification of defects.S. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects Damages amounting to Rs. 88.32 lakhs imposed for delayed maintenance. Bulging of RE wall has been rectified as per Rutting, settlement of approach suggestions of CRRI. Majority of 49 Delhi-Vadodara Expressway Pkg. 5 2024 & bulging of RE wall the rutting has been rectified. Further, in addition to above, IIT Kharagpur has been engaged for detailed study for permanent rectification of defects. Delhi-Vadodara Greenfield Stretch is operational w.e.f. Alignment (NH-148N) (Pkg-16) (Ch. 30.11.2023 and at some 427.300 to Ch.452.420) [Major EPC Contractor has rectified 50 2024 locations the settlements bridge over Takli river near damages. R observed in approaches of Nayagaon Jageer village to structure Rajasthan/MP Border] Construction of proposed 2-lane Post-completion, structural ROB and its approaches in lieu of Contract has been defects have been observed in existing level crossing no. C-64 at terminated. ⁠ ⁠Debarment of 51 2024 the deck slab of the ROB due to km. 172.990 on Jodhpur–Ajmer contractor taken up. Bid for honeycombing caused by poor Road on NH-65 in District Nagaur rectification works invited. workmanship. Rajasthan Four Laning of NH-161 from Mangloor (Design Km 86.788 /existing Km 91.350 to At some locations Rutting and Penalty of of Rs.134.784 Telangana/Maharashtra Border Bleeding was observed in the Cr. imposed towards Breach of Telangana 52 2022 (Design Km 135.751/ Existing Km Project Highway during O&M maintenance obligations. 140.873) in the state of Telangana Period under Bharatmala Pariyojana on Hybrid Annuity Mode (Package-III) 3 Girders (G1, G2 & G3) between pier P4 & P5 at Km Contractor has replaced the girders 4-laning of Madurai - Chettikulam 53 2021 2+850 of down ramp collapsed at the said locations at his own section from Km 0.000 to Km 7.300. during fixing of the Bearing cost. during construction. In 2022: In 2022: A Segmental Girder on P16-A penalty amounting to Rs. 7.305 P17 of RHS Carriageway fell crore (being 0.5% of the BPC) had Tamil Nadu down due to failure of hydraulic been imposed and recovered from 4-laning of Sethiyathope - 2022 jacks at Km 107+400 Anaikarai the Concessionaire. 54 Cholpauram section from Km and Major Bridge across Kollidam The collapsed span has been 65.960 to Km 116.440 2025 river. reconstructed by the Concessionaire with their own cost. In 2025: The RE wall blocks portion of In 2025: the A2 (Thanjavur) side The rectification work completed byS. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects approach (LHS side) have been the Concessionaire at their own disconnected from the geo grid cost. and fallen down. The RE wall panel portion of the 4-laning of Thanjavur - Trichy A1 (Thanjavur) side approach Based on report of Expert 55 section from Km 80.000 to Km 2023 (LHS side) have been Committee, restoration work using 136.490 disconnected from the geo grid soil nailing completed by and fallen down. Contractor. Construction of 4 lane green field highway from km 35.00 to 49.155 of The project is under construction, NH-731A with paved shoulder on Cracks observed over DBM due the repair and rectification work 56 Hybrid Annuity Mode in the State of 2025 to percolation of rain water in Uttar taken up by the concessionaire at Uttar Pradesh. (Job No. CE-RO- some stretches. Pradesh its own cost. LKO/NH(O)/NH-731A/2021- 22/627 dt 05-01-2022) Cracks in PQC Panel in length Contractor has initiated process for 57 Lucknow Ring Road Pkg-3A 2024 of 2.886 Km. rectification of damages. Uttar 4L of Haridwar-Nagina section of Contractor has initiated process for Pradesh & 58 2023 PQC panel cracks NH-74 rectification of damages. Uttarakhand Construction, Operation and Maintenance of 2-Lane Bi- Rectification measures taken up by Directional Silkyara Bend Barkot the EPC contractors at its own Tunnel with escape passage Collapse at cavity in under cost. Uttarakhand 59 including approaches on Dharasu– 2023 construction Silkyara Tunnel. Yamunotri section between Ch. Actions as per the Investigation 25.400 Km and Ch. 51.000 Km Committee Report initiated. falling along NH-134 (OLD NH-94) in the state of Uttarakhand i) Rectification works initiated by Construction of 4-Laning of Puruliya Contractor. Amount of Rs. 20.00 Bypass Section from Km. 84.030 to Cracks have developed in the Lakh withheld from Contractor's bill. 60 Km. 94.345 of NH-32 (length 10.315 2025 newly constructed PQC. Km) in the State of West Bengal on ii) Key personal of AE has been EPC Mode debarred for a period of one year. West Bengal Four laning with paved shoulders of NH-6 from Chichra to Kharagpur Km 185.150 to Km 134.400 Repaired at the Risk and Cost of 61 2023 Cracks in PQC panels including rehabilitation of existing EPC Contractor. four lane from Km 134.400 to Km 129.600 in the state of West Bengal 1. Faulty Design in Bridge at 1. For Faulty Design at Km 96+326, km. 96+326: penalty imposed of Rs.30 Lakhs on Chandikhole-Bhadrak Section of Odisha 62 2023 the Concessionaire and Rs.5 Lakhs NH-16 2. Bridge at km. 79+614: on the Independent Engineer. The span A1-P1 had dislodged Team Leader of IE and KeyS. Year of Details of Major damages / State Name of the Project Action Taken No. incident defects from the pier P2 due to breaking Personnel of Concessionaire of the cantilever suspended. Portion of the pier cap and had fallen on the ground. 2. For Bridge at km. 79+614: Penalty of Rs.5 crore imposed on Appearance of wide cracks (up the Contractor and Penalty of to 3-4mm) in the pier cap on Rs.20 lakh imposed on the grid “P2”. Supervision Consultant. Damages of deck slab and Debarment of DPR Consultant for 1 girders of the dislodged span. year. The cost of entire remedial measures / reconstruction recovered from the Concessionaire. Completion of Balance Work Collapse of pier cap (P8) and Panikoili – Rimuli section of NH-215 girders (P8 – P9 Span) Balance Restoration work executed by (New NH-20) from Km.0.000 to work of Belabahali Major Bridge Contractor at his own Cost based 63 Km.163.000 (Design Chainage 2022 LHS at Km.35.341 which was on the recommendation of Expert Km0.000 to 166.173) in the state of under construction collapsed Committee constituted. Odisha in single percentage item during launching of girders. rate Contract Construction of 6-lane Standalone Flyovers at Bongaigaon, Chapaguri, Pathsala, Simlaguri Chowk and Falling of one PSC Girder at Baihata Junctions on stretches of Baihata Flyover (Span P1-P2), Penalty imposed on Contractor. Assam 64 2024 NH-31 & NH-31C [new NH-27 resulting in the death of one Contractor debarred for 4 months. (EW)] in the State of Assam under person. Bharatmala Pariyojana on EPC basis Rehabilitation of km 181.00 to Km 206.00 section in Andaman Trunk Road of NH-4 to Intermediate Lane Distress, sinking of pavement at 65 with hard shoulder in the union 2024 Rectification works completed. various locations. Territory of Andaman & Nicobar islands (Total length 25.00 km) on Andaman & EPC Mode” (Package-VII) Nicobar Construction of 4 Nos. of Minor Islands The EPC contractor has carried out Bridges at Km 21.717, Km 23.150, Punching in Deck Slab (LHS) of the necessary rectifications at their Km 88.300, Km 92.100 of NH- 223 the minor bridge across BD own expense including 66 (New NH-4) connecting South 2024 Nallah at Km 88+300 and other replacement of slab as Andaman and Baratang Island in quality issues including bad recommended by CRRI-CSIR the Union Territory of Andaman & workmanship. report. Nicobar Islands on EPC mode. *****

Continue your research