Date: 2025-12-18 Category: Not Applicable State: Union Government Country: India

Parliament Question: National Highway Projects in Rajasthan

Issued by ROAD TRANSPORT AND HIGHWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document contains the answer to Unstarred Question No. 3172 in the Lok Sabha, answered on December 18, 2025, concerning National Highway (NH) projects in Rajasthan. The Minister of Road Transport and Highways addresses the status of delayed projects, bid invitations, and government measures for timely completion, referencing data up to the 2025 answering date. The Annexure lists state-wise details of the delayed projects, including their number and cost. **Key Points / Main Content** * **Delayed Projects:** * 643 under-construction National Highway projects, sanctioned and awarded since the Financial Year 2014-15, have exceeded their original completion schedule. * The total cost of these projects is approximately Rs. 4.13 lakh crore. * These figures exclude projects under consideration for termination or foreclosure. * **Projects with Bids Awarded but Construction Not Started:** * 158 National Highway projects, with a total cost of approximately Rs. 1.15 lakh crore, have been awarded but have not had appointed dates declared. * This delay is due to pending fulfilment of prerequisite conditions, including the availability of encumbrance-free land and necessary clearances. * **Government Measures:** * The Ministry of Road Transport & Highways is streamlining land acquisition through review and resolution mechanisms, collaborating with State Governments and stakeholders. * The Government is working to expedite clearances/approvals and the fulfillment of conditions precedent for new projects. * **Annexure:** * Contains state-wise details of the delayed National Highway projects, including the number of projects and their total cost. **Impact Analysis** **Ministry of Road Transport and Highways** * **Impact:** Responsible for addressing project delays and streamlining processes. * **Action Required:** Continue implementing measures to expedite land acquisition, resolve bottlenecks, and secure necessary clearances for both ongoing and new projects. **State Governments:** * **Impact:** Directly involved in facilitating land acquisition and obtaining clearances for National Highway projects within their respective states. * **Action Required:** Collaborate with the Ministry of Road Transport & Highways to resolve bottlenecks, expedite land acquisition, and ensure the timely provision of necessary clearances. **Contractors/Concessionaires:** * **Impact:** Affected by project delays due to land acquisition and clearance issues. * **Action Required:** Work with the Ministry of Road Transport & Highways and State Governments to address challenges related to land availability and clearances to enable project commencement and completion. **Citizens of India:** * **Impact:** Experience delays in the development of National Highway infrastructure, which can affect connectivity and economic growth. * **Action Required:** N/A

Key Entities Referenced

National Highway projects: The central subject of the document is the approval, status, and potential delays related to National Highway projects. Rajasthan: The primary geographic focus of the question and answer is National Highway projects within Rajasthan. Ministry of Road Transport and Highways: The government ministry responsible for the oversight and management of National Highway projects. Lok Sabha: The lower house of the Parliament of India, where the unstarred question regarding National Highway projects was raised.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 3172 ANSWERED ON 18TH DECEMBER, 2025 NATIONAL HIGHWAY PROJECTS IN RAJASTHAN †3172. SHRI MURARI LAL MEENA: Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) the number of approved National Highway projects in the last ten years in Rajasthan and across the country including Dausa which are currently delayed; (b) if so, the number and status, State-wise and project-wise along with the estimated cost thereof; (c) the number of National Highway projects for which bids were invited and received during the last ten years but construction is yet to begin and the reasons therefor; (d) whether the Government is taking any specific policy or corrective measures to ensure timely completion, check cost escalation and expedite the work on these delayed National Highway projects; and (e) whether the Government is preparing any action plan to restart and complete all pending or not yet started National Highway projects in a timely manner in Rajasthan including Dausa, if so, the details thereof? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI) (a) to (b) 643 under construction National Highways (NHs) projects with a total cost of about Rs. 4.13 lakh crore, which were sanctioned and subsequently awarded since the Financial Year 2014-15 onwards, have spilled beyond their original completion schedule as per contract, withoutattaining any of the various stages of project completion and excluding projects under consideration for termination / foreclosure. State-wise details of delayed projects are annexed. (c) 158 NH projects with total cost of about Rs. 1.15 lakh crore have been awarded but appointed date could not be declared pending fulfilment of prerequisite conditions, inter-alia, availability of encumbrance free land and clearances including forest and wildlife clearances excluding available time period with contractor/concessionaire for achievement of financial close and submission of bank guarantee. (d) and (e) The Government in the Ministry of Road Transport & Highways has taken various steps to streamline land acquisition process by leveraging the mechanism of review and resolution of bottlenecks / hindrances in ongoing projects, in active collaboration with the State Governments and other stakeholders. Further, Government is making full efforts to expedite the availability of necessary clearances / approvals and the fulfilment of conditions precedent for new projects.ANNEXURE ANNEXURE REFERRED TO IN REPLY TO PART (a) to (b) OF LOK SABHA UNSTARRED QUESTION NO. 3172 ANSWERED ON 18TH DECEMBER, 2025 ASKED BY SHRI MURARI LAL MEENA REGARDING NATIONAL HIGHWAY PROJECTS IN RAJASTHAN. Total State/ UT's No. Cost Andaman and Nicobar 5 1463 Andhra Pradesh 38 19947 Arunachal Pradesh 13 3857 Assam 24 9750 Bihar 33 28183 Chhattisgarh 13 4788 Dadra and Nagar Haveli And Daman and Diu 1 102 Delhi 1 1467 Goa 5 151 Gujarat 17 18539 Haryana 10 12871 Himachal Pradesh 14 7346 Jammu and Kashmir 30 26017 Jharkhand 18 13281 Karnataka 49 26738 Kerala 13 39161 Ladakh 4 1265 Madhya Pradesh 25 9183 Maharashtra 66 45120 Manipur 21 7071 Meghalaya 4 1120 Mizoram 7 2158 Nagaland 11 3404 Odisha 28 7616 Punjab 22 22527 Rajasthan 17 5561 Sikkim 9 3323 Tamil Nadu 21 21252 Telangana 28 15967 Tripura 5 986 Uttar Pradesh 48 37035 Uttarakhand 30 11442 West Bengal 13 4372 Grand Total 643 413064 *****