See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3256
ANSWERED ON 12TH MARCH, 2026
POOR QUALITY OF WORK DUE TO LOW BIDS
3256. COM. SELVARAJ V:
SHRI SUBBARAYAN K:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether there is a recent trend of road contractors quoting low bids of up
to forty-eight per cent less than the estimated project cost largely due to
aggressive bidding which usually has a direct bearing on the quality of work;
(b) whether it is a fact that a number of complaints have been reported
recently about the collapse of National Highways and flyovers under
construction particularly in Kerala; and
(c) if so, the details thereof and the action taken against the contractors in
these cases?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) Government engages contractors for project works implementation
through a transparent and competitive bidding process in accordance with
the prescribed procurement guidelines. In certain cases, bids have been
received at rates far lower than the estimated project cost put to tender,
primarily due to competitive market conditions and aggressive bidding
strategies adopted by the bidders.
To safeguard the interests of the Government and to ensure that quality
standards are not compromised, suitable provisions have been incorporated
in the bidding documents including requirement of Additional PerformanceSecurity. Further, all works are executed strictly in accordance with the
relevant codes/manuals prescribed. Independent Engineers/Authority
Engineers and regular field inspections ensure supervision and adherence to
quality standards at every stage of construction. Independent Quality Audit
is also taken up in certain projects where required. Accordingly, necessary
safeguards are in place to ensure that competitive bidding does not
adversely impact the quality of National Highway works.
(b) & (c) The details of complaints /failure since 1.01.2025 are annexed.ANNEXURE REFERRED TO IN REPLY TO PART (b) AND (C) OF LOK SABHA
UNSTARRED QUESTION NO. 3256 ANSWERED ON 12TH MARCH, 2026 ASKED BY
COM. SELVARAJ V AND SHRI SUBBARAYAN K REGARDING „POOR QUALITY OF
WORK DUE TO LOW BIDS‟.
Sl. Action taken against
NH Nature of Reason(s) of
No State Name of project contractor/
No. Complaint failure
. concessionaire
A monetary penalty
of Rs. 2.8 Cr. on the
Contractor along with
a recommendation for
debarment up to one
year or until
Ruts, cracks successful
Ruts, and surface rectification,
cracks and deformation/ whichever is later.
surface Distress was Contractor has taken
deformation observed up repair/ restoration
Sanchor - observed at recently after works.
754 Santalpur PKG-4 several rains in June
1 Gujarat
A of NH- 754A in locations on month 2025, Additionally, in view
Gujarat the project severe of public safety being
highway rutting at compromised, the
during some Contractor has been
constructio locations suspended from
n during the participating in any
under ongoing/future
Construction tenders for a period of
period one month or until full
compliance with
IRC/MoRTH standards
and contractual
provisions.VIP
Reference
regarding
the poor
“Strengthening / quality of
improvement work on NH-
including 6—
regular particularly
maintenance the stretch
work from Km at Kulang
120.200 to village. The
Poor Quality The rectification work
171.455 of the Hon‟ble MP
of overlaying have been carried out
project Two has
NH- leading to by the contractor.
Lane with paved highlighted
6 slippage of However, a penalty of
Meghalay shoulders that the
2 (old bituminous Rs. 20,00,000/- was
a configuration in tar/paveme
NH- concrete for imposed on the
Jowai- nt can be
44) a length of contractor for
Meghalaya removed by
approx. 10-15 tarnishing the image
Assam Border hand,
mt. found of NHAI.
Section of NH - indicating
44 from Km gross
69.200 to Km negligence,
173.200 (Design poor
Ch. 171.455 ) in execution,
the state of and the use
Meghalaya” of
substandar
d materials
by the
contractor.
1. Penalty of Rs.18.05
Lakh was imposed on
4-laning of
14.01.2026 over the
Sethiyathope -
Concessionaire M/s.
Tamil Cholapuram Earth Inadequate
Patel Infrastructure
3 36 Nadu section from km Retaining Geotechnical
Ltd.
(Madurai) 65.960 to Km Structures Investigation
2. Further, a Penalty
116.440 of NH-
of Rs.5.00 Lakh was
36
imposed on the IE,
M/s. Theme
Engineering ServicesPrivate Limited.
NHAI suspended the
Concessionaire and
its promoter M/s.
Megha Engineering &
Infrastructure ltd. to
participate in future
bidding for 01-month
period or till
Concessionaire
proposes remedial
measures including
rectification of
designs of slope
protection works with
proper geophysical/
geotechnical, studies
and demonstrate that
Shotcrete
such incidence will
thickness
not repeat at other
inadequate;
slope protection
nail spacing
locations in the
large;
project reach
Chengala-
4 66 Kerala Others anchorage
whichever is later.
Neeleshwaram
length
Further, Settlement
insufficient;
Agreement was
drainage
executed on
behind wall
19.02.2026 between
inadequate.
NHAI and
Concessionaire. As
per para 3.1.2 (b) of
SA-2, the
Concessionaire shall
be solely responsible
for slope protection
works and to
construct and rectify
the defective works
at its own risk & cost.
The Concessionaire/
Promoter self-
restrained themselves
from participating in
the bids of Authority/
Implementing
Agencies of MORTHtill date.
Concessionaire
agreed to pay 5% of
current value of failed
work as per Policy
Circular dt.06.10.2021
of MoRTH &
16.11.2021 of NHAI.
Concessionaire also
agreed to comply with
the recommendations
of Expert Group and
complete rectification
works at their own
cost.
Show Cause Notice
issued to
Concessionaire on
25.07.2025. Settleme
nt Agreement
executed on
19.02.2026 between
NHAI and
Concessionaire, as
per para 3.1.2 (b) of
SA-2, Concessionaire
shall be solely
responsible for slope
protection works to
construct and remedy
Neeleshwaram -
5 66 Kerala Others Slope failure
the defective works
Thaliparambha
at its own risk & cost.
The Concessionaire/
Promoter self-
restrained themselves
from participating in
the bids of Authority/
Implementing
Agencies of MoRTH
till date.
Concessionaire
agreed to pay 5% of
current value of failed
work as per Policy
Circular dt.06.10.2021
of MoRTH &16.11.2021 of NHAI.
Concessionaire also
agreed to comply with
the recommendations
of Expert Group and
complete rectification
works at their own
cost.
A Show Cause Notice
dated 31.07.2024 was
issued to
Concessionaire.
Further, another Show
Cause Notice dated
07.01.2026 was
issued to
Substandard
Concessionaire for
work
Azhiyur- other defaults. In
6 66 Kerala Others execution &
Vengalam response to the Show
poor
Cause Notice, the
workmanship
Concessionaire
submitted the reply
dated 21.01.2026.
Personal hearing was
given to
Concessionaire on
10.02.2026. Final
order is to be passed.
Debarment notice
issued to M/s. KNR
construction Ltd. for
debarment upto 1
year + penalty of 5%
RE wall
of Current value of
design
failed work or 0.5% of
inadequate
Earth
Contract value of
Ramanattukara- for saturated
7 66 Kerala Retaining
whole work
Valancherry soils; poor
Structures
whichever is
compaction;
more. Concessionaire
missing filter
& IE have approached
media.
Delhi High Court
against such action.
Viaduct is being
constructed
with contractor'sown expense of Rs 80
Cr.
Key personnel of
Contractor and AE
have been removed
Aroor to from the project work
Malfunctionin
8 66 Kerala Thuravoor Flyover and debarred for 3
g of jack
Thekku years. Expert
Committee's final
decision not yet
received.
NHAI, imposed a
penalty of Rs. 15.35
Lakhs for ensuring of
safe construction of
works and a deterrent
Delay in action in the interest
cross girder of the Authority and
Thuravoor to
9 66 Kerala Bridges casting and public for ensuring
Paravoor
lapse in the safe construction
execution. of the work. Two
officials of Contractor
and two officials of
Authority Engineer
have been terminated
from the site.
NH connectivity
Substandard
to ICTT at
work Penalty of Rs. 30.74
966 Vallarpadam
10 Kerala Others execution & Cr was imposed on
A from
poor the Contractor.
Kalamassery to
workmanship
Vallarpadam
Substandard
The Concessionaire
work
Kodugallur to has been penalized
11 66 Kerala Others execution &
Edapppally with a one-year
poor
debarment.
workmanship
Penalty of Rs. 9.55
Lakh has been
Kollam to Staging issue
imposed on
12 66 Kerala Kdambattukona Bridges & improper
Concessionaire and
m supervision
the Concessionaire
has terminated the
services of theirEngineer responsible.
Deep-Seated
Shear Failure The Concessionaire
Earth (Rotational has been debarred for
13 66 Retaining Slide); 01 month or till
Structures Bearing submission of
Capacity investigation report.
Failure.
Construction of
4-lane from
Manegaon to
NH-45, from
design Ch.
19.050 to
design Ch. Rs. 1 Cr. penalty
Staging issue
Madhya 39.180 imposed to EPC
14 45 Bridges and improper
Pradesh (Jabalpur Ring Contractor M/s NKC
supervision
Road, Pkg-2) Projects Pvt. Ltd.
under
Bharatmala
Pariyojana in
the State of
Madhya Pradesh
EPC Mode.
*****