GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3271
ANSWERED ON 12TH MARCH, 2026
NATIONAL HIGHWAY PROJECTS IN MAHARASHTRA
†3271. SHRI BAJRANG MANOHAR SONWANE:
Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the current status of National Highway projects in the rural and
backward areas of Maharashtra and the district-wise details of
incomplete works;
(b) whether the condition of roads in Beed district and surrounding
areas is poor and if so, the action taken for their repair and sanction of
funds;
(c) the specific schemes being implemented by the Union Government
for the upgradation of rural roads and sanction of new routes and the
number of villages in Maharashtra that have benefited therefrom;
(d) the safety measures implemented by the Ministry to reduce
accidents on National Highways;
(e) the timeline fixed for completion of pending flyovers, bypasses and
widening projects; and
(f) whether some projects have been delayed due to lack of
coordination between the Union and State Governments, if so, the
arrangements made to ensure their timely completion?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)(a) 116 National Highway projects including rural and backward
areas covering a length of 2,612 km at an estimated cost of Rs. 57,360
cr. are under various stages of implementation in the State of
Maharashtra.
(b) The Government has prioritized the maintenance of existing NH
network and inter-alia evolved a mechanism to ensure Maintenance
and Repair (M&R) of all NHs sections through accountable
maintenance agencies.
NHs development projects are executed on mainly three modes
i.e. (i) Build Operate and Transfer (BOT), (ii) Hybrid Annuity Model
(HAM) and (iii) Engineering Procurement and Construction (EPC).
Concession period including maintenance for projects on Build
Operate and Transfer (BOT) is 15 to 20 years and on Hybrid Annuity
Model (HAM) is generally 15 years. The Concessionaire is responsible
for maintenance of the respective NHs stretches within the
concession period of the project. Only in case of EPC projects, Defect
Liability Period (DLP) is 5 years for the bituminous pavement works
and 10 years for concrete pavement works.
For Toll-Operate-Transfer (TOT) and InvIT (Infrastructure
Investment Trust) projects, concession period including maintenance
is 20 to 30 years. Concession period for Projects on Operate, Maintain
and Transfer (OMT) is generally 9 years.
For all remaining sections of NHs stretches, where DLP has
ended or is not under any concession period of BOT/HAM/TOT/InvIT
project, Government has taken a policy decision to undertake
maintenance works through Performance Based Maintenance Contract
(PBMC) or Short Term Maintenance Contract (STMC). While STMC
works are generally undertaken for a contract period of 1-2 year,
PBMC works are undertaken for a contract period of about 5-7 years.
The Government has sanctioned work having length 38 km and
costing Rs. 28.56 Crores under PBMC scheme and one work havinglength of 1.041km costing Rs. 0.73 Crores under STMC scheme for the
stretches not covered under DLP.
(c) The Government in the Ministry of Road Transport and Highways
is primarily responsible for development and maintenance of NHs. The
works for development of rural roads are sanctioned under Pradhan
Mantri Gram Sadak Yojana (PMGSY). As reported by the State
Government of Maharashtra, 804 projects costing Rs. 3442.23 crores
and covering 3540 km of road length and 213 number of bridges have
been sanctioned under PMGSY scheme in the last three years
including current year benefiting 8187 number of villages.
(d) Any accident that occurs on National Highways is notified on e-
DAR portal and detailed cause analysis of the accident is carried out
by technical consultants for taking necessary corrective measures for
reducing the Road accidents. Immediate short term measures such
road markings, signages, crash barriers, raised pavement markers,
delineators, closure of median openings, traffic calming measures,
etc., are provided for reducing the Road accidents. In addition to this,
long term rectification measures involving improvement of road
geometrics, junction improvements, spot widening of carriageway,
construction of underpasses/ overpasses etc. are also on implemented
based on the road safety audit of the accident spots.
(e) There have been delays in completion of some NH projects due
to existing Right Of Way (ROW) disputes, delays in land acquisition,
forest as well as wildlife clearances, delays in utility shifting and other
pre-construction activities as well as cash flow issues with some of
the Contractors and COVID-19 lockdown. All the pending issues of land
acquisition, forest clearances and utility shifting have been
substantially resolved in close co-ordination with the State
Government and the balance works are under implementation with
regular monitoring.
(f) In order to ensure timely completion of NH projects, the
Government has undertaken various initiatives. These include
streamlining and expediting land acquisition using “Bhoomirashi”portal and GIS-based Land Acquisition Plan, revamping “Parivesh”
Portal to facilitate faster forest and environmental clearances,
enabling online approval of General Arrangement Drawings (GAD) of
Road Over Bridge/Road Under Bridge (ROB/RUB) from the Railways,
and leveraging the mechanism of review and resolution of bottlenecks
/ hindrances in ongoing projects, in active collaboration with the State
Governments and other stakeholders. Railways has also launched a
web portal for Railway related clearances with defined timelines for
various approvals.
The Government has put in place a strong framework using
multiple mechanisms for monitoring project progress and contractor
inefficiencies. Regular review meetings are conducted at various
levels with stakeholders to assess project progress, and critical
projects, such as those delayed by more than three years or pending
for award / appointment.
Further, many State Governments conduct coordination meetings
led by the Chief Secretary to resolve issues affecting project
execution. Projects where issues remain unresolved are escalated for
further review through the Project Monitoring Group.
*****